Buc-ee's
- Jurisdiction
- El Paso County
- Applicant
- Vertex Consulting Services, LLC Nina Dossey
- County project manager
- Kylie Bagley
- Filed
- Aug 31, 2026
- Parcels
- 7102200016, 7102200017, 7102200019
- Map
-
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
- Area map
- See all Tri-Lakes projects on the map
- Source record
- El Paso County EDARP file
Documents (38)
PCM - Notice of Intent to Construct a Non-Juris. Water Impoundment Structure (proof of submittal)reviewSep 14, 2026
Comments Received Through Nov. 5additionalNov 5, 2026
The attached documents are not part of the official record for Project PPR2628. They have been included in the project file for reference purposes only and should not be considered as formal submissions or evidence within the project’s official record.
Agency review comments (34)
Colorado Department of Transportation - Pueblo Officereview 1Nov 5, 2026
Please refer to the attached letter for CDOT's comments regarding this development.
County Attorney - Waterreview 1Nov 3, 2026
Comments from the County Attorney's Office have been sent to the Project Manager via email.
Lori Seago
Sr. County Attorney
loriseago@elpasoco.com
PCD Project Managerreview 1Nov 3, 2026
Stormwater Management Plan Redlines
PCD Project Managerreview 1Nov 3, 2026
Stormwater Management Plan Checklist Redlines
PCD Project Managerreview 1Nov 3, 2026
PCM Operations & Maintenance (O&M) Manual Redlines
PCD Project Managerreview 1Nov 3, 2026
PCM Maintenance Agreement Redlines
PCD Project Managerreview 1Nov 3, 2026
Grading and Erosion Control Plan Redlines
PCD Project Managerreview 1Nov 3, 2026
Grading and Erosion Control Checklist Redlines
PCD Project Managerreview 1Nov 3, 2026
Financial Assurance Estimate Redlines
PCD Project Managerreview 1Nov 3, 2026
The planning department has comments on the following documents:
- Site development plan
- Landscape Plan
- Lighting plan
- Letter of Intent
- Elevation Plans
- Offsite Sewer
EPC DPW Development Services - Engineeringreview 1Nov 2, 2026
Development Services Engineering Review has provided initial comments on the following documents (to be uploaded by project manager):
- Application
- Letter of Intent
- Offsite Sewer Plans
- Construction Drawings
- Roadway Plans
- Site Development Plan
- Traffic Impact Study
- Grading & Erosion Control Plans
- Drainage Report
- Financial Assurance Estimate Form
-Geotech Report
CDOT Interchange Construction Plans were submitted for information only. These construction plans are reviewed and approved by CDOT.
With next submittal:
- Please provide legal description of parcel and a boundary closure.
- Construction Drawing & Roadway plan sets submitted were only a 60% plan set. Provide a 100% plan set on the next submittal per Development Services requirements.
- Please remove utility plans from Construction Drawing plan set and create stand alone Utility Construction Drawing plan set.
Due to the volume and nature of comments provided, as well as the incomplete submittal, expect to receive additional comments on the subsequent submittal. The next submittal will be treated as the 1st review.
Daniel Torres, P.E.
Danieltorres@elpasoco.com
&
Gilbert LaForce, P.E.
gilbertlaforce@elpasoco.com
PCD Project Managerreview 1Nov 2, 2026
Please provide information regarding the electrical and gas infrastructure to be extended to the site. Are significant infrastructure design and construction anticipated to serve the site? Please provide details so a determination can be made as to if the service extensions are subject to the Areas and Activities of State Interest, Appendix B of the Land Development Code.
Please provide correspondence identifying how the sewer force main & lift station for the off-site sewer is exempt from the Areas and Activities of State Interest, Appendix B of the Land Development Code
Please note the water system as depicted on the Site Development Plan intends to include: treatment system, pump station, above-ground 0.5 million-gallon water tank (all noted as not final on the review 1 plan set), and well utilizing approximately 25.47 acre-feet per year.
The Code, Section 8.4.7.7 (d) identifies 0.26 acre-feet per SFE ~> 250 SFE = 65 acre-feet annually plus 2.46 acre-feet annually per acre of landscape. It appears the use is less than 250SFE annually. A wastewater analysis was not provided; therefore, it is not known if the wastewater will exceed the 2000 gallons per day threshold identified below.
Please provide correspondence identifying how the water-related infrastructure is exempt from the Areas and Activities of State Interest, Appendix B of the Land Development Code
Please see Appendix B, Chapter 4 of the Code:
Article 1. - General Provisions
4.101. Designation of Activities of State Interest
Any activity wholly or partially within the unincorporated jurisdiction of El Paso County which falls within one or more of the following categories shall be considered to be site selection and construction of major new domestic water and sewage treatment systems and/or major extension of existing domestic water and sewage treatment systems, which activities are hereby designated as activities of state interest requiring a permit under these Regulations. No person may engage in construction, expansion, reoperation or other significant change in use of the following activities wholly or partially within unincorporated El Paso County without first obtaining a Permit pursuant to these Regulations.
(1)New water supply systems, new water treatment plants, or extensions of those systems or plants including water storage tanks, and line extensions that serve more than 250 single-family equivalents.
(2)Water service for commercial and/or industrial use equal to or greater than an amount equivalent to that in paragraph
(1) above.
(3)Domestic Sewage Systems. A project which is planned for or requires the creation of a major new sewage treatment system(s) or a major extension(s) of an existing sewage treatment system(s), which means any new collector sewer lines, return flow lines, pumping structure or treatment facilities proposed for:
(a)New wastewater treatment plants, extensions or expansions to existing plants, or individual sewage disposal systems (on-site wastewater treatment systems) that have an average flow of more than 2,000 gallons per day;
(b)Wastewater lift stations that pump wastewater from areas too low to drain into available sewers receiving an average flow of more than 2,000 gallons per day;
(c)Wastewater interceptors, as defined at Section 4.103;
(d)Service for commercial and/or industrial use that serves an equivalent of more than 250 single-family equivalents, and that is not served at the time of permit application.
(4)This designation does not include extensions of water or sewer lines for which construction plans have been or are subject to approval as part of a subdivision development under the LDC.
Reviewed by,
Kari Parsons, Principal Planner 719520-6306
EPC DPW Stormwaterreview 1Nov 1, 2026
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following documents (to be uploaded by the Project Manager):
- CDs
- Drainage Report
- ESQCP
- FAE
- GEC Plan
- GEC Checklist
- Landscape Plan
- PCM Applicability Form
- PCM Maintenance Agreement
- PCM O&M Manual
- SWMP
- SWMP Checklist
Please provide the following document upon resubmittal (the planner will need to send an upload request):
- PCM - MHFD Detention Calcs or SDI Form
Due to the construction drawings set being at a 60% design level, these comments are preliminary in nature and EPC DPW Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review.
Reviewed by:
Christina Prete, P.E.
Stormwater Manager
719.520.6877
ChristinaPrete@elpasoco.com
EPC DPW Road Impact Fee Administratorreview 1Oct 29, 2026
Thank you for the opportunity to review this project. Road Impact Fees are applicable. Road Impact Fees to be paid at time of building permit. General Commercial use category $5,498/1,000 sf.
Project fees based on 74,000 sq ft = $406,852.00.
Road impact fees will be applicable to future proposed EV charging stations. A COM/SDP application will be required.
Daniel Torres
Engineering Manager
El Paso County Department of Public Works
O: 719-520-6305 C: 719-2086783
danieltorres@elpasoco.com
Gilbert LaForce
Deputy County Engineer
El Paso County Department of Public Works
O: 719-520-7945 C: 719-331-7134
gilbertlaforce@elpasoco.com
Pikes Peak Regional Building Departmentreview 1Oct 29, 2026
Enumerations has the following comments:
1. The street name shown in numerous places for the street on the northern boundary of the project is incorrect. The correct street name is County Line Rd. Update the plan pages to show the correct street name.
2. All addressing for this project will be from Beacon Lite Rd.. The site plan shows numerous structures which will require separate addresses and building permits. Once the DP has been approved, provide Enumerations with a site plan showing all structures which will require a unique street address, such as the chlorination building, retaining walls over 4 feet, gas canopies, etc. for address assignment. Once the addresses have been assigned, they can be used to submit building plans for review/permit.
Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
Mountain View Electric Association, Inc.review 1Oct 22, 2026
See attached comment
EPC Parks Departmentreview 1Oct 22, 2026
The El Paso County Parks Department has reviewed this Site Development Plan project and has no objections. The 2022 Parks Master Plan shows no impacts to existing or proposed parks, trails, or open space.
Parks department staff will not have comments on this project.
Thank you!
Ashlyn Mathy
Parks Planner
Park Planning Division
El Paso County Parks Department
Office: 719.520.6978
Tri-Lakes-Monument Fire Protection Districtreview 1Oct 19, 2026
Please label the room used for the sprinkler Riser Room.
Please show where Fire Alarm Panel location will be
Please provide for a Fire Hydrant located at the entrance to the south, by the future EV Charging area
PCD Project Managerreview 1Oct 15, 2026
No further planning comments
US Army Corps of Engineersreview 1Oct 13, 2026
Our office is currently reviewing an approved jurisdictional determination (AJD) request by the applicant. The applicant should also contact CDPHE, Dredge and Fill Program. Our office has no further comments.
Timeline
- Nov 5, 2026Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
- Nov 3, 2026Request for Review Comments returned by County Attorney - Water
- Nov 3, 2026Submission request sent to Applicant
- Nov 3, 2026Request for Review Comments email sent for Project Buc-ee's for review by Colorado Geological Survey on behalf of Colorado Geological Survey
- Nov 3, 2026Request for Review Comments email sent for Project Buc-ee's for review by on behalf of Colorado Department of Public Health and Environment
- Nov 3, 2026Request for Review Comments email sent for Project Buc-ee's for review by Brendan Cicione on behalf of Colorado Department of Public Health and Environment
- Nov 3, 2026Submission request canceled
- Nov 3, 2026Submission request sent to Applicant
- Nov 3, 2026Request for Review Comments returned by PCD Project Manager
- Nov 2, 2026Request for Review Comments returned by EPC DPW Development Services - Engineering
- Nov 2, 2026Request for Review Comments returned by EPC DPW Stormwater
- Nov 2, 2026Request for Review Comments returned by PCD Project Manager
- Nov 2, 2026Request for Review Comments returned by PCD Project Manager
- Nov 2, 2026Request for Review Comments returned by PCD Project Manager
- Oct 29, 2026Request for Review Comments returned by EPC DPW Road Impact Fee Administrator
- Oct 29, 2026Request for Review Comments returned by Pikes Peak Regional Building Department
- Oct 22, 2026Request for Review Comments returned by Mountain View Electric Association, Inc.
- Oct 22, 2026Request for Review Comments returned by EPC Parks Department
- Oct 20, 2026Request for Review Comments email sent for Project Buc-ee's for review by Victoria Chavez on behalf of EPC DPW Road Impact Fee Administrator
- Oct 20, 2026Request for Review Comments email sent for Project Buc-ee's for review by Kristen Ibarra on behalf of EPC DPW Road Impact Fee Administrator
- Oct 20, 2026Request for Review Comments email sent for Project Buc-ee's for review by Raquel Mananno on behalf of EPC DPW Road Impact Fee Administrator
- Oct 20, 2026Request for Review Comments email resent for Project Buc-ee's for review by Kristen Ibarra on behalf of EPC DPW Road Impact Fee Administrator
- Oct 20, 2026Request for Review Comments returned by EPC DPW Road Impact Fee Administrator
- Oct 19, 2026Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
- Oct 19, 2026Submission Triaged
- Oct 15, 2026Submission received from Applicant
- Oct 15, 2026Request for Review Comments returned by PCD Project Manager
- Oct 15, 2026Submission request sent to Applicant
- Oct 13, 2026First appeared on the EDARP active list
- Oct 13, 2026Request for Review Comments returned by US Army Corps of Engineers
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Scott Benson on behalf of Tri-Lakes-Monument Fire Protection District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Aaron Wood on behalf of Tri-Lakes-Monument Fire Protection District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by on behalf of Town of Monument Planning
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by on behalf of Pikes Peak Regional Building Department
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by William Vogl on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Harry Thomas on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Katie Miller on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Mariah Hudson on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Douglas County on behalf of Douglas County Planning
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Daniel Delgado on behalf of US Army Corps of Engineers
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Michael Wicklund on behalf of Monument Sanitation District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Vicki Wood on behalf of Lewis Palmer School District 38
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Melissa Andrews on behalf of Lewis Palmer School District 38
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Brett Ridgway on behalf of Lewis Palmer School District 38
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by General Email on behalf of Mountain View Electric Association, Inc.
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by on behalf of EPC Parks Department
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Catherine McGarvy on behalf of EPC Health Department
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by HEAEH LandUse on behalf of EPC Health Department
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Glenn Reese on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Erica Rylander on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Christina Prete on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Victoria Chavez on behalf of EPC DPW Road Impact Fee Administrator
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Raquel Mananno on behalf of EPC DPW Road Impact Fee Administrator
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Kristen Ibarra on behalf of EPC DPW Road Impact Fee Administrator
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Lori Seago on behalf of County Attorney - Water
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Erika Keech on behalf of County Attorney - Water
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by April Willie on behalf of County Attorney - Water
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Justin Kilgore on behalf of PCD Project Manager
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Scott Benson on behalf of Tri-Lakes-Monument Fire Protection District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Aaron Wood on behalf of Tri-Lakes-Monument Fire Protection District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by on behalf of Town of Monument Planning
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by on behalf of Pikes Peak Regional Building Department
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by William Vogl on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Harry Thomas on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Katie Miller on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Mariah Hudson on behalf of El Paso County Conservation Dist
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Douglas County on behalf of Douglas County Planning
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Daniel Delgado on behalf of US Army Corps of Engineers
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Michael Wicklund on behalf of Monument Sanitation District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Chester Sawyer on behalf of Misty Acres Metro District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Andrew Bussa on behalf of Misty Acres Metro District
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Vicki Wood on behalf of Lewis Palmer School District 38
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Melissa Andrews on behalf of Lewis Palmer School District 38
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Brett Ridgway on behalf of Lewis Palmer School District 38
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by General Email on behalf of Mountain View Electric Association, Inc.
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by on behalf of EPC Parks Department
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Catherine McGarvy on behalf of EPC Health Department
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by HEAEH LandUse on behalf of EPC Health Department
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Erica Rylander on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Glenn Reese on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Christina Prete on behalf of EPC DPW Stormwater
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Victoria Chavez on behalf of EPC DPW Road Impact Fee Administrator
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Raquel Mananno on behalf of EPC DPW Road Impact Fee Administrator
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Kristen Ibarra on behalf of EPC DPW Road Impact Fee Administrator
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Lori Seago on behalf of County Attorney - Water
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Erika Keech on behalf of County Attorney - Water
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by April Willie on behalf of County Attorney - Water
- Oct 12, 2026Request for Review Comments email sent for Project Buc-ee's for review by Justin Kilgore on behalf of PCD Project Manager
- Oct 12, 2026Project Manager Assigned: Kylie Bagley
- Oct 12, 2026Fees paid: 10/12/2026 (Receipt: 1012757)
- Oct 12, 2026Payment Request sent: 10/12/2026
- Oct 12, 2026File # Assigned: PPR2628
- Oct 12, 2026Submission Triaged
- Oct 12, 2026Submission received from Applicant
- Oct 12, 2026Submission request sent to Applicant
- Oct 12, 2026Submission Triaged
- Oct 12, 2026Submission received from Applicant
- Sep 16, 2026Submission request sent to Applicant
- Sep 16, 2026Submission request sent to Applicant
- Sep 16, 2026Submission request canceled
- Sep 14, 2026Submission request sent to Applicant
- Sep 14, 2026Submission request canceled
- Sep 14, 2026Submission request sent to Applicant
- Aug 31, 2026Submission request sent to Applicant
- Aug 31, 2026Project Created