Calm Breeze Pt Subdivision
4 lot subdivision
- Location
- 12650 CALM BREEZE PT, 80908
- Jurisdiction
- El Paso County
- Applicant
- M&S Civil Consultants, Inc. Virgil Sanchez
- Land owner (assessor)
- AMMONS CALLIE & AMMONS KRAMER
- County project manager
- Jen Uhler
- Filed
- Oct 30, 2025
- Parcel
- 5211000013
- Map
-
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
- Area map
- See all Tri-Lakes projects on the map
- Source record
- El Paso County EDARP file
Documents (28)
Neighbor Notice & Vicinity MapadditionalJul 16, 2026
Notice of Application letters were mailed to surrounding property owners on 07/16/2026. JM
Mailing LabelsadditionalJul 16, 2026
Mailing Labels for the 14 surrounding property owners that received notices. Cost = $10.36. JM
Agency review comments (31)
Black Forest Land Use Committeereview 1Aug 6, 2026
The Black Forest Land Use Committee has reviewed this proposal and recommends denial for two reasons.
1. Approval would add these homes as well as many potential new homes to a long cul-de-sac that has only one exit. The LDC limits cul-de-sacs to 25 homes. Looking at past BoCC decisions, the flawed reasoning in the Hay Creek Road decision must not be used again. The LDC limit is for a total of 25 homes, not only to homes fronting on the road. Applying the rationale for the Hay Creek Road decision, there could be 1000 homes along Hay Creek Road and still meet the LDC rule as long as no more than 25 homes "fronted" on the road. The potential for loss of life in a fire on cul-de-sacs like this one dictates that the number of homes must be limited.
2. The Seclusion subdivision has already been subdivided into large parcels of 35-40 acres. Developers should not be permitted to further subdivide such parcels because the people who purchased these parcels purchased them with the understanding that they would not be further subdivided. Most recently the BoCC approved the division of the Welsch property from 5 to two 2.5 acre lots, This doubles the density and changes the character of the development. A past BoCC decision to deny division of a 5-acre lot into two 2.5-acre lots in the Overlook Estates development near the Discovery Canyon school campus acknowledged that the owners in that subdivision purchased lots with the understanding that the 5-acre lots would remain that size. The rights and expectations of existing property owners must be a strong consideration in decisions such as this.
PCD Project Managerreview 1Jul 29, 2026
water resources report with summary
PCD Project Managerreview 1Jul 29, 2026
Letter of intent comments with summary
PCD Project Managerreview 1Jul 29, 2026
Planning has reviewed the proposal and has comments on the following documents
- Water Resources Report
- Letter of Intent
- Final Plat Drawings
- Legal Description
Jen Uhler
PCD Planner
719-520-7952
jenuhler@elpasoco.com
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
Traffic Memo comments
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
SIA comments
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
PCM Applicability Form comments
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
Letter of Intent comments
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
FAE comments
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
Final Plat comments
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
Drainage Report comments
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
Deviation Request comments
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
Construction Drawings comments
EPC DPW Development Services - Engineeringreview 1Jul 27, 2026
Review 1.
Engineering comments on the following documents:
- Letter of Intent
- Final Plat Drawing
- Final Drainage Report
- Deviation Request
- Construction Drawings
- Financial Assurance Estimate
- Traffic Memo
- Subdivision Improvement Agreement
Reviewed by:
Joe Sandstrom, EIT, CFM
Associate Engineer
Department of Public Works
O: 719-520-6314
M: 719-505-0516
josephsandstrom@elpasoco.com
County Attorney - Development Reviewreview 1Jul 27, 2026
See attached edits to Subdivision Improvements Agreement. No additional comments from County Attorney - Development Review at this time.
Reviewed by: Erika Keech, Sr. County Attorney, erikakeech2@elpasoco.com.
Colorado Geological Surveyreview 1Jul 27, 2026
The available referral documents include a Soils and Geology Study prepared by Entech Engineering, Inc. (Entech), dated May 29, 2026. As stated on page 9 of the report, “No significant geologic hazards were identified on the site; however, the following constraints have been identified on the site: artificial fill, potentially expansive soils, potentially shallow and seasonally shallow groundwater areas, drainage areas, downslope creep, potentially unstable slopes, and the potential for elevated radon levels.” Entech also identifies possible soil-erosion hazards and describes the site soils as moderately susceptible to erosion.
Note 17 of the Final Plat prepared by M&S Civil Consultants, Inc., dated June 11, 2026, generally identifies the geologic constraints described in the Entech report. However, the note does not identify the specific lots affected by each constraint, include soil erosion as a geologic constraint, or provide the applicable mitigation measures.
According to the National Flood Insurance Program (NFIP) Flood Insurance Rate Map (FIRM) Panel 08041C0320G, effective December 7, 2018, portions of the subject property are located within the Zone A 100-year floodplain. The Entech report also identifies potentially unstable creek-bank slopes associated with Black Squirrel Creek and localized areas of potentially shallow or seasonally shallow groundwater. These constraints can generally be addressed through implementation of the report's recommendations.
Potential building sites are shown in Entech's report. Lots 1 and 3 contain mapped geologic constraints, including downslope creep and potentially shallow or seasonally shallow groundwater. CGS recommends that the Final Plat identify all mapped geologic hazards and constraints, including soil erosion; specify the lots affected by each condition; and include the applicable avoidance or mitigation measures. At a minimum, the plat should clearly document the constraints and mitigation requirements applicable to Lots 1 and 3.
Submitted 7/27/2026 by Amy Crandall, Engineering Geologist, Colorado Geological Survey (303-384-2632 or acrandall@mines.edu)
County Attorney - Waterreview 1Jul 24, 2026
Please address the chain of title. 462-BD was issued to John Phillips. The deed we are provided is from Seclusion Development to the Ammons. Can you please upload information showing the gap between Phillips and Seclusion Development please. Once water quality testing pursuant to 8.4.7.B10(a) has been uploaded, as well as a letter from the Colorado Division of Water Resources finding adequate water, the County Attorney’s Office will begin review.
EPC DPW Stormwaterreview 1Jul 22, 2026
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s):
- Drainage Report
- Final Plat Drawing
- PCM Applicability Form
Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
EPC Parks Departmentreview 1Jul 22, 2026
El Paso County Parks staff has reviewed the Calm Breeze Point Subdivision application and has attached our review packet.
Thank you!
Ashlyn Mathy
Parks Planner
Park Planning Division
El Paso County Parks Department
Office 719.520.6978
RBD Floodplainreview 1Jul 22, 2026
plat note 2 should read
FLOOD PLAIN CERTIFICATION
According to the National Flood Insurance Program, Flood Insurance Rate Map Panel 08041C05320G with an effective date of December 7, 2018, the subject property is located in Zone A 100 year floodplain. Draft model backed BFEs and floodplain extents for this area have been developed as part of Phase 1 for the ongoing El Paso County, CO, Risk MAP Project”. The data has been reviewed and approved through FEMA’s QA/QC process (May 11, 2022) and is currently in the MIP (Case No. 19-08-0037s). The Phase 1/Base Level Engineering outputs and Zone A ready deliverables are, under the following folder: K:/FY2019/19-08-0037S/Discovery - BLE - El Paso and Teller Counties, CO - FY18 - 04/Discovery Data Capture - Discovery Data Capture - El Paso and Teller Counties, CO - 01/El Paso_Discovery_1. Floodplain extents shown hereon include both current effective and CWCB Phase 1 data. Floodplain Base Flood Elevations (BFEs) shown are derived via the FEMA approved contour interpolation method in conjunction with the BLE approved extents.
Pikes Peak Regional Building Departmentreview 1Jul 17, 2026
1. Add the street name Calm Breeze Point to page 2 in the right of way.
2. Lot 1 address is 12591, lot 2-12590, lot 3-12530 and lot 4-12650 Calm Breeze Point. Add these addresses to the lots. Each address should be running parallel to the street they are being addressed from. Addressing should be as close to the edge of the lot as possible. This indicates and is made clear to anyone looking at the plat, which street the lot is addressed from.
3. Standard plat comments:
a. Enumerations will review the pre-plat (mylar) prior to plat for address placement, street names, and title block.
b. A $10.00 per lot and tract platting fee will be due at the time of the review of the pre-plat, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. As of December 5th 2023, the fee for all credit/debit cards has changed from the flat 2.95% fee to the following: Over the phone Credit/Debit Card payments will be 2.3% and In-Person Debit Card payments will be 1.5% (in-person only). Paid directly to the Enumerations Department.
c. Pre-plat reviews can be reviewed via “pdf” or in-person. The pre-plat will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations stamping the pre-plat and receiving payment of plat fees. If any pre-plat changes occur, even if changes do not apply to Enumerations, we still need to re-stamp the pre-plat. The Enumerations stamped pre-plat copy should match the recorded document minus a few signatures. If you would like an in-person review, please make an appointment on our website, https://www.pprbd.org/Home/BookAppt
d. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Please email the Enumerations staff member that reviewed your project. Amy@pprbd.org; Brent@pprbd.org; or BeckyA@pprbd.org
Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
PCD Administrative Noticereview 1Jul 16, 2026
On 07/16/2026, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (14 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $10.36. JM
Black Forest Fire Protection Districtreview 1Jul 14, 2026
Black Forest Fire Rescue has reviewed the submitted Final Plat, Letter of Intent, Street Improvement Plans, Traffic Memorandum, Water Supply Information Summary, and supporting documentation for Calm Breeze Filing No. 1.
The proposed subdivision will be accessed by an existing private gravel roadway known as Calm Breeze Point. The plans indicate the roadway consists of an approximately 20-foot-wide gravel driving surface within a 32-foot access easement and will ultimately provide access to seven residential parcels. While the roadway is requesting an Engineering Criteria Manual deviation from County roadway standards, all fire apparatus access roads shall comply with the currently adopted 2021 International Fire Code, Section 503, and Black Forest Fire Rescue standards. This includes maintaining a minimum unobstructed width of 20 feet, adequate vertical clearance, an all-weather driving surface capable of supporting the imposed loads of fire apparatus, and sufficient turning radii for emergency vehicles. The applicant shall verify that all existing culverts, bridges, and roadway improvements are designed to support the weight of Black Forest Fire Rescue apparatus, including water tenders.
The plans also indicate that Calm Breeze Point is gated. However, the submitted documents do not identify how emergency responders will gain access to the subdivision. Prior to final approval, the applicant shall provide an emergency access plan for review and approval by Black Forest Fire Rescue. The gate shall comply with IFC Section 503.6 and include an approved Knox emergency access system or other fire department-approved emergency access method. Gate operation during power failure, minimum clear opening width, and emergency override features shall also be submitted for review.
The applicant shall submit a **Fire Water Supply Plan** for review and approval by the Black Forest Fire Rescue Authority Having Jurisdiction (AHJ). The current submittal identifies only domestic wells and does not demonstrate compliance with the district's fire protection water supply requirements. The Fire Water Supply Plan shall identify the proposed method of providing fire protection water, whether by an approved fire cistern, pressurized fire hydrant system, or another fire department-approved water supply. The plan shall include all required fire flow calculations, available water volume, fire department connection details, apparatus access, maintenance responsibilities, and any supporting hydraulic or engineering information necessary to demonstrate compliance with the adopted 2021 International Fire Code, applicable appendices, and Black Forest Fire Rescue standards. Approval of the subdivision is contingent upon review and acceptance of the proposed fire water supply by the Black Forest Fire Rescue AHJ.
Future residential development within the subdivision shall comply with all applicable provisions of the 2021 International Fire Code, the adopted Colorado Wildland-Urban Interface Code, and Black Forest Fire Rescue standards. Individual driveways, addressing, emergency access, and defensible space requirements will be reviewed during the building permit process. Roadway signage, address identification, and emergency vehicle access shall be maintained in accordance with district requirements.
Based on the information submitted, Black Forest Fire Rescue has no objection to the proposed subdivision **provided the above conditions are satisfied** prior to final approval. Final approval is contingent upon demonstrating compliant emergency vehicle access, approved emergency gate access, and an approved Fire Water Supply Plan accepted by the Black Forest Fire Rescue Authority Having Jurisdiction.
Colorado Springs Planning & Community Developmentreview 1Jul 12, 2026
City Planning has no comment.
911 Authority - El Paso/Teller Countyreview 1Jul 9, 2026
Calm Breeze Pt – Previously approved - Existing private roadway
No action for E911 on this submittal.
Thank you
Justin
Upper Black Squirrel Creek GWMDreview 1Jul 8, 2026
The Upper Black Squirrel Creek GWMD does not have any comments at this time but does respectfully reserve the right to comment on any future submittals.
Academy School District 20 Building Fundreview 1Jul 6, 2026
Academy District 20 is in receipt of File #SF2614 for approval of the Calm Breeze Pt Subdivision. The District is requesting fees in lieu of land dedication per the existing County Code for all residential units within this development.
The District is able to serve each student who is a resident of District 20.
If you need additional information, please contact me.
Peter Ristig
Executive Director for Operations
Academy School District
peter.ristig@asd20.org
Land ownership timeline
- Nov 25, 2024Parcel 5211000013 acquired by AMMONS CALLIE & AMMONS KRAMER — no sale price recorded, often a non-market transfer such as a deed into a related entity (assessor record)
Timeline
- Aug 6, 2026Request for Review Comments returned by Black Forest Land Use Committee
- Aug 4, 2026Request for Review Comments email resent for Project Calm Breeze Pt Subdivision for review by Terry Stokka on behalf of Black Forest Land Use Committee
- Jul 29, 2026Submission request sent to Applicant
- Jul 29, 2026Request for Review Comments returned by PCD Project Manager
- Jul 27, 2026Request for Review Comments returned by EPC DPW Development Services - Engineering
- Jul 27, 2026Request for Review Comments returned by County Attorney - Development Review
- Jul 27, 2026Request for Review Comments returned by EPC DPW Stormwater
- Jul 27, 2026Request for Review Comments returned by Colorado Geological Survey
- Jul 26, 2026Request for Review Comments returned by Black Forest Land Use Committee
- Jul 24, 2026Request for Review Comments returned by County Attorney - Water
- Jul 22, 2026Request for Review Comments returned by EPC Parks Department
- Jul 22, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Jul 22, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Jul 22, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Jul 22, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Trish Riber on behalf of Black Hills Energy-Aquila
- Jul 22, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
- Jul 22, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Bob Swatek on behalf of Black Hills Energy-Aquila
- Jul 22, 2026Request for Review Comments returned by RBD Floodplain
- Jul 22, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Keith Curtis on behalf of RBD Floodplain
- Jul 17, 2026Request for Review Comments returned by Pikes Peak Regional Building Department
- Jul 16, 2026Request for Review Comments returned by PCD Administrative Notice
- Jul 14, 2026Request for Review Comments returned by Black Forest Fire Protection District
- Jul 12, 2026Request for Review Comments returned by Colorado Springs Planning & Community Development
- Jul 10, 2026Request for Review Comments returned by Colorado Parks and Wildlife
- Jul 9, 2026Request for Review Comments returned by EPC Environmental Services
- Jul 9, 2026Request for Review Comments returned by 911 Authority - El Paso/Teller County
- Jul 8, 2026Request for Review Comments returned by Upper Black Squirrel Creek GWMD
- Jul 6, 2026Request for Review Comments returned by Academy School District 20 Building Fund
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Drew Foxx on behalf of Colorado Springs Planning & Community Development
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Allison Stocker on behalf of Colorado Springs Planning & Community Development
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Alexander Painter on behalf of Colorado Springs Planning & Community Development
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by on behalf of Pikes Peak Regional Building Department
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Cheryl Pixley on behalf of Black Forest Trails Association
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Terry Stokka on behalf of Black Forest Land Use Committee
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Terry Stokka on behalf of Black Forest Land Use Committee
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Victoria Poulton on behalf of Colorado Parks and Wildlife
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Travis Sauder on behalf of Colorado Parks and Wildlife
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Peter Chapman on behalf of Colorado Parks and Wildlife
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Tim Kroening on behalf of Colorado Parks and Wildlife
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Karen Voltura on behalf of Colorado Parks and Wildlife
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Colorado Geological Survey on behalf of Colorado Geological Survey
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Mike Matz on behalf of Colorado Division of Water Resources
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Tony Cerrone on behalf of Black Forest Fire Protection District
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Rachel Dunn on behalf of Black Forest Fire Protection District
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Michael Alvarado on behalf of Black Forest Fire Protection District
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by on behalf of Black Forest Fire Protection District
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Fielding Lucas on behalf of Black Forest Fire Protection District
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Cody Poole on behalf of Black Forest Fire Protection District
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Chad Herdt on behalf of Black Forest Fire Protection District
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Becky Allan on behalf of Academy School District 20 Building Fund
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Peter Ristig on behalf of Academy School District 20 Building Fund
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by on behalf of EPC Parks Department
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Catherine McGarvy on behalf of EPC Health Department
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by HEAEH LandUse on behalf of EPC Health Department
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Kathy Andrew on behalf of EPC Environmental Services
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Glenn Reese on behalf of EPC DPW Stormwater
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Erica Rylander on behalf of EPC DPW Stormwater
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Christina Prete on behalf of EPC DPW Stormwater
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Lori Seago on behalf of County Attorney - Water
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Erika Keech on behalf of County Attorney - Water
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by April Willie on behalf of County Attorney - Water
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Lori Seago on behalf of County Attorney - Development Review
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Erika Keech on behalf of County Attorney - Development Review
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by April Willie on behalf of County Attorney - Development Review
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by Justin Kilgore on behalf of PCD Project Manager
- Jul 6, 2026Request for Review Comments email sent for Project Calm Breeze Pt Subdivision for review by on behalf of PCD Administrative Notice
- Jul 6, 2026Project Manager Assigned: Jen Uhler
- Jun 27, 2026Fees paid: 6/27/2026 (Receipt: 1012251)
- Jun 12, 2026Payment Request sent: 6/12/2026
- Jun 12, 2026File # Assigned: SF2614
- Jun 12, 2026Submission Triaged
- Jun 12, 2026Submission received from Applicant
- Jun 1, 2026Project Manager Assigned: Justin Kilgore
- Mar 24, 2026Submission request sent to Applicant
- Feb 19, 2026Submission request sent to Applicant
- Feb 19, 2026Set Applicant to M&S Civil Consultants, Inc.
- Nov 4, 2025Submission request sent to Applicant
- Oct 30, 2025Project Manager Assigned: Maria Lancto
- Oct 30, 2025Project Created
- Oct 30, 2025EA Assigned: EA25119