David Weekley Homes at Flying Horse North F4
- Jurisdiction
- El Paso County
- Applicant
- David Weekley Homes Alicia Petz
- County project manager
- Stormwater Mikayla Hartford
- Filed
- Jun 29, 2026
- Source record
- El Paso County EDARP file
Documents (10)
Agency review comments (7)
EPC DPW Stormwaterreview 3Aug 20, 2026
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document:
- GEC Plan
Reviewed by:
Mikayla Hartford, P.E.
Senior Engineer - Stormwater
719.339.5053
MikaylaHartford@elpasoco.com
EPC DPW Stormwaterreview 2Jul 21, 2026
Review 2: EPC DPW Stormwater comments have been resolved on the following documents:
- AESQCP Form
- GEC Plan
All EPC DPW Stormwater comments have been addressed.
Reviewed by:
Mikayla Hartford, P.E.
Senior Engineer - Stormwater
719.339.5053
MikaylaHartford@elpasoco.com
EPC DPW Stormwaterreview 1Jul 1, 2026
Review 1: Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- AESQCP Form
- GEC Plan
Reviewed by:
Mikayla Hartford, P.E.
Senior Engineer - Stormwater
719.339.5053
MikaylaHartford@elpasoco.com
Timeline
- Aug 28, 2026Left the EDARP active list (approved, withdrawn, or closed)
- Aug 20, 2026Submission request sent to Applicant
- Aug 20, 2026Request for Review Comments returned by EPC DPW Stormwater
- Aug 19, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Aug 19, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Aug 19, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Glenn Reese on behalf of EPC DPW Stormwater
- Aug 19, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Erica Rylander on behalf of EPC DPW Stormwater
- Aug 19, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Christina Prete on behalf of EPC DPW Stormwater
- Aug 19, 2026Submission Triaged
- Aug 19, 2026Submission received from Applicant
- Aug 13, 2026First appeared on the EDARP active list
- Aug 13, 2026Submission request sent to Applicant
- Aug 13, 2026Project reopened for Review Comments
- Jul 21, 2026Project Approved: 7/21/2026
- Jul 21, 2026Project Closed
- Jul 21, 2026Request for Review Comments returned by EPC DPW Stormwater
- Jul 15, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Jul 15, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Jul 15, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Glenn Reese on behalf of EPC DPW Stormwater
- Jul 15, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Erica Rylander on behalf of EPC DPW Stormwater
- Jul 15, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Christina Prete on behalf of EPC DPW Stormwater
- Jul 15, 2026Submission Triaged
- Jul 14, 2026Submission received from Applicant
- Jul 1, 2026Submission request sent to Applicant
- Jul 1, 2026Request for Review Comments returned by EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Glenn Reese on behalf of EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Erica Rylander on behalf of EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project David Weekley Homes at Flying Horse North F4 for review by Christina Prete on behalf of EPC DPW Stormwater
- Jun 30, 2026Submission Triaged
- Jun 30, 2026Submission received from Applicant
- Jun 29, 2026Submission request sent to Applicant
- Jun 29, 2026Project Created. Parent Project: Flying Horse North Filing No. 4 (ESQ258)
- Jun 29, 2026Project Manager Assigned: Stormwater Mikayla Hartford
- Jun 29, 2026File # Assigned: ASQ2659
- Jun 29, 2026No Fees