Deim Subdivision Plat
4 lot subdivision Floodplain/Floodway; no public roads
- Location
- SUNDANCE RANCH LN, 80908
- Jurisdiction
- El Paso County
- Applicant
- Vertex Consulting Services Nina Ruiz
- Land owner (assessor)
- DEIM CONNIE & DIEM JOSH
- County project manager
- Kari Parsons
- Filed
- Oct 21, 2024
- Parcel
- 5100000509
- Map
-
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
- Area map
- See all Tri-Lakes projects on the map
- Source record
- El Paso County EDARP file
Documents (58)
Mailing LabelsadditionalMay 1, 2025
Mailing Labels for the 9 surrounding property owners that received notices. Cost = $6.21. JM
Neighbor Notice & Vicinity MapadditionalMay 1, 2025
Notice of Application letters were mailed to surrounding property owners on 04/30/2025. JM
Agency review comments (66)
PCD Project Managerreview 3Dec 5, 2025
Final Plat comments remain.
PCD Engineering Divisionreview 3Dec 5, 2025
DPW Engineering Comments review 3 has comments on the following documents:
- Letter of Intent
- Final Plat
- FDR
- Closure sheet
- Deviation request - Culvert
Also needed:
- Deviation request for roadway (required to document that the road does not meet ECM standard)
Comments have been resolved on the following:
- Traffic memo
Reviewed by:
Bret Dilts, PE
BretDilts@elpasoco.com
719-520-6864
PCD Project Managerreview 3Dec 4, 2025
In the first 2 submittals, the notes identified a maintenance Plan for the 3 private road access points, of which 2 traverse outside subdivision property and covenants will not extend to those points. Provide the plan for improvements to 3 roads and O and M.
It has been removed with this submittal, but the Code requires one. Staff has been awaiting the plan with the resubmittals for review, providing the applicant time to craft one.
6.2.8. Maintenance Plans
(A)General. (1)Purpose. Maintenance plans are intended to provide for the long term maintenance and care of roads, common areas, recreational and park areas or facilities, open space, bikeways, trails, paths, malls, parking areas, sanitation facilities, common sewerage or water system, permanent BMPs, or private detention ponds where responsibility for operation and maintenance is shared by 2 or more dwelling units, ownerships, businesses, or uses, or any other similar facility.(2)Applicability. An applicant for a development which includes non-governmental maintenance and care of roads, common areas, recreational and park areas, or facilities, open space, bikeways, trails, paths, malls, parking areas, sanitation facilities, common sewerage or water system by 2 or more dwelling units or uses, private detention ponds, permanent BMPs, or any other similar type of facility and tracts that are not building sites, is responsible for preparing a maintenance plan as part of the development application for the project.(B)Standards. Maintenance plans shall meet the following requirements:(1)Address All Required Elements. The maintenance plan shall address all the required elements that will not be maintained by a governmental or quasi-governmental agency.(2)Best Available Maintenance Practices. The maintenance plan shall provide for best available practices to maintain the lot, parcel, or tract for the use specified in the maintenance plan.(3)Mechanism for Adequate Maintenance Funding. An individual or organization shall be designated to provide an adequate funding mechanism to ensure maintenance and annual monitoring of the lot, parcel, or tract for the life of the project.(4)County Informed of Responsible Party. An adequate mechanism shall be included in the maintenance plan to keep the County informed of any changes in ownership or responsibility for the maintenance of the lot, parcel, or tract.(5)Contingency Plan. An adequate contingency plan shall be provide for the long term maintenance of the site if irrigation water is removed from the site or the use of the site changes significantly.(C)Recording Maintenance Plans. All BMP Maintenance Plans shall be recorded in the records of the El Paso County Clerk and Recorder's Office.
Pikes Peak Regional Building Departmentreview 3Dec 4, 2025
1. Due to the new subdivision in this area, it is required that the developer communicate with surrounding property owners, specifically the residences at 6155 Hodgen Rd and 5975 Hodgen Rd., and officially notify them that their addresses will need to change. It is very important that this proposed project does not catch the surrounding property owners unaware that their addresses will be changing.
2. Confirmation of support from the property owners who will need an address change as a result of this development is required before Enumerations will support or approve this plat. See link for the address change form on the PPRBD website https://www.pprbd.org/File/Resources/Downloads/Addressing/Request%20for%20change%20of%20address%20ACCESS.pdf
3. Address changes will need to be issued for surrounding properties in this area prior to the plat being recorded. The five addresses that will be impacted by changes to the area and will require address changes are as follows:
a. 5969 Hodgen Rd – 51000-00-484 – Well House
b. 5975 Hodgen Rd - 51000-00-501 - Residence
c. 5989 Hodgen Rd & 5999 Hodgen Rd - 51000-00-485 – Pumpstation & Water Tank
d. 6155 Hodgen Rd - 51000-00-505 – Residence
4. Please add the following addresses to the plat for the new development: Lot 1 = 16181, Lot 2 = 6280, Lot 3 = 6210 & Lot 4 = 16121 off of Falcon Nation View and 6140 off of Purple Majestic View.
5. Standard Final Plat comments still apply.
Thank you,
Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
County Attorney - Development Reviewreview 3Dec 3, 2025
Plat note 17 still needs to be corrected to say that lots 1 and 4 may take direct access to the 50' access easement (rather than lots 1 and 2).
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com
EPC Fire and Wildfire Program Managerreview 3Dec 2, 2025
Comments have been addressed. Fire flow required at site plan from existing hydrants.
911 Authority - El Paso/Teller Countyreview 3Nov 21, 2025
Comments for E911 as follows:
Purple Majestic Vw – Available
Falcon Nation Vw – Available
Sundance Ranch Ln – Available, as a private street the suffix should be (Grove, Heights, Point, or View).
Thank you.
Justin
RBD Floodplainreview 3Nov 20, 2025
plat looks good no further comment
Cherokee Metro Distreview 2Nov 5, 2025
Subdivision is outside of District Boundaries and does not contain any Subterrain Cherokee Utilities going through the project area. No further review needed
El Paso County Conservation Distreview 2Oct 30, 2025
No comments at this time.
Pikes Peak Regional Building Departmentreview 2Oct 17, 2025
1. The note on the plat showing access easement for the benefit of Lots 2 & 3 shows note 16, it appears it should be Plat note 17.
2. Comments still need to be addresses regarding address changes, specifically the residences at 6155 Hodgen Rd and 5975 Hodgen Rd.
• Once street names have been reserved and added to the plat, address changes will need to be issued for surrounding properties in this area prior to the plat being recorded. The five addresses that will be impacted by changes to the area and will require address changes are as follows:
a. 5969 Hodgen Rd – 51000-00-484 – Well House
b. 5975 Hodgen Rd - 51000-00-501 - Residence
c. 5989 Hodgen Rd & 5999 Hodgen Rd - 51000-00-485 – Pumpstation & Water Tank
d. 6155 Hodgen Rd - 51000-00-505 – Residence
• Due to the new subdivision in this area, it is required that the developer communicate with surrounding property owners and officially notify them that their addresses will need to change. Confirmation of support from the property owners who will need an address change as a result of this development is required before Enumerations will support this plat. See link for the address change form on the PPRBD website https://www.pprbd.org/File/Resources/Downloads/Addressing/Request%20for%20change%20of%20address%20ACCESS.pdf
3. Comments still need to be addressed regarding naming the N/S coming off of Hodgen Rd. and a name for the roadway leading to Lots 2 & 3. 911 Authority Streetnaming information (criteria, existing/reserved names) can be found at:
https://www.elpasoteller911.org/street-emergency-number-databases
Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
911 Authority - El Paso/Teller Countyreview 2Oct 17, 2025
Comments for E911
Sundance Ranch Ln is available.
There are two other road names necessary for this development.
- Existing unnamed North/South access coming from Hodgen Rd.
- New roadway leading to Lots 2 and 3 for this development.
Naming the two existing roadways will require readdressing of existing residences. The developer should communicate with the owners, and provide documentation of this communication.
Streetnaming information (criteria, existing/reserved names) can be found at:
https://www.elpasoteller911.org/street-emergency-number-databases
Thank you
Justin
PCD Engineering Divisionreview 2Oct 15, 2025
DPW Engineering Comments review 2 has comments on the following documents:
- Letter of Intent (uploaded by Planner/PM)
- Final Plat
- FDR
- Traffic memo
- Closure sheet
- Deviation request - Culvert
Also needed:
- Deviation request for roadway
Reviewed by:
Bret Dilts, PE
BretDilts@elpasoco.com
719-520-6864
PCD Project Managerreview 2Oct 15, 2025
Please submit a deviation on the correct form with the backup material as one line item.
DPW Engineering, Bret Dilts will upload the remainder of the documents when he has completed his review. Planning staff does have Plat comments.
EPC Stormwater Reviewreview 2Oct 14, 2025
Review 2: EPC DPW Stormwater comments have been resolved on the following documents:
- Final Drainage Report
- Final Plat
- PCM Applicability Form
EPC DPW Stormwater has no further comments. EPC Project Manager: no re-review necessary.
Reviewed by:
Mikayla Hartford, P.E.
Engineer - Stormwater
719.339.5053
MikaylaHartford@elpasoco.com
County Attorney - Development Reviewreview 2Oct 14, 2025
Please correct the reference to plat note 16 to be a reference to plat note 17 on p. 2 of the plat where the new 20’ access easement is identified. Also, please correct plat note 17 to say that Lots 1 and 4 may take direct access to 50’ access easement (private drive), not Lots 1 and 2.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
EPC Fire and Wildfire Program Managerreview 2Oct 13, 2025
The fire protection report references an existing hydrant to be used. At Site Plan provide the fire flow for this hydrant at 20psi per the Land Development Code.
The WUI Plat Note has been added to the Final Plat Plans.
The comments have been addressed.
Roland Peterson
Fire Safety and Wildfire Mitigation Program Manager
Planning & Community Development
719.520.6075
rolandpeterson@elpasoco.com
EPC Parks Departmentreview 2Oct 10, 2025
El Paso County Parks Department, Final Comments, 2nd Submittal - Please See Attached Documentation (Originally endorsed by the El Paso County Park Advisory Board on May 14, 2025)
County Attorney - Waterreview 2Oct 9, 2025
County Attorney’s Office will begin review after comments from 5/13/25 have been addressed. Thank you.
Black Forest Fire Protection Districtreview 1May 30, 2025
BFFRPD (Black Forest Fire Rescue Protection District) has reviewed the proposed project. Of concern for BFFRPD operations is the fire department access and fire protection water supplies, considering there are no known cisterns and there is not a municipal water system. While minor subdivisions are exempt from the IFC, the language (requiring a fire cistern) still exist in the LDC. The County is the Authority Having Jurisdiction (AHJ) that will determine the requirements for cistern and specifications for access/egress. If the County requires one, then one is required irrespective of what the IFC calls for.
All structures and street signs need to comply with PPRBD, EL Paso County standards, IBC 2021 and IFC 2021 standards. Our recommendation is the applicant demonstrate full compliance and conformance with El Paso County’s adopted Land Development Code (LDC), Engineering Criteria Manual (ECM), adopted International Fire Code (IFC), and all other adopted codes, provisions, or statutes that impact fire safety to include access/egress, water supply, hardening of structures, addressing, fire protection systems, etc.
It is recommended that the applicant submit a comprehensive fire protection report from a qualified fire protection engineer that is licensed as a Professional Engineer (PE) by the Colorado State Board of Registration for Professional Engineers to demonstrate conformance to all requirements. The current Fire Protection report is not completed by such person. Furthermore, the District does not support any waivers or variances that negatively impact any fire safety provisions including access/egress, water supply, hardening of structures, addressing, fire protections systems, etc.
Cherokee Metro Distreview 1May 29, 2025
(See attachment). Cherokee has a Transmission line on the road to the Southwest of the Platte. No utility request being made and Platte does not overlay on Cherokee line. No further review needed
Mountain View Electric Association, Inc.review 1May 27, 2025
See previous comment from Jan 29.
County Attorney - Development Reviewreview 1May 20, 2025
With respect to the SIA and DMA, no comments from County Attorney - Development Review at this time.
With respect to access, the Letter of Intent indicates that access is being provided via easement. However, we do not see any new access easements identified on the plat. The documents provided do not provide legal access to these parcels. If you want to rely on the easement recorded at 220900262, please provide it. Thank you.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
PCD Project Managerreview 1May 20, 2025
(B)Wetlands Standards. (1)Reductions of Impacts and Avoidance. Wetlands offer important wildlife habitat, improve surface water quality, and are often indicators of significant natural hazards. When developing a lot, tract or parcel, wetlands should be incorporated into the design of the project or avoided when practical. Storm drainage system design should consider the presence of wetlands and limit impacts that can result from flow volumes, flow rates, and water quality entering a wetland.(2)Removal of Wetlands. If a wetland must be removed to facilitate the development of a lot, tract or parcel, mitigation should be considered and may be required by the BoCC or other agencies including replacement wetlands.
Note if any road/drive crossing of the wetland is to occur.
These wetland areas are proposed to be in lots owned by individuals and are a part of the development please update the natural features report to include this section and analysis.
PCD Project Managerreview 1May 20, 2025
If a cistern is determined to be needed, add to the FAE please.
PCD Project Managerreview 1May 20, 2025
6.2.8. Maintenance Plans
(A)General. (1)Purpose. Maintenance plans are intended to provide for the long term maintenance and care of roads, common areas, recreational and park areas or facilities, open space, bikeways, trails, paths, malls, parking areas, sanitation facilities, common sewerage or water system, permanent BMPs, or private detention ponds where responsibility for operation and maintenance is shared by 2 or more dwelling units, ownerships, businesses, or uses, or any other similar facility.(2)Applicability. An applicant for a development which includes non-governmental maintenance and care of roads, common areas, recreational and park areas, or facilities, open space, bikeways, trails, paths, malls, parking areas, sanitation facilities, common sewerage or water system by 2 or more dwelling units or uses, private detention ponds, permanent BMPs, or any other similar type of facility and tracts that are not building sites, is responsible for preparing a maintenance plan as part of the development application for the project.
Provide the maintenance plan for the shared road- a driveway only serves 3 lots....the access serves more than 3 lots...
PCD Project Managerreview 1May 20, 2025
Is the development to be known as Sundance Ranch or Deim Sub?
PCD Project Managerreview 1May 20, 2025
PCD & DPW staff Comments on permission for use of the existing easement between the pipeline company and Cherokee MD, documentation provided.
Please note: the applicant still needs to provide the maintenance agreement for the use of the easements as it pertains to future lot owners, as this is the proposed access to the development in addition to the documentation requested in the comments on the easement between the two utilities.
They are 2 separate documents.
PCD Project Managerreview 1May 20, 2025
Based on the documentation provided by the USFWS- further study is required; see highlighted portion of attachment.
PCD Engineering Divisionreview 1May 19, 2025
DSD Engineering Comments R1:
See attached comment memo.
Redlines are provided on:
- Letter of Intent (to be uploaded by Planner/PM)
- Final Plat (to be uploaded by Planner/PM)
- FDR
- Traffic memo
- CD note page
Also needed:
- Deviation requests
Notes:
- Per restrictions in the Cherokee Metro District easements, documentation is required from the district regarding use of their easements by the future subdivision property owners and potential future County ROW that would be required to supersede the easement, if granted.
- Protection and unimpeded use of the flood control dam and reservoir easement is required as noted in redlines and comment memo.
Reviewed by:
Bret Dilts - BretDilts@elpasoco.com; 719-520-6864
Jeff Rice - jeffrice@elpasoco.com; 719-520-7877
EPC Stormwater Reviewreview 1May 19, 2025
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents (to be uploaded by the Project Manager):
- Final Drainage Report
- Final Plat
- PCM Applicability Form
Reviewed by:
Mikayla Hartford, P.E.
Engineer - Stormwater
719.339.5053
MikaylaHartford@elpasoco.com
Black Forest Land Use Committeereview 1May 18, 2025
The Black Forest Land Use Committee has no objection to this proposal.
Colorado Geological Surveyreview 1May 16, 2025
As noted on page 4 of the Soils and Geology Study (Entech Engineering, February 14, 2025), “The engineering geologic constraints/hazards identified on this site include artificial fill, potentially expansive soils, ponded water, and potential seasonally shallow groundwater areas.” The site also lies within a mapped floodplain zone (FEMA Map No. 08041CO305G, dated December 7, 2018) associated with the Franktown Parker FPE-2 Reservoir. Entech states, “Building areas are expected to be well above this drainage area.” Additionally, this area is depicted as a “No Build/No Disturbance Area” on the final plat. CGS generally agrees with the geologic interpretation, the hazards and constraints identified that are related to site geology, and the recommendations for mitigating these conditions. Entech’s recommendations concerning identified hazards and constraints should be followed except where noted in the following paragraphs, where additional recommendations are provided.
1. Figures 3 and 6 in Entech’s report should be updated to include the entire maps.
2. Entech states p.3, “Groundwater was not encountered in the test borings during or subsequent to drilling which were drilled to depths of 20 feet.” The test borings were drilled during December 2024. It does not appear that these test holes were checked days following drilling operations. Due to the proximity to the mapped floodplain/reservoir, CGS recommends that groundwater monitoring/observation holes be installed to measure/check groundwater fluctuations through at least the Spring and Summer to determine the feasibility of basements. CGS recommends that the county require a note on the plat stating that no basements are allowed unless a monitoring program through a 12-month period establishes the depth and fluctuation of groundwater at this location.
3. Entech states (p.5), “Finished floor levels should be located a minimum of one foot above the floodplain level.” Once the revised floodplain levels are established, Entech should review proposed finish floor elevations and grading plans to ensure they align with their recommendations.
4. A geologic hazard note should be included in the final plat that references Entech’s report and the geologic hazards/constraints with mitigation measures listed.
Submitted 5/16/2025 by Amy Crandall, Colorado Geological Survey: acrandall@mines.edu
EPC Fire and Wildfire Program Managerreview 1May 16, 2025
Fire plan review comments added to final plat drawing and fire protection report.
Pikes Peak Regional Building Departmentreview 1May 16, 2025
1. In order to provide addresses for this subdivision an internal named street will be needed. Access to lots 3 and 4 will need to be shown on the plat.
2. Intent letter states that there is access from an existing looped private street. We do not have a Sundance Ranch Lane in our records, nor has it been reserved.
3. The street name (Sundance Ranch Ln) is not shown on the final plat, please clarify this street name, and if needed, please reserve this proposed street name with the 911 Authority - El Paso/Teller County.
4. In order to accommodate possible future development in this area, at least two existing roadways will need be named. Address changes will also need to be issued for surrounding properties in this area. The five addresses that will be impacted by changes to the area and will require address changes are as follows:
a. 5969 Hodgen Rd – 51000-00-484 – Well House
b. 5975 Hodgen Rd - 51000-00-501 - Residence
c. 5989 Hodgen Rd & 5999 Hodgen Rd - 51000-00-485 – Pumpstation & Water Tank
d. 6155 Hodgen Rd - 51000-00-505 - Residence
5. Due to the new subdivision in this area, it is required that the developer communicate with surrounding property owners and officially notify them that their addresses will need to change. We will not process address changes until we receive correspondence that the property owners have been notified of the address changes.
6. See link for the address change form on the PPRBD website https://www.pprbd.org/File/Resources/Downloads/Addressing/Request%20for%20change%20of%20address%20ACCESS.pdf
7. Standard Final Plat comments apply.
Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
Parks Advisory Boardreview 1May 15, 2025
El Paso County Parks Department, Final Comments - Please See Attached Documentation (Endorsed by the Park Advisory Board on May 14, 2025)
EPC Parks Departmentreview 1May 15, 2025
El Paso County Parks Department, Final Comments - Please See Attached Documentation (Endorsed by the Park Advisory Board on May 14, 2025)
911 Authority - El Paso/Teller Countyreview 1May 14, 2025
Comments for E911 as follows:
Sundance Ranch Lane is available, name will not be reserved until depicted on submitted plan drawings.
It appears that there will need to be three named roads for this development:
- Existing unnamed North/South access coming from Hodgen Rd.
- Existing unnamed Southeast access running past this development.
- New roadway leading to Lots 2 and 3 for this development (should be indicated on plans).
Naming the two existing roadways will require readdressing of existing residences. The developer should communicate with the owners, and provide documentation of this communication.
Thank you.
Justin
County Attorney - Waterreview 1May 13, 2025
Please provide the Cherokee Agreement referenced in paragraph 26.B. of the Water Decree in 23CW3067 as well as a Deed from the Sundance Property Owner's Association to the Deim's showing that they own their portion of the water. Thank you.
PCD Administrative Noticereview 1May 1, 2025
On 04/30/2025, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (9 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $6.21. JM
US Postal Servicereview 1Apr 28, 2025
Please contact Rita Minnard (oreta.j.minnard@usps.gov) directly to review this development for mail service. To establish mail delivery and kiosk locations an appointment will be required with USPS to determine final locations. Information required for this establishment include proposed locations, type of mail receptacle, final plat with addresses, type of development (residential/commercial) and date of first occupancy.
RBD Floodplainreview 1Apr 28, 2025
The parcel is located within the current effective Zone A floodplain with no BFEs(no supporting model available). Draft model backed BFEs for this area have been developed as part of Phase 1 for the ongoing El Paso County, CO, Risk MAP Project”. The data has been reviewed and approved through FEMA’s QA/QC process (May 11, 2022) and is currently in the MIP (Case No. 19-08-0037s). The Phase 1/Base Level Engineering outputs and Zone A ready deliverables are, under the following folder:
K:/FY2019/19-08-0037S/Discovery - BLE - El Paso and Teller Counties, CO - FY18 - 04/Discovery Data Capture - Discovery Data Capture - El Paso and Teller Counties, CO - 01/El Paso_Discovery_1
BFEs from the aforementioned study should be shown on the final plat to comply with RBC 313.18.5
see attached
Land ownership timeline
- Feb 1, 2021Parcel 5100000509 acquired by DEIM CONNIE & DIEM JOSH for $570,000 (assessor record)
Timeline
- Dec 5, 2025Submission request sent to Applicant
- Dec 5, 2025Request for Review Comments returned by PCD Project Manager
- Dec 5, 2025Request for Review Comments returned by PCD Engineering Division
- Dec 4, 2025Request for Review Comments returned by EPC Health Department
- Dec 4, 2025Submission request sent to Applicant
- Dec 4, 2025Request for Review Comments returned by Pikes Peak Regional Building Department
- Dec 3, 2025Request for Review Comments returned by County Attorney - Development Review
- Dec 2, 2025Request for Review Comments returned by EPC Fire and Wildfire Program Manager
- Dec 2, 2025Request for Review Comments email resent for Project Deim Subdivision Plat for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Dec 2, 2025Request for Review Comments returned by EPC Fire and Wildfire Program Manager
- Nov 21, 2025Request for Review Comments returned by 911 Authority - El Paso/Teller County
- Nov 20, 2025Request for Review Comments returned by RBD Floodplain
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of Pikes Peak Regional Building Department
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Keith Curtis on behalf of RBD Floodplain
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Chuck Reed on behalf of Cherry Creek Basin Water Quality Authority
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by John Hunyadi on behalf of Colorado Dam Safety Division
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Brian McCormick PE on behalf of Colorado Dam Safety Division
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Catherine McGarvy on behalf of EPC Health Department
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Mike McCarthy on behalf of EPC Health Department
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by HEAEH LandUse on behalf of EPC Health Department
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Lori Seago on behalf of County Attorney - Development Review
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Erika Keech on behalf of County Attorney - Development Review
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by April Willie on behalf of County Attorney - Development Review
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Justin Kilgore on behalf of PCD Project Manager
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
- Nov 20, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Engineering Manager on behalf of PCD Engineering Division
- Nov 20, 2025Submission Triaged
- Nov 20, 2025Submission received from Applicant
- Nov 13, 2025Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Nov 5, 2025Request for Review Comments returned by Cherokee Metro Dist
- Oct 30, 2025Request for Review Comments returned by El Paso County Conservation Dist
- Oct 30, 2025Request for Review Comments returned by Central CO Conservation District
- Oct 27, 2025Request for Review Comments returned by EPC Health Department
- Oct 20, 2025Submission request sent to Applicant
- Oct 17, 2025Request for Review Comments returned by PCD Engineering Division
- Oct 17, 2025Request for Review Comments email resent for Project Deim Subdivision Plat for review by Engineering Manager on behalf of PCD Engineering Division
- Oct 17, 2025Request for Review Comments returned by Pikes Peak Regional Building Department
- Oct 17, 2025Request for Review Comments returned by PCD Engineering Division
- Oct 17, 2025Request for Review Comments returned by 911 Authority - El Paso/Teller County
- Oct 15, 2025Request for Review Comments returned by PCD Project Manager
- Oct 15, 2025Request for Review Comments returned by EPC Stormwater Review
- Oct 14, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Jeff Munger on behalf of Cherokee Metro Dist
- Oct 14, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Brandon Zembles on behalf of Cherokee Metro Dist
- Oct 14, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Vicki Wood on behalf of Lewis Palmer 38
- Oct 14, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Melissa Andrews on behalf of Lewis Palmer 38
- Oct 14, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Brett Ridgway on behalf of Lewis Palmer 38
- Oct 14, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of Pikes Peak Regional Building Department
- Oct 14, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
- Oct 14, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
- Oct 14, 2025Request for Review Comments returned by County Attorney - Development Review
- Oct 13, 2025Request for Review Comments returned by EPC Fire and Wildfire Program Manager
- Oct 10, 2025Request for Review Comments returned by EPC Parks Department
- Oct 9, 2025Request for Review Comments returned by County Attorney - Water
- Oct 3, 2025Request for Review Comments returned by EPC Environmental Services
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Harry Thomas on behalf of El Paso County Conservation Dist
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Oliver Watkins on behalf of El Paso County Conservation Dist
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Katie Miller on behalf of El Paso County Conservation Dist
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Erica Carter on behalf of El Paso County Conservation Dist
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of El Paso County Conservation Dist
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Mariah Hudson on behalf of El Paso County Conservation Dist
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Cassie Olgren on behalf of El Paso County Conservation Dist
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Billy Richard on behalf of El Paso County Conservation Dist
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Chuck Reed on behalf of Cherry Creek Basin Water Quality Authority
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of Central CO Conservation District
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by John Hunyadi on behalf of Colorado Dam Safety Division
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Brian McCormick PE on behalf of Colorado Dam Safety Division
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Kathy Andrew on behalf of EPC Environmental Services
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Zachary Jannusch on behalf of EPC Stormwater Review
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Mikayla Hartford on behalf of EPC Stormwater Review
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Glenn Reese on behalf of EPC Stormwater Review
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Christina Prete on behalf of EPC Stormwater Review
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of EPC Parks Department
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Mike McCarthy on behalf of EPC Health Department
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Catherine McGarvy on behalf of EPC Health Department
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by HEAEH LandUse on behalf of EPC Health Department
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Lori Seago on behalf of County Attorney - Water
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Erika Keech on behalf of County Attorney - Water
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by April Willie on behalf of County Attorney - Water
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Lori Seago on behalf of County Attorney - Development Review
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Erika Keech on behalf of County Attorney - Development Review
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by April Willie on behalf of County Attorney - Development Review
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Justin Kilgore on behalf of PCD Project Manager
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Engineering Manager on behalf of PCD Engineering Division
- Oct 1, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Oct 1, 2025Submission Triaged
- Oct 1, 2025Submission received from Applicant
- Sep 15, 2025Submission request sent to Applicant
- Sep 15, 2025Submission request sent to Applicant
- Jul 21, 2025Submission request sent to Applicant
- Jul 21, 2025Submission Triaged
- Jul 21, 2025Submission received from Applicant
- Jun 14, 2025Request for Review Comments returned by EPC Health Department
- Jun 5, 2025Submission request sent to Applicant
- Jun 4, 2025Request for Review Comments returned by Colorado Parks and Wildlife
- Jun 2, 2025Submission request sent to Applicant
- May 30, 2025Request for Review Comments returned by Black Forest Fire Protection District
- May 29, 2025Request for Review Comments returned by Cherokee Metro Dist
- May 29, 2025Request for Review Comments email resent for Project Deim Subdivision Plat for review by Brandon Zembles on behalf of Cherokee Metro Dist
- May 28, 2025Request for Review Comments returned by Cherokee Metro Dist
- May 27, 2025Request for Review Comments returned by Mountain View Electric Association, Inc.
- May 20, 2025Request for Review Comments returned by County Attorney - Development Review
- May 20, 2025Submission request sent to Applicant
- May 20, 2025Request for Review Comments returned by PCD Project Manager
- May 19, 2025Request for Review Comments returned by PCD Engineering Division
- May 19, 2025Request for Review Comments returned by EPC Stormwater Review
- May 18, 2025Request for Review Comments returned by Black Forest Land Use Committee
- May 16, 2025Request for Review Comments returned by Colorado Geological Survey
- May 16, 2025Request for Review Comments returned by EPC Fire and Wildfire Program Manager
- May 16, 2025Request for Review Comments returned by Pikes Peak Regional Building Department
- May 15, 2025Request for Review Comments returned by Parks Advisory Board
- May 15, 2025Request for Review Comments returned by EPC Parks Department
- May 14, 2025Request for Review Comments returned by 911 Authority - El Paso/Teller County
- May 13, 2025Request for Review Comments returned by County Attorney - Water
- May 12, 2025Request for Review Comments returned by Colorado Division of Water Resources
- May 8, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Chuck Reed on behalf of Cherry Creek Basin Water Quality Authority
- May 8, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Jeff Munger on behalf of Cherokee Metro Dist
- May 8, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Brandon Zembles on behalf of Cherokee Metro Dist
- May 8, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of Central CO Conservation District
- May 8, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by John Hunyadi on behalf of Colorado Dam Safety Division
- May 8, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Brian McCormick PE on behalf of Colorado Dam Safety Division
- May 1, 2025Fees paid: 5/1/2025 (Receipt: 1010486)
- May 1, 2025Payment Request sent: 5/1/2025
- May 1, 2025Request for Review Comments returned by PCD Administrative Notice
- Apr 29, 2025Request for Review Comments returned by EPC Environmental Services
- Apr 28, 2025Project Manager Assigned: Kari Parsons
- Apr 28, 2025Request for Review Comments returned by US Postal Service
- Apr 28, 2025Request for Review Comments returned by RBD Floodplain
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Bill Crimmel on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by General Email on behalf of Mountain View Electric Association, Inc.
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Melissa Andrews on behalf of Lewis Palmer 38
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Vicki Wood on behalf of Lewis Palmer 38
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Brett Ridgway on behalf of Lewis Palmer 38
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Harry Thomas on behalf of El Paso County Conservation Dist
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Oliver Watkins on behalf of El Paso County Conservation Dist
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Katie Miller on behalf of El Paso County Conservation Dist
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Erica Carter on behalf of El Paso County Conservation Dist
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of El Paso County Conservation Dist
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Mariah Hudson on behalf of El Paso County Conservation Dist
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Cassie Olgren on behalf of El Paso County Conservation Dist
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Billy Richard on behalf of El Paso County Conservation Dist
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Bob Swatek on behalf of Black Hills Energy-Aquila
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Adam Magoon on behalf of Black Hills Energy-Aquila
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Cheryl Pixley on behalf of Black Forest Trails Association
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Terry Stokka on behalf of Black Forest Land Use Committee
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Terry Stokka on behalf of Black Forest Land Use Committee
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Rachel Dunn on behalf of Black Forest Fire Protection District
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Michael Alvarado on behalf of Black Forest Fire Protection District
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of Black Forest Fire Protection District
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Chad Herdt on behalf of Black Forest Fire Protection District
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Keith Curtis on behalf of RBD Floodplain
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of Pikes Peak Regional Building Department
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Rita Otega on behalf of US Postal Service
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Peyton Post Office on behalf of US Postal Service
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Travis Sauder on behalf of Colorado Parks and Wildlife
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Tim Kroening on behalf of Colorado Parks and Wildlife
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Karen Voltura on behalf of Colorado Parks and Wildlife
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Colorado Geological Survey on behalf of Colorado Geological Survey
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Melissa Van Der Poel on behalf of Colorado Division of Water Resources
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of Parks Advisory Board
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Zachary Jannusch on behalf of EPC Stormwater Review
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Mikayla Hartford on behalf of EPC Stormwater Review
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Glenn Reese on behalf of EPC Stormwater Review
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Christina Prete on behalf of EPC Stormwater Review
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Jeff Kramer on behalf of EPC Sheriff's Department
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Andrew Prehm on behalf of EPC Sheriff's Department
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of EPC Parks Department
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Mike McCarthy on behalf of EPC Health Department
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Catherine McGarvy on behalf of EPC Health Department
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by HEAEH LandUse on behalf of EPC Health Department
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Kathy Andrew on behalf of EPC Environmental Services
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Lori Seago on behalf of County Attorney - Water
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Erika Keech on behalf of County Attorney - Water
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by April Willie on behalf of County Attorney - Water
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Lori Seago on behalf of County Attorney - Development Review
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Erika Keech on behalf of County Attorney - Development Review
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by April Willie on behalf of County Attorney - Development Review
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Justin Kilgore on behalf of PCD Project Manager
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Gilbert LaForce on behalf of PCD Engineering Division
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by Engineering Manager on behalf of PCD Engineering Division
- Apr 28, 2025Request for Review Comments email sent for Project Deim Subdivision Plat for review by on behalf of PCD Administrative Notice
- Apr 28, 2025Project Manager Assigned: Lisa Elgin