Fall Mountain Farm Expansion
Special Use to allow agritainment parking greater than 50
- Location
- 16300 MOUNT HERMAN LN; 16456 FALLON RD; 16455 FALLON RD, 80132
- Jurisdiction
- El Paso County
- Applicant
- Fall Mountain Farm Company Steve Roscio
- Land owners (assessor)
- ROSCIO STEVEN J & ROSCIO CATHERINE L; ROSCIO STEVE & ROSCIO CATHY
- County project manager
- Lacey Dean
- Filed
- Jan 14, 2025
- Parcels
- 7100000355, 7129001003, 7129002002
- Map
-
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
- Source record
- El Paso County EDARP file
Documents (11)
Mailing LabelsadditionalMay 11, 2026
Mailing Labels for the 11 surrounding property owners. The cost to be billed to the applicant = $8.14 JM
Hearing Notice & Vicinity MapadditionalMay 11, 2026
"Notice of Administrative Decision" letters were mailed by PCD on 05/11/2025. The potential decision can be made after 05/25/2025. JM
Timeline
- Aug 10, 2026Request for Review Comments returned by EPC DPW Stormwater
- Jul 28, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Jul 28, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Jul 28, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Erica Rylander on behalf of EPC DPW Stormwater
- Jul 28, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Glenn Reese on behalf of EPC DPW Stormwater
- Jul 28, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Christina Prete on behalf of EPC DPW Stormwater
- Jul 28, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Justin Kilgore on behalf of PCD Project Manager
- Jul 28, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Gilbert LaForce on behalf of PCD Engineering Division
- Jul 28, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Engineering Manager on behalf of PCD Engineering Division
- Jul 28, 2026Submission Triaged
- Jul 23, 2026Submission received from Applicant
- Jun 1, 2026Submission request sent to Applicant
- Jun 1, 2026Request for Review Comments returned by PCD Project Manager
- May 26, 2026Request for Review Comments returned by PCD Engineering Division
- May 20, 2026Request for Review Comments returned by EPC DPW Stormwater
- May 19, 2026Request for Review Comments returned by Pikes Peak Regional Building Department
- May 14, 2026Fees paid: 5/14/2026 (Receipt: 1012055)
- May 14, 2026Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
- May 11, 2026Payment Request sent: 5/11/2026
- May 11, 2026Request for Review Comments returned by PCD Administrative Notice
- May 6, 2026Request for Review Comments returned by Mountain View Electric Association, Inc.
- May 6, 2026Request for Review Comments returned by EPC Code Enforcement
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Scott Benson on behalf of Tri-Lakes-Monument Fire Protection District
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Aaron Wood on behalf of Tri-Lakes-Monument Fire Protection District
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Bill Crimmel on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by General Email on behalf of Mountain View Electric Association, Inc.
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by on behalf of Pikes Peak Regional Building Department
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Vicki Wood on behalf of Lewis Palmer 38
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Brett Ridgway on behalf of Lewis Palmer 38
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Melissa Andrews on behalf of Lewis Palmer 38
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Trish Riber on behalf of Black Hills Energy-Aquila
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Bob Swatek on behalf of Black Hills Energy-Aquila
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Catherine McGarvy on behalf of EPC Health Department
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by HEAEH LandUse on behalf of EPC Health Department
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Christina Prete on behalf of EPC DPW Stormwater
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Glenn Reese on behalf of EPC DPW Stormwater
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Kurt Arnoldussen on behalf of EPC Code Enforcement
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Justin Kilgore on behalf of PCD Project Manager
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Engineering Manager on behalf of PCD Engineering Division
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Gilbert LaForce on behalf of PCD Engineering Division
- May 4, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by on behalf of PCD Administrative Notice
- May 4, 2026Project Manager Assigned: Lacey Dean
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Scott Benson on behalf of Tri-Lakes-Monument Fire Protection District
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Aaron Wood on behalf of Tri-Lakes-Monument Fire Protection District
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Bill Crimmel on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by General Email on behalf of Mountain View Electric Association, Inc.
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by on behalf of Pikes Peak Regional Building Department
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Vicki Wood on behalf of Lewis Palmer 38
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Melissa Andrews on behalf of Lewis Palmer 38
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Brett Ridgway on behalf of Lewis Palmer 38
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Trish Riber on behalf of Black Hills Energy-Aquila
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Bob Swatek on behalf of Black Hills Energy-Aquila
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Catherine McGarvy on behalf of EPC Health Department
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by HEAEH LandUse on behalf of EPC Health Department
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Glenn Reese on behalf of EPC DPW Stormwater
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Christina Prete on behalf of EPC DPW Stormwater
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Kurt Arnoldussen on behalf of EPC Code Enforcement
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Justin Kilgore on behalf of PCD Project Manager
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Gilbert LaForce on behalf of PCD Engineering Division
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by Engineering Manager on behalf of PCD Engineering Division
- May 1, 2026Request for Review Comments email sent for Project Fall Mountain Farm Expansion for review by on behalf of PCD Administrative Notice
- Apr 30, 2026Fees paid: 4/30/2026 (Receipt: 1012005)
- Apr 30, 2026File # Assigned: AL2611
- Apr 30, 2026Payment Request sent: 4/30/2026
- Apr 30, 2026Submission Triaged
- Apr 30, 2026Submission received from Applicant
- Aug 26, 2025Submission request sent to Applicant
- Aug 18, 2025Submission request sent to Applicant
- May 21, 2025Submission request sent to Applicant
- Jan 23, 2025Submission request sent to Applicant
- Jan 14, 2025Project Created
- Jan 14, 2025Project Manager Assigned: Lisa Elgin