Flying Horse North PUD/SP Amendment (Major/Filing 9)
Major amendment to the Flying Horse North PUD Development Plan and Preliminary Plan to add 11 single-family lots.
- Location
- ALLEN RANCH RD; QUARTZ CREEK DR, 80908
- Jurisdiction
- El Paso County
- Applicant
- HR Green Inc. Blaine Perkins
- Land owner (assessor)
- PRI #2 LLC
- County project manager
- Ryan Howser
- Filed
- Apr 15, 2026
- Parcels
- 6136000008, 6136000009
- Map
-
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
- Area map
- See all Tri-Lakes projects on the map
- Source record
- El Paso County EDARP file
Documents (38)
Mailing LabelsadditionalJul 20, 2026
Mailing Labels for the 14 surrounding property owners that received notices. Cost = $10.92. JM
Neighbor Notice & Vicinity MapadditionalJul 20, 2026
Notice of Application letters were mailed to surrounding property owners on 07/20/2026. JM
Agency review comments (56)
EPC Parks Departmentreview 2Sep 23, 2026
El Paso County Parks Department, Final Comments - 2nd Submittal. Please see attached documentation - originally endorsed by the El Paso County Park Advisory Board on August 12, 2026. Thank you!
County Attorney - Waterreview 2Sep 10, 2026
County Attorney's Office will complete review once the Applicant has provided the Colorado Division of Water with the additional information they requested as of September 8, 2026, and an updated letter has been received from them.
EPC DPW Development Services - Engineeringreview 2Sep 8, 2026
Drainage Report - Preliminary
EPC DPW Development Services - Engineeringreview 2Sep 8, 2026
DPW Engineering review 2 has comments on the following documents
- Traffic Impact Study
- Drainage Report - Preliminary
Comments have been resolved on the following documents
- Letter of Intent
- PUD Development Plan
Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
Laura Besler, PE
laurabesler@elpasoco.com
EPC DPW Development Services - Engineeringreview 2Sep 8, 2026
Traffic Impact Study
PCD Project Managerreview 2Sep 8, 2026
Review 2: PCD Planning Division has no additional comments at this time.
Colorado Geological Surveyreview 2Sep 3, 2026
The available referral documents include the PUD & Preliminary Plan Major Amendment (HR Green, August 13, 2026), Letter of Intent (HR Green Development, LLC, July 27, 2026), the Response to CGS Review Comments (Entech Engineering, Inc., August 17, 2026), and other relevant documents.
Entech’s responses in their August 17, 2026 letter generally address our previous comments for Filing No. 9. Specifically:
1. Entech states in their response letter, “Due to the size of the lots and overall grade variations across the lots daylighting of drains should be feasible.” An underdrain system should be allowed ONLY if it can gravity discharge to a daylight outfall or is connected to an existing underdrain system that gravity discharges to a daylight outfall.
2. As indicated by Entech in their response letter, erosional setbacks should be established near drainages and noted in the plans. Building footprints should be outside the setback areas.
Entech states in their response letter, “In all of our studies shallow groundwater has not been encountered except in well-defined drainages.” The preliminary plan (Geologic Hazard Note) states, “Groundwater monitoring/observation holes to obtain groundwater data to verify that proposed floor levels are at least 3-feet above maximum anticipated groundwater levels and maintained-year round are to be implemented.” CGS continues to recommend that the county require groundwater monitoring/observation holes at the Flying Horse North to be checked seasonally.
Provided Entech’s recommendations are strictly adhered to, CGS has no further comments.
Submitted 9/3/2026 by Amy Crandall, Engineering Geologist, Colorado Geological Survey (303-384-2632 or acrandall@mines.edu)
EPC DPW Stormwaterreview 2Aug 27, 2026
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s), to be uploaded by the PM:
- Drainage Report
Please sign stamp the following document(s):
- PCM Applicability Form
Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
El Paso County Conservation Distreview 2Aug 23, 2026
The El Paso County Conservation District has reviewed the note from the applicant on our previous comments. As long as our issues are well addressed in the final plat plan, then EPCCD has no further comments to add to this application at this time. Thank you.
Parks Advisory Boardreview 1Aug 18, 2026
El Paso County Parks Department, Final Review Comments. Please See Attached Documentation for Park Advisory Board endorsed recommendations and comments - endorsed on August 12, 2026
EPC Sheriff's Departmentreview 1Aug 9, 2026
Black Forest Fire Rescue is the fire agency having jurisdiction for this location, EPSO Wildland defers comments to BFFR.
EPC Parks Departmentreview 1Aug 4, 2026
El Paso County Parks Department, Preliminary Comments - Please See Attached Documentation (To be presented to the El Paso County Park Advisory Board for consideration and endorsement on August 12, 2026)
Cherokee Metro Districtreview 1Jul 27, 2026
Cherokee Metropolitan District has no objection to this amendment to the PUD.
Future development applications will need a Site development plan that includes the proposed water/wastewater plan and profile views. The connection of the development into an established system needs to be called out/shown on the plans as well.
County Attorney - Waterreview 1Jul 24, 2026
The Water Resource Report shows a demand of 450.47 af/y and the Water Supply Information Summary (2nd page) shows a demand of 285.58 af/y. Please reconcile these numbers.
RBD Floodplainreview 1Jul 22, 2026
site not in the floodplain no comment
El Paso County Conservation Distreview 1Jul 21, 2026
The El Paso County Conservation District has reviewed this and we have the following comments:
1) Erosion controls/Revegetation plans/Watershed protections
We did not see any documents that went over an erosion control or revegetation/landscape plan during and post construction of the proposed building. We feel that this is particularly important for both the road and house construction phases because this sits in a drainage of E Cherry Creek that not only drains into the local golf course ponds, but also further down within about a mile is also the Franktown Parker FPE - 2 Reservoir. This is a stormwater control dam that El Paso County maintains and EPPC shares an easement on, as well is part of regular inspections of through our MOU with El Paso County. As such, EPCCD would like to see the following recommendations followed during and after construction:
A) Disturbed areas not being built on should be mulched and revegetated within 45 days of disturbance using plant/grass species native and/or naturalized to El Paso County, weather depending.
B) Disturbed areas be either: mulched after seeding with either weed-free hay or straw mulch at approximately 5,000 lbs per acre; Or approx. 1-2" of wood mulch coverage of these disturbed areas made from forest mitigation work and tree clearing on site; Or areas that are not suitable for revegetation such as driveways, parking areas (if not going to be paved), or safety areas around buildings should have a 1-2" thick layer of crushed rock, road base, or gravel to assist in preventing having exposed soil that would be prone to wind/runoff erosion concerns.
C) Prior to any soil work, silt fences need to be installed around all work areas to ensure loose soil does not become an erosion issue for the drainage in the event of heavy rainfall events.
D) For areas being replanted with natural grass, consider using the El Paso County Conservation District’s Native Shotgun Mix (available at EPCCD.org) for reseeding, which is well suited to soils present on this site and is comprised of 100% native and naturalized grass species.
2) Firewise, Fire Risk, and Forest Health
EPCCD has a strong commitment to forest health and fire safety within the areas we serve, particularly within Black Forest. The project site is located in a lightly forested transition area of Black Forest that carries an elevated wildfire risk, particularly due to its close proximity to the Hwy 83 Corridor, which is very heavily overgrown. The applicant had a fantastic Forest Management plan is obviously working with a forestry expert already to manage forest health, so we have no comments to add on that topic. We did not see an Firewise plans for when house construction begins, so we would like to see the following implemented to assist with these issues:
A) Vegetation management consistent with Firewise principles, including clearing trees and brush within approximately 35 feet of the proposed building. Trees should also be cleared to approximately 15 feet from the centerline on each side of all driveways, which is critical for safe emergency vehicle access and for faster emergency egress of residence in the event of a wildfire.
B) Thinning forested areas within 35–100 feet beyond the proposed houses (as recommended by Firewise practices) to approximately 40–60 trees per acre, reflecting a healthy Ponderosa pine and Douglas fir forest density based on U.S. Forest Service and Colorado State Forest Service guidance. This also supports improved fire resilience, wildlife habitat, and visual quality consistent with the El Paso County Master Plan for this area.
If these measures are added to the project's plan, then the El Paso County Conservation District will be content with the applicant's commitment to soil conservation, watershed protection, and protection of the surrounding community.
For any questions, please feel free to contact the EPCCD at 719-600-4706 or Will Vogl - Board VP at Will@EPCCD.org
PCD Project Managerreview 1Jul 21, 2026
Review 1: PCD Planning Division comments have been provided (in green) on the following uploaded documents:
- Letter of Intent
- PUDSP
- Waster Resources Report
PCD Project Manager has also uploaded the following documents with Engineering and Stormwater comments:
- Drainage Report
- PCM Applicability Form
- TIS
EPC DPW Development Services - Engineeringreview 1Jul 21, 2026
DPW Engineering review 1 has comments on the following documents
- Letter of Intent
- Traffic Impact Study
- Drainage Report - Preliminary
- PUD Development Plan
Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
Laura Besler, PE
laurabesler@elpasoco.com
EPC DPW Stormwaterreview 1Jul 21, 2026
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s), to be uploaded by the PM:
- Drainage Report
- PCM Applicability Form
Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
PCD Administrative Noticereview 1Jul 20, 2026
On 07/20/2026, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (14 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $10.92. JM
Black Forest Land Use Committeereview 1Jul 15, 2026
The Black Forest Land Use Committee commends the applicant for returning to the 5-acre average for lots in Flying Horse North. We strongly believe this will make a most beautiful and appealing residential development.
We support and approve this filing.
Black Forest Fire Protection Districtreview 1Jul 14, 2026
BFFR accepts the proposed amendment based on the access and fire water supply discussions previously held with the applicant, design team, fire protection consultant, and BFFR representatives. The approval is based on the understanding that the project will be constructed and maintained in accordance with the access and water supply approach discussed and agreed upon during those meetings.
From a fire apparatus access standpoint, the submittal identifies a new roadway serving the 11 lots with a cul-de-sac and a total road length of less than 1,000 feet. Fire apparatus access shall comply with the currently adopted **International Fire Code**, including **IFC Section 503**, applicable IFC appendices, El Paso County requirements, and BFFR standards. Access roads shall provide an approved all-weather surface, minimum unobstructed width, minimum vertical clearance of 13 feet 6 inches, acceptable grade, turning radius, and load-bearing capacity for BFFR apparatus, including engines, ambulances, brush apparatus, and water tenders. The proposed cul-de-sac and roadway layout are acceptable at this stage provided the final construction documents maintain fire apparatus access compliance and do not create access restrictions.
For fire protection water supply, BFFR reviewed the Fire Protection Report prepared for Filing No. 9. The report identifies the existing fire hydrant at the Flying Horse North clubhouse as the primary pressurized water source for fire protection support. The report states that this hydrant is supplied by the irrigation pump system located west of the clubhouse and is capable of providing a minimum of **500 gpm at 20 psi**. The report also states that the pump house contains three 750 gpm pumps, with total available pump capacity up to 2,250 gpm. The clubhouse hydrant is identified as being approximately one-half mile from the furthest lot within Filing No. 9. This water supply approach is consistent with the discussions and agreements reached with BFFR and is accepted provided the hydrant, pump system, and access remain available, maintained, and operational for fire department use.
The Fire Protection Report identifies two required access improvements related to the fire water supply. First, approved Knox access shall be provided at the clubhouse and pump house gates so BFFR and mutual aid companies can access the hydrant and pump house during an emergency. Second, the parking space closest to the clubhouse hydrant shall be marked as a fire lane to maintain unobstructed access to the hydrant. BFFR agrees with these requirements. These items shall be completed and maintained prior to final fire acceptance or as otherwise approved by the BFFR AHJ.
The project is located within the Black Forest wildland-urban interface area. The submitted wildfire report classifies the Filing No. 9 area as a low fire intensity classification based on current fuels, topography, surrounding golf course fuel breaks, and proposed mitigation. All future homes, accessory structures, and site improvements shall comply with the adopted Colorado Wildland Urban Interface / Wildfire Resiliency Code, adopted building code, adopted International Fire Code, and BFFR requirements in effect at the time of building permit. Defensible space, vegetation management, ignition-resistant construction, and driveway access shall be maintained for the life of the development.
Black Forest Fire Rescue recommends **acceptance with conditions**. Acceptance is contingent upon maintaining the agreed-upon fire apparatus access, maintaining the clubhouse hydrant and pump house water supply for fire department use, installing approved Knox access at required gates, marking and maintaining the hydrant access area as a fire lane, and complying with all applicable IFC, WUI, addressing, driveway, and BFFR requirements. Any material change to the proposed access layout or fire water supply method shall be resubmitted to BFFR for review and approval.
Mountain View Electric Association, Inc.review 1Jul 13, 2026
See attached comment letter
Colorado Springs Public Worksreview 1Jul 13, 2026
Engineering Development Review will require all public improvements to be built to full City Standards if this is chosen for pre-annexation per the IGA.
Joel Dagnillo, P.E.
Engineering Development Review
City of Colorado Springs
(719)385-5412
Joel.dagnillo@coloradosprings.gov
Colorado Springs Public Worksreview 1Jul 8, 2026
Traffic Engineering has no comments on this item.
Brian Shevock
Public Works/Traffic Engineering
Traffic Engineer II
City of Colorado Springs
brian.shevock@coloradosprings.gov
Academy School District 20 Building Fundreview 1Jul 6, 2026
Academy District 20 is in receipt of File #PUDSP263 for approval of the Flying Horse North PUD/SP Amendment (Major/Filing 9). The District is requesting fees in lieu of land dedication per the existing County Code for all residential units within this development.
The District is able to serve each student who is a resident of District 20.
If you need additional information, please contact me.
Peter Ristig
Executive Director for Operations
Academy School District
E911 Authority - El Paso/Teller Countyreview 1Jul 1, 2026
Comments for E911 as follows:
Sorraia Way – Acceptable and reserved
No other action for E911 on this submittal.
Thank you.
Justin
Pikes Peak Regional Building Departmentreview 1Jun 30, 2026
1. An email from Justin Annan jannan@eptc911.org; or Glenn West gwest@eptc911.org;, with El Paso-Teller County E-9-1-1 Authority, reserving the street names is required to be emailed to the Enumerations department. Amy Vanderbeek Amy@pprbd.org; Brent Johnson Brent@pprbd.org; or Becky Allen BeckyA@pprbd.org
2. Contact Enumerations when you are ready to have addresses assigned.
3. If underground service is needed prior to plat, submit a Utilities Addressing Plan (UAP), to Colorado Springs Utilities via the related link at https://www.csu.org/Pages/GISMapping.aspx For more information contact: Jade Swan jswan@csu.org
Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
Colorado Department of Transportation - Pueblo Officereview 1Jun 30, 2026
All required improvements at Stagecoach Road and State Highway 83 have been constructed with the first phase of Flying Horse North. There is a current CDOT Access Permit (#218037) for Stagecoach Road and State Highway 83. No further action is required.
Please refer to the attached letter.
Colorado Springs Planning & Community Developmentreview 1Jun 30, 2026
City Planning has no comment.
Land ownership timeline
- Jun 26, 2026Parcels 6136000008, 6136000009 acquired by PRI #2 LLC for $10 (assessor record)
Timeline
- Sep 23, 2026Request for Review Comments returned by EPC Parks Department
- Sep 15, 2026Submission request sent to Applicant
- Sep 10, 2026Request for Review Comments returned by County Attorney - Water
- Sep 8, 2026Request for Review Comments returned by Colorado Division of Water Resources
- Sep 8, 2026Request for Review Comments returned by EPC DPW Development Services - Engineering
- Sep 8, 2026Request for Review Comments returned by PCD Project Manager
- Sep 8, 2026Request for Review Comments email resent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Sep 3, 2026Request for Review Comments returned by Colorado Geological Survey
- Sep 2, 2026Request for Review Comments returned by EPC DPW Stormwater
- Aug 23, 2026Request for Review Comments returned by El Paso County Conservation Dist
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by William Vogl on behalf of El Paso County Conservation Dist
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Harry Thomas on behalf of El Paso County Conservation Dist
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Katie Miller on behalf of El Paso County Conservation Dist
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of El Paso County Conservation Dist
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Mariah Hudson on behalf of El Paso County Conservation Dist
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Colorado Geological Survey on behalf of Colorado Geological Survey
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of EPC Parks Department
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Glenn Reese on behalf of EPC DPW Stormwater
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Erica Rylander on behalf of EPC DPW Stormwater
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Christina Prete on behalf of EPC DPW Stormwater
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Lori Seago on behalf of County Attorney - Water
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by April Willie on behalf of County Attorney - Water
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Erika Keech on behalf of County Attorney - Water
- Aug 18, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Justin Kilgore on behalf of PCD Project Manager
- Aug 18, 2026Submission Triaged
- Aug 18, 2026Request for Review Comments returned by Parks Advisory Board
- Aug 17, 2026Submission received from Applicant
- Aug 9, 2026Request for Review Comments returned by EPC Sheriff's Department
- Aug 4, 2026Request for Review Comments returned by EPC Parks Department
- Jul 29, 2026Request for Review Comments returned by Black Forest Fire Protection District
- Jul 27, 2026Request for Review Comments returned by Cherokee Metro District
- Jul 24, 2026Submission request sent to Applicant
- Jul 24, 2026Request for Review Comments returned by County Attorney - Water
- Jul 24, 2026Request for Review Comments email resent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Jul 22, 2026Request for Review Comments returned by Colorado Division of Water Resources
- Jul 22, 2026Request for Review Comments returned by RBD Floodplain
- Jul 21, 2026Request for Review Comments returned by El Paso County Conservation Dist
- Jul 21, 2026Request for Review Comments returned by PCD Project Manager
- Jul 21, 2026Request for Review Comments returned by EPC DPW Development Services - Engineering
- Jul 21, 2026Request for Review Comments returned by EPC DPW Stormwater
- Jul 21, 2026Request for Review Comments returned by Colorado Geological Survey
- Jul 21, 2026Request for Review Comments returned by Colorado Springs Public Works
- Jul 21, 2026Request for Review Comments email resent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of Black Forest Fire Protection District
- Jul 20, 2026Request for Review Comments returned by PCD Administrative Notice
- Jul 15, 2026Request for Review Comments returned by Black Forest Land Use Committee
- Jul 14, 2026Request for Review Comments returned by Black Forest Fire Protection District
- Jul 13, 2026Request for Review Comments returned by Mountain View Electric Association, Inc.
- Jul 10, 2026Request for Review Comments returned by Colorado Parks and Wildlife
- Jul 6, 2026Request for Review Comments returned by Academy School District 20 Building Fund
- Jul 1, 2026Request for Review Comments returned by EPC Environmental Services
- Jul 1, 2026Request for Review Comments returned by E911 Authority - El Paso/Teller County
- Jun 30, 2026Request for Review Comments returned by Pikes Peak Regional Building Department
- Jun 30, 2026Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
- Jun 30, 2026Request for Review Comments returned by Colorado Springs Planning & Community Development
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Zaker Alazzeh on behalf of Colorado Springs Public Works
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by LaShunda Simpson on behalf of Colorado Springs Public Works
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Jonathan Scherer on behalf of Colorado Springs Public Works
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Joel Dagnillo on behalf of Colorado Springs Public Works
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Hao Vo on behalf of Colorado Springs Public Works
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by General Email on behalf of Colorado Springs Public Works
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Erin Powers on behalf of Colorado Springs Public Works
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Brian Shevock on behalf of Colorado Springs Public Works
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Drew Foxx on behalf of Colorado Springs Planning & Community Development
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Allison Stocker on behalf of Colorado Springs Planning & Community Development
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Alexander Painter on behalf of Colorado Springs Planning & Community Development
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Keith Curtis on behalf of RBD Floodplain
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of Pikes Peak Regional Building Department
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Bill Crimmel on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by William Vogl on behalf of El Paso County Conservation Dist
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Harry Thomas on behalf of El Paso County Conservation Dist
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Katie Miller on behalf of El Paso County Conservation Dist
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of El Paso County Conservation Dist
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Mariah Hudson on behalf of El Paso County Conservation Dist
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Dave Munger on behalf of Council of Neighborhood Organizations (CONO)
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Cheryl Pixley on behalf of Black Forest Trails Association
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Terry Stokka on behalf of Black Forest Land Use Committee
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Terry Stokka on behalf of Black Forest Land Use Committee
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Kimberly Wilkes on behalf of US Forest Service, Pikes Peak Ranger District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Jennifer DeWoody on behalf of US Forest Service, Pikes Peak Ranger District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Daniel Delgado on behalf of US Army Corps of Engineers
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Mike Till on behalf of Colorado State Forest Service
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Victoria Poulton on behalf of Colorado Parks and Wildlife
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Tim Kroening on behalf of Colorado Parks and Wildlife
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Travis Sauder on behalf of Colorado Parks and Wildlife
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Peter Chapman on behalf of Colorado Parks and Wildlife
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Karen Voltura on behalf of Colorado Parks and Wildlife
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Colorado Geological Survey on behalf of Colorado Geological Survey
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Mike Matz on behalf of Colorado Division of Water Resources
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Jeff Munger on behalf of Cherokee Metro District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Brandon Zembles on behalf of Cherokee Metro District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Tony Cerrone on behalf of Black Forest Fire Protection District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Rachel Dunn on behalf of Black Forest Fire Protection District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Michael Alvarado on behalf of Black Forest Fire Protection District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of Black Forest Fire Protection District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Cody Poole on behalf of Black Forest Fire Protection District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Fielding Lucas on behalf of Black Forest Fire Protection District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Chad Herdt on behalf of Black Forest Fire Protection District
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Tom Gregory on behalf of Academy School District 20 Building Fund
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Donald Smith on behalf of Academy School District 20 Building Fund
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Becky Allan on behalf of Academy School District 20 Building Fund
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by General Email on behalf of Mountain View Electric Association, Inc.
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Trish Riber on behalf of Black Hills Energy-Aquila
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Bob Swatek on behalf of Black Hills Energy-Aquila
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Meredith Nichols on behalf of Pikes Peak OEM (Office of Emergency Management)
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of Parks Advisory Board
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Jeff Kramer on behalf of EPC Sheriff's Department
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Lizz Floro on behalf of EPC Sheriff's Department
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of EPC Public Works, County Engineer
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of EPC Public Works, County Engineer
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of EPC Parks Department
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Catherine McGarvy on behalf of EPC Health Department
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by HEAEH LandUse on behalf of EPC Health Department
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Kathy Andrew on behalf of EPC Environmental Services
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Glenn Reese on behalf of EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Erica Rylander on behalf of EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Christina Prete on behalf of EPC DPW Stormwater
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Justin Annan on behalf of E911 Authority - El Paso/Teller County
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Glenn West on behalf of E911 Authority - El Paso/Teller County
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Lori Seago on behalf of County Attorney - Water
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Erika Keech on behalf of County Attorney - Water
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by April Willie on behalf of County Attorney - Water
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by Justin Kilgore on behalf of PCD Project Manager
- Jun 30, 2026Request for Review Comments email sent for Project Flying Horse North PUD/SP Amendment (Major/Filing 9) for review by on behalf of PCD Administrative Notice
- Jun 29, 2026Fees paid: 6/29/2026 (Receipt: 1012260)
- Jun 26, 2026File # Assigned: PUDSP263
- Jun 26, 2026Payment Request sent: 6/26/2026
- Jun 26, 2026Submission Triaged
- Jun 25, 2026Submission received from Applicant
- May 5, 2026Submission request sent to Applicant
- Apr 15, 2026Project Created
- Apr 15, 2026Project Manager Assigned: Ryan Howser