Flying Horse North PUD/SP Amendment (Major/Filing 9)

PUD / preliminary plan PUDSP263 Active

Major amendment to the Flying Horse North PUD Development Plan and Preliminary Plan to add 11 single-family lots.

Location
ALLEN RANCH RD; QUARTZ CREEK DR, 80908
Jurisdiction
El Paso County
Applicant
HR Green Inc. Blaine Perkins
Land owner (assessor)
PRI #2 LLC
County project manager
Ryan Howser
Filed
Apr 15, 2026
Parcels
6136000008, 6136000009
Map
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
Area map
See all Tri-Lakes projects on the map
Source record
El Paso County EDARP file

Documents (38)

Traffic Impact StudyreviewAug 17, 2026
WRR Review HRG ResponsesreviewAug 5, 2026
PDR Review HRG ResponsesreviewAug 5, 2026
LOI Review HRG ResponsesreviewAug 5, 2026
PUD Review HRG ResponsesreviewAug 5, 2026
PCM Applicability FormreviewAug 5, 2026
Water Resources ReportreviewAug 5, 2026
Letter of IntentreviewAug 5, 2026
Letter of IntentreviewJun 25, 2026
Traffic Impact StudyreviewJun 25, 2026
PCM Applicability FormreviewJun 24, 2026
Zoning MapreviewJun 24, 2026
Application/Petition FormreviewJun 15, 2026
Forestry Management PlanreviewJun 15, 2026
Water Resources ReportreviewMay 5, 2026
Natural Features ReportreviewMay 5, 2026
Soils & Geology ReportreviewMay 5, 2026
Landscape Plan drawingsreviewMay 5, 2026
Fire Protection ReportreviewMay 5, 2026
Selected RangeadditionalJul 20, 2026
Selected Range was 500 feet. JM
Mailing LabelsadditionalJul 20, 2026
Mailing Labels for the 14 surrounding property owners that received notices. Cost = $10.92. JM
Neighbor Notice & Vicinity MapadditionalJul 20, 2026
Notice of Application letters were mailed to surrounding property owners on 07/20/2026. JM

Agency review comments (56)

Comments returned by referral agencies during review, from the county's public EDARP file. Some agencies attach a letter instead of (or alongside) written comments.

EPC Parks Departmentreview 2Sep 23, 2026
El Paso County Parks Department, Final Comments - 2nd Submittal. Please see attached documentation - originally endorsed by the El Paso County Park Advisory Board on August 12, 2026. Thank you!
View attached comment letter
County Attorney - Waterreview 2Sep 10, 2026
County Attorney's Office will complete review once the Applicant has provided the Colorado Division of Water with the additional information they requested as of September 8, 2026, and an updated letter has been received from them.
Colorado Division of Water Resourcesreview 1Sep 8, 2026
View attached comment letter
Colorado Division of Water Resourcesreview 1Sep 8, 2026
View attached comment letter
EPC DPW Development Services - Engineeringreview 2Sep 8, 2026
Drainage Report - Preliminary
View attached comment letter
EPC DPW Development Services - Engineeringreview 2Sep 8, 2026
DPW Engineering review 2 has comments on the following documents - Traffic Impact Study - Drainage Report - Preliminary Comments have been resolved on the following documents - Letter of Intent - PUD Development Plan Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 Laura Besler, PE laurabesler@elpasoco.com
EPC DPW Development Services - Engineeringreview 2Sep 8, 2026
Traffic Impact Study
View attached comment letter
PCD Project Managerreview 2Sep 8, 2026
Review 2: PCD Planning Division has no additional comments at this time.
Colorado Geological Surveyreview 2Sep 3, 2026
The available referral documents include the PUD & Preliminary Plan Major Amendment (HR Green, August 13, 2026), Letter of Intent (HR Green Development, LLC, July 27, 2026), the Response to CGS Review Comments (Entech Engineering, Inc., August 17, 2026), and other relevant documents. Entech’s responses in their August 17, 2026 letter generally address our previous comments for Filing No. 9. Specifically: 1. Entech states in their response letter, “Due to the size of the lots and overall grade variations across the lots daylighting of drains should be feasible.” An underdrain system should be allowed ONLY if it can gravity discharge to a daylight outfall or is connected to an existing underdrain system that gravity discharges to a daylight outfall. 2. As indicated by Entech in their response letter, erosional setbacks should be established near drainages and noted in the plans. Building footprints should be outside the setback areas. Entech states in their response letter, “In all of our studies shallow groundwater has not been encountered except in well-defined drainages.” The preliminary plan (Geologic Hazard Note) states, “Groundwater monitoring/observation holes to obtain groundwater data to verify that proposed floor levels are at least 3-feet above maximum anticipated groundwater levels and maintained-year round are to be implemented.” CGS continues to recommend that the county require groundwater monitoring/observation holes at the Flying Horse North to be checked seasonally. Provided Entech’s recommendations are strictly adhered to, CGS has no further comments. Submitted 9/3/2026 by Amy Crandall, Engineering Geologist, Colorado Geological Survey (303-384-2632 or acrandall@mines.edu)
EPC DPW Stormwaterreview 2Aug 27, 2026
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s), to be uploaded by the PM: - Drainage Report Please sign stamp the following document(s): - PCM Applicability Form Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
El Paso County Conservation Distreview 2Aug 23, 2026
The El Paso County Conservation District has reviewed the note from the applicant on our previous comments. As long as our issues are well addressed in the final plat plan, then EPCCD has no further comments to add to this application at this time. Thank you.
Parks Advisory Boardreview 1Aug 18, 2026
El Paso County Parks Department, Final Review Comments. Please See Attached Documentation for Park Advisory Board endorsed recommendations and comments - endorsed on August 12, 2026
View attached comment letter
EPC Sheriff's Departmentreview 1Aug 9, 2026
Black Forest Fire Rescue is the fire agency having jurisdiction for this location, EPSO Wildland defers comments to BFFR.
EPC Parks Departmentreview 1Aug 4, 2026
El Paso County Parks Department, Preliminary Comments - Please See Attached Documentation (To be presented to the El Paso County Park Advisory Board for consideration and endorsement on August 12, 2026)
View attached comment letter
Cherokee Metro Districtreview 1Jul 27, 2026
Cherokee Metropolitan District has no objection to this amendment to the PUD. Future development applications will need a Site development plan that includes the proposed water/wastewater plan and profile views. The connection of the development into an established system needs to be called out/shown on the plans as well.
County Attorney - Waterreview 1Jul 24, 2026
The Water Resource Report shows a demand of 450.47 af/y and the Water Supply Information Summary (2nd page) shows a demand of 285.58 af/y. Please reconcile these numbers.
RBD Floodplainreview 1Jul 22, 2026
site not in the floodplain no comment
El Paso County Conservation Distreview 1Jul 21, 2026
The El Paso County Conservation District has reviewed this and we have the following comments: 1) Erosion controls/Revegetation plans/Watershed protections We did not see any documents that went over an erosion control or revegetation/landscape plan during and post construction of the proposed building. We feel that this is particularly important for both the road and house construction phases because this sits in a drainage of E Cherry Creek that not only drains into the local golf course ponds, but also further down within about a mile is also the Franktown Parker FPE - 2 Reservoir. This is a stormwater control dam that El Paso County maintains and EPPC shares an easement on, as well is part of regular inspections of through our MOU with El Paso County. As such, EPCCD would like to see the following recommendations followed during and after construction: A) Disturbed areas not being built on should be mulched and revegetated within 45 days of disturbance using plant/grass species native and/or naturalized to El Paso County, weather depending. B) Disturbed areas be either: mulched after seeding with either weed-free hay or straw mulch at approximately 5,000 lbs per acre; Or approx. 1-2" of wood mulch coverage of these disturbed areas made from forest mitigation work and tree clearing on site; Or areas that are not suitable for revegetation such as driveways, parking areas (if not going to be paved), or safety areas around buildings should have a 1-2" thick layer of crushed rock, road base, or gravel to assist in preventing having exposed soil that would be prone to wind/runoff erosion concerns. C) Prior to any soil work, silt fences need to be installed around all work areas to ensure loose soil does not become an erosion issue for the drainage in the event of heavy rainfall events. D) For areas being replanted with natural grass, consider using the El Paso County Conservation District’s Native Shotgun Mix (available at EPCCD.org) for reseeding, which is well suited to soils present on this site and is comprised of 100% native and naturalized grass species. 2) Firewise, Fire Risk, and Forest Health EPCCD has a strong commitment to forest health and fire safety within the areas we serve, particularly within Black Forest. The project site is located in a lightly forested transition area of Black Forest that carries an elevated wildfire risk, particularly due to its close proximity to the Hwy 83 Corridor, which is very heavily overgrown. The applicant had a fantastic Forest Management plan is obviously working with a forestry expert already to manage forest health, so we have no comments to add on that topic. We did not see an Firewise plans for when house construction begins, so we would like to see the following implemented to assist with these issues: A) Vegetation management consistent with Firewise principles, including clearing trees and brush within approximately 35 feet of the proposed building. Trees should also be cleared to approximately 15 feet from the centerline on each side of all driveways, which is critical for safe emergency vehicle access and for faster emergency egress of residence in the event of a wildfire. B) Thinning forested areas within 35–100 feet beyond the proposed houses (as recommended by Firewise practices) to approximately 40–60 trees per acre, reflecting a healthy Ponderosa pine and Douglas fir forest density based on U.S. Forest Service and Colorado State Forest Service guidance. This also supports improved fire resilience, wildlife habitat, and visual quality consistent with the El Paso County Master Plan for this area. If these measures are added to the project's plan, then the El Paso County Conservation District will be content with the applicant's commitment to soil conservation, watershed protection, and protection of the surrounding community. For any questions, please feel free to contact the EPCCD at 719-600-4706 or Will Vogl - Board VP at Will@EPCCD.org
PCD Project Managerreview 1Jul 21, 2026
V1: Water Resources Report
View attached comment letter
PCD Project Managerreview 1Jul 21, 2026
V1: TIS
View attached comment letter
PCD Project Managerreview 1Jul 21, 2026
V1: PUDSP
View attached comment letter
PCD Project Managerreview 1Jul 21, 2026
V1: PCM Form
View attached comment letter
PCD Project Managerreview 1Jul 21, 2026
V1: Letter of Intent
View attached comment letter
PCD Project Managerreview 1Jul 21, 2026
V1: Drainage Report
View attached comment letter
PCD Project Managerreview 1Jul 21, 2026
Review 1: PCD Planning Division comments have been provided (in green) on the following uploaded documents: - Letter of Intent - PUDSP - Waster Resources Report PCD Project Manager has also uploaded the following documents with Engineering and Stormwater comments: - Drainage Report - PCM Applicability Form - TIS
EPC DPW Development Services - Engineeringreview 1Jul 21, 2026
DPW Engineering review 1 has comments on the following documents - Letter of Intent - Traffic Impact Study - Drainage Report - Preliminary - PUD Development Plan Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 Laura Besler, PE laurabesler@elpasoco.com
EPC DPW Stormwaterreview 1Jul 21, 2026
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s), to be uploaded by the PM: - Drainage Report - PCM Applicability Form Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
Colorado Geological Surveyreview 1Jul 21, 2026
View attached comment letter
Colorado Geological Surveyreview 1Jul 21, 2026
View attached comment letter
Colorado Geological Surveyreview 1Jul 21, 2026
View attached comment letter
Colorado Geological Surveyreview 1Jul 21, 2026
View attached comment letter
Colorado Geological Surveyreview 1Jul 21, 2026
View attached comment letter
Colorado Geological Surveyreview 1Jul 21, 2026
View attached comment letter
PCD Administrative Noticereview 1Jul 20, 2026
On 07/20/2026, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (14 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $10.92. JM
Black Forest Land Use Committeereview 1Jul 15, 2026
The Black Forest Land Use Committee commends the applicant for returning to the 5-acre average for lots in Flying Horse North. We strongly believe this will make a most beautiful and appealing residential development. We support and approve this filing.
Black Forest Fire Protection Districtreview 1Jul 14, 2026
BFFR accepts the proposed amendment based on the access and fire water supply discussions previously held with the applicant, design team, fire protection consultant, and BFFR representatives. The approval is based on the understanding that the project will be constructed and maintained in accordance with the access and water supply approach discussed and agreed upon during those meetings. From a fire apparatus access standpoint, the submittal identifies a new roadway serving the 11 lots with a cul-de-sac and a total road length of less than 1,000 feet. Fire apparatus access shall comply with the currently adopted **International Fire Code**, including **IFC Section 503**, applicable IFC appendices, El Paso County requirements, and BFFR standards. Access roads shall provide an approved all-weather surface, minimum unobstructed width, minimum vertical clearance of 13 feet 6 inches, acceptable grade, turning radius, and load-bearing capacity for BFFR apparatus, including engines, ambulances, brush apparatus, and water tenders. The proposed cul-de-sac and roadway layout are acceptable at this stage provided the final construction documents maintain fire apparatus access compliance and do not create access restrictions. For fire protection water supply, BFFR reviewed the Fire Protection Report prepared for Filing No. 9. The report identifies the existing fire hydrant at the Flying Horse North clubhouse as the primary pressurized water source for fire protection support. The report states that this hydrant is supplied by the irrigation pump system located west of the clubhouse and is capable of providing a minimum of **500 gpm at 20 psi**. The report also states that the pump house contains three 750 gpm pumps, with total available pump capacity up to 2,250 gpm. The clubhouse hydrant is identified as being approximately one-half mile from the furthest lot within Filing No. 9. This water supply approach is consistent with the discussions and agreements reached with BFFR and is accepted provided the hydrant, pump system, and access remain available, maintained, and operational for fire department use. The Fire Protection Report identifies two required access improvements related to the fire water supply. First, approved Knox access shall be provided at the clubhouse and pump house gates so BFFR and mutual aid companies can access the hydrant and pump house during an emergency. Second, the parking space closest to the clubhouse hydrant shall be marked as a fire lane to maintain unobstructed access to the hydrant. BFFR agrees with these requirements. These items shall be completed and maintained prior to final fire acceptance or as otherwise approved by the BFFR AHJ. The project is located within the Black Forest wildland-urban interface area. The submitted wildfire report classifies the Filing No. 9 area as a low fire intensity classification based on current fuels, topography, surrounding golf course fuel breaks, and proposed mitigation. All future homes, accessory structures, and site improvements shall comply with the adopted Colorado Wildland Urban Interface / Wildfire Resiliency Code, adopted building code, adopted International Fire Code, and BFFR requirements in effect at the time of building permit. Defensible space, vegetation management, ignition-resistant construction, and driveway access shall be maintained for the life of the development. Black Forest Fire Rescue recommends **acceptance with conditions**. Acceptance is contingent upon maintaining the agreed-upon fire apparatus access, maintaining the clubhouse hydrant and pump house water supply for fire department use, installing approved Knox access at required gates, marking and maintaining the hydrant access area as a fire lane, and complying with all applicable IFC, WUI, addressing, driveway, and BFFR requirements. Any material change to the proposed access layout or fire water supply method shall be resubmitted to BFFR for review and approval.
Mountain View Electric Association, Inc.review 1Jul 13, 2026
See attached comment letter
View attached comment letter
Colorado Springs Public Worksreview 1Jul 13, 2026
Engineering Development Review will require all public improvements to be built to full City Standards if this is chosen for pre-annexation per the IGA. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov
Colorado Parks and Wildlifereview 1Jul 10, 2026
View attached comment letter
Colorado Parks and Wildlifereview 1Jul 10, 2026
View attached comment letter
Colorado Parks and Wildlifereview 1Jul 10, 2026
View attached comment letter
Colorado Parks and Wildlifereview 1Jul 10, 2026
View attached comment letter
Colorado Parks and Wildlifereview 1Jul 10, 2026
View attached comment letter
Colorado Parks and Wildlifereview 1Jul 10, 2026
View attached comment letter
Colorado Springs Public Worksreview 1Jul 8, 2026
Traffic Engineering has no comments on this item. Brian Shevock Public Works/Traffic Engineering Traffic Engineer II City of Colorado Springs brian.shevock@coloradosprings.gov
Academy School District 20 Building Fundreview 1Jul 6, 2026
Academy District 20 is in receipt of File #PUDSP263 for approval of the Flying Horse North PUD/SP Amendment (Major/Filing 9). The District is requesting fees in lieu of land dedication per the existing County Code for all residential units within this development. The District is able to serve each student who is a resident of District 20. If you need additional information, please contact me. Peter Ristig Executive Director for Operations Academy School District
EPC Environmental Servicesreview 1Jul 1, 2026
View attached comment letter
EPC Environmental Servicesreview 1Jul 1, 2026
View attached comment letter
EPC Environmental Servicesreview 1Jul 1, 2026
View attached comment letter
EPC Environmental Servicesreview 1Jul 1, 2026
View attached comment letter
EPC Environmental Servicesreview 1Jul 1, 2026
View attached comment letter
EPC Environmental Servicesreview 1Jul 1, 2026
View attached comment letter
E911 Authority - El Paso/Teller Countyreview 1Jul 1, 2026
Comments for E911 as follows: Sorraia Way – Acceptable and reserved No other action for E911 on this submittal. Thank you. Justin
Pikes Peak Regional Building Departmentreview 1Jun 30, 2026
1. An email from Justin Annan jannan@eptc911.org; or Glenn West gwest@eptc911.org;, with El Paso-Teller County E-9-1-1 Authority, reserving the street names is required to be emailed to the Enumerations department. Amy Vanderbeek Amy@pprbd.org; Brent Johnson Brent@pprbd.org; or Becky Allen BeckyA@pprbd.org 2. Contact Enumerations when you are ready to have addresses assigned. 3. If underground service is needed prior to plat, submit a Utilities Addressing Plan (UAP), to Colorado Springs Utilities via the related link at https://www.csu.org/Pages/GISMapping.aspx For more information contact: Jade Swan jswan@csu.org Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org
Colorado Department of Transportation - Pueblo Officereview 1Jun 30, 2026
All required improvements at Stagecoach Road and State Highway 83 have been constructed with the first phase of Flying Horse North. There is a current CDOT Access Permit (#218037) for Stagecoach Road and State Highway 83. No further action is required. Please refer to the attached letter.
View attached comment letter
Colorado Springs Planning & Community Developmentreview 1Jun 30, 2026
City Planning has no comment.

Land ownership timeline

The documented chain of ownership per parcel, from El Paso County Assessor records and TriLakes Growth's monthly re-checks. Where the record hasn't been collected yet, the gap is shown rather than papered over.

Timeline