Hidden Creek Estates Subdivision
Final plat application to create six (6) residential single-family lots. Previously known as "Hay Creek Subdivision Filing 2"
- Location
- HAY CREEK RD, 80921
- Jurisdiction
- El Paso County
- Applicant
- Vertex Consulting Services Nina Ruiz
- Land owner (assessor)
- 3405 HAY CREEK LLC (state record)
- County project manager
- Joe Letke
- Filed
- Jan 10, 2024
- Parcel
- 7133007025
- Map
-
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
- Area map
- See all Tri-Lakes projects on the map
- Source record
- El Paso County EDARP file
Documents (113)
BOCC Hearing AgendaadditionalJan 6, 2026
Hearing Agenda for the Board of County Commissioners hearing on 01/08/2026. JM
BOCC Staff Report - final with attachmentsadditionalDec 23, 2025
Staff Report for the Board of County Commissioners hearing on 01/08/2026. JM
Signed PC ResolutionadditionalDec 22, 2025
Recommendation from the Planning Commission hearing on 12/18/2025. JM
Affidavit of Published Legal AdvertisementadditionalDec 16, 2025
P2413 AFFIDAVIT FOR PUBLISHED LEGAL. Gazette 12-11-2025
PC Staff Report - final with attachmentsadditionalDec 15, 2025
Staff Report for the Planning Commission hearing on 12/18/2025. JM
PC Hearing AgendaadditionalDec 15, 2025
Hearing Agenda for the Planning Commission hearing on 12/18/2025. JM
PC & BOCC PosteradditionalDec 4, 2025
Poster for the Planning Commission hearing on 12/18/2025 and the Board of County Commissioners hearing on 01/08/2026. JM
Mailing Labels - Hearing NoticeadditionalDec 4, 2025
Mailing Labels for the 11 surrounding property owners that received notices. PCD mailed the letters on 12/04/2025. Cost = $8.14. JM
Hearing Notice & Vicinity MapadditionalDec 4, 2025
Hearing Notice for the Planning Commission hearing on 12/18/2025 and the Board of County Commissioners hearing on 01/08/2026. JM
Notice of ApplicationadditionalJan 28, 2025
Notice of Application letters were mailed to surrounding property owners on 1/28/2025. JM
Mailing LabelsadditionalJan 28, 2025
Mailing Labels for the 11 surrounding property owners that received notices. Cost = $7.59. JM
Agency review comments (125)
EPC Stormwater Reviewreview 10Sep 10, 2026
Review 10: EPC DPW Stormwater comments have been resolved on the following document(s):
- ESQCP
- FAE
- GEC Plan
EPC DPW Stormwater has no further comments. EPC Project Manager: no re-review necessary.
Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
County Attorney - Development Reviewreview 9Sep 9, 2026
No comments from County Attorney - Development Review at this time.
Reviewed by: Erika Keech, Sr. County Attorney, erikakeech2@elpasoco.com.
PCD Project Managerreview 8Aug 18, 2026
Planning has no further comments.
Joe Letke
Planner
JoeLetke@elpasoco.com
EPC Stormwater Reviewreview 9Aug 18, 2026
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s):
- ESQCP
- FAE
- GEC Plan
Please provide the following document(s) upon resubmittal (the planner will need to send an upload request):
- GEC Checklist
Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
PCD Engineering Divisionreview 8Aug 17, 2026
No engineering comments.
County Attorney - Waterreview 9Aug 14, 2026
Comments from 7/24/26 are still outstanding.
Lori Seago
Sr. County Attorney
loriseago@elpasoco.com
County Attorney - Waterreview 8Jul 24, 2026
Please carefully review the requirements in the Water Supply Review. They have not yet been met. Among other things, an HOA must be formed, the covenants must assign certain responsibilities and authorities to the HOA, the augmentation plan and sufficient Arapahoe and L-FH water must be conveyed to the HOA, the form deeds to lot owners must be in the amounts and contain the language set forth in the requirements.
Lori Seago
Sr. County Attorney
loriseago@elpasoco.com
Mountain View Electric Association, Inc.review 8Jul 20, 2026
MVEA has no further comments.
PCD Engineering Divisionreview 7Jul 19, 2026
No engineering comments. See comments from planner on the final plat.
reviewed by:
Daniel Torres
danieltorres@elpasoco.com
PCD Project Managerreview 7Jul 14, 2026
Planning has comments on the following version 7 documents:
-Final Plat
Joe Letke
Planner
JoeLetke@elpasoco.com
(documents will be uploaded by DPW engineering)
County Attorney - Waterreview 7Feb 12, 2026
The conditions in Requirement J of the Water Supply Review have been met. Compliance with the other Requirements remains pending.
County Attorney - Development Reviewreview 7Jan 29, 2026
Review # 7: No additional comments from County Attorney - Development Review at this time.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)review 5Dec 16, 2025
The USFWS already concurred with the determination that this Project may affect, but is not likely to adversely affect, the Preble's meadow jumping mouse on 6/5/2025. No further concerns.
County Attorney - Waterreview 6Dec 15, 2025
See attached Water Supply Review and Recommendations.
Colorado Division of Water Resourcesreview 6Dec 11, 2025
DWR Response Letter
Tri-Lakes-Monument Fire Protection Districtreview 6Dec 1, 2025
No additional comment
PCD Engineering Divisionreview 6Nov 25, 2025
No additional comments
Daniel Torres
danieltorres@elpasoco.com
PCD Project Managerreview 6Nov 25, 2025
Planning has no comments.
Joe Letke
Planner
JoeLetke@elpasoco.com
EPC Fire and Wildfire Program Managerreview 6Nov 24, 2025
The water on wheels from Monument Fire arrives with is the limit of the size of structure that can be built. This will be evaluated with each Site Plan submitted for the development.
County Attorney - Development Reviewreview 6Nov 18, 2025
Memorializing our understanding that a shared cistern is no longer needed/desired for this application. No additional comments from County Attorney – Development Review at this time.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
Tri-Lakes-Monument Fire Protection Districtreview 5Nov 6, 2025
No additional comments
EPC Stormwater Reviewreview 5Nov 4, 2025
Review 4: EPC DPW Stormwater comments have been resolved on the following document(s):
- CDs
- PBMP Applicability Form
- Drainage Report
EPC DPW Stormwater has no further comments. EPC Project Manager: no re-review necessary.
Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
719.675.2654
GlennReese@elpasoco.com
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
PCD Engineering Divisionreview 5Nov 3, 2025
Review 4: Provided that there are no additional comments by the stormwater engineer, the engineering documents will be routed to the ECM administrator for approval.
reviewed by:
Daniel Torres
danieltorres@elpasoco.com
PCD Project Managerreview 5Nov 3, 2025
Planning has no further comments. Additional redline documents may be uploaded by engineering.
Joe Letke
Planner
JoeLetke@elpasoco.com
PCD Project Managerreview 5Nov 3, 2025
-V4 Wildland fire and hazard mitigation plan
EPC Fire and Wildfire Program Managerreview 5Nov 3, 2025
Fire Safety and Wildfire Mitigation Program comments added to the following documents
- Wildland Fire and Hazard Mitigation Plan
Roland Peterson
Fire Safety and Wildfire Mitigation Program Manager
Planning & Community Development
719.520.6075
rolandpeterson@elpasoco.com
County Attorney - Waterreview 5Nov 3, 2025
The water totals listed in 9. of the Water Supply Information Summary "Use" and "Water Requirements" are different. Please fix it so they match. The County Attorney's Office will review once a letter has been received from the Colorado Division of Water Resources that shows water sufficiency for this project.
County Attorney - Development Reviewreview 5Oct 30, 2025
County Attorney comments from 7/29/25 in the Shared Fire Cistern Agreement have not been addressed. Please address them and resubmit the Shared Fire Agreement for review.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com
PCD Project Managerreview 4Jul 30, 2025
V3_Wildland Fire and Hazard Mitigation Plan Response
PCD Project Managerreview 4Jul 30, 2025
V3_Wildland Fire & Hazard Mitigation Plan
PCD Project Managerreview 4Jul 30, 2025
V3_Construction Drawings (PlansProfiles)
PCD Project Managerreview 4Jul 30, 2025
V3_Fire Protection Report Response
PCD Engineering Divisionreview 4Jul 30, 2025
Review 3 comments on the following documents shall be uploaded:
-Final Drainage Report
-CD
-Final Plat
-Letter of Intent
-FAE
-Roadway Variance Request: A variance request is not needed. A deviation request form shall be submitted for the proposed deviations for consideration by the ECM administrator.
reviewed by:
Daniel Torres
danieltorres@elpasoco.com
County Attorney - Development Reviewreview 4Jul 29, 2025
Edits to Shared Fire Agreement attached.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
PCD Project Managerreview 4Jul 29, 2025
Planning has outstanding V1, V2, and new V3 comments on the following documents:
-LOI
-Plat Drawing
-Wildand Fire and Hazard Mitigation Plan
-Soils and Geology Report
-Shared Fire Agreement (not signed)
Joe Letke
Planner
joeletke@elpasoco.com
Colorado Geological Surveyreview 4Jul 29, 2025
No additional comments on the updated referral comments. See prior comments on 4/17/2025.
EPC Fire and Wildfire Program Managerreview 4Jul 29, 2025
Fire comments provided on the following documents:
-Final Plat Drawings
-Fire Protection Report Response
-Wildland Fire and hazard Mitigation Plan Response
The Wildland Fire and Hazard Mitigation Plan is still showing the wrong acreage and shape for the project. It appears there has been no change to this report.
County Attorney - Waterreview 4Jul 28, 2025
County Attorney’s Office will review for water sufficiency following receipt of updated findings from the Colorado Division of Water Resources. Thank you.
EPC Stormwater Reviewreview 4Jul 28, 2025
Review 3: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) that will be uploaded by the PM and/or DS Engr:
- CDs
- Drainage Report
- PBMP Applicability Form
EPC DPW Stormwater comments have been resolved on the following document(s):
- FAE
Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
719.675.2654
GlennReese@elpasoco.com
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
Tri-Lakes-Monument Fire Protection Districtreview 4Jul 21, 2025
No additional comments.
Pikes Peak Regional Building Departmentreview 4Jul 16, 2025
Standard final plat comments still apply. See prior comments for details.
Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
Monumentreview 4Jul 15, 2025
After reviewing the documents, the Town of Monument has no additional comments to offer.
Tri-Lakes-Monument Fire Protection Districtreview 3May 1, 2025
Water supply letter
911 Authority - El Paso/Teller Countyreview 3May 1, 2025
Comments for E911 as follows:
Golden Valley View is available, and has been reserved for this project.
No other action for E911 on this submittal.
Thank you
Justin
Colorado Division of Water Resourcesreview 3Apr 22, 2025
DWR Comment Letter
County Attorney - Waterreview 2Apr 21, 2025
1. It appears that the WSIS conflates demand and supply to some extent. Understanding, for example, that the lot drawing from the Dawson aquifer may withdraw up to 0.972 AF/year per the decree, that isn’t necessarily the estimated demand. Please use the WSIS to summarize the estimated demand of the subdivision as a whole; for example, the first line in section 9 should be 6 units at 1.56 AF/year. Each line thereafter will set forth the total subdivision demand for that category of use.
2. If lots will have different demand amounts, that needs to be more fully explained in the Water Resource Report. Also, please further explain the uses for a pond and firefighting and how those demand amounts were calculated.
3. Please provide a deed showing water ownership in the current property owner’s name.
County Attorney - Development Reviewreview 2Apr 21, 2025
County Attorney’s office will review the Shared Fire Agreement in a later referral after the EPC Fire and Wildlife Program Manager’s comments have been addressed.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
PCD Engineering Divisionreview 2Apr 17, 2025
Review 2 comments on the following documents shall be uploaded:
-Final Drainage Report
-CD
-Final Plat
-Letter of Intent
-FAE
reviewed by:
Daniel Torres
danieltorres@elpasoco.com
PCD Project Managerreview 2Apr 17, 2025
-Wildfire & Hazard Mitigation Plan
EPC Fire and Wildfire Program Managerreview 3Apr 17, 2025
Fire Safety and Wildfire Mitigation has comments on the following:
-Wildland Fire and Hazard Mitigation Plan
-Final Plat Drawings
Documents to be uploaded by project manager
Roland Peterson
Fire Safety and Wildfire Mitigation Program Manager
Planning & Community Development
719.520.6075
https://planningdevelopment.elpasoco.com/
PCD Project Managerreview 2Apr 17, 2025
Major V1 comments remain unaddressed in V2. Due to the number of repeat and new comments in V2, there may be additional comments in V3. Please note that Roland Peterson, PCD Fire Safety and Wildfire Mitigation Program Manager, issued comments in red text.
-Application Form
-LOI
-Plat Drawings
-Fire Protection Report
-Construction Drawings
-Shared Fire Agreement
-Soils and Geology Report
-Wildland Fire and Hazard Mitigation Plan
Joe Letke
Planner
joeletke@elpasoco.com
Colorado Geological Surveyreview 3Apr 17, 2025
With this referral, we received the Final Plat (Polaris Surveying, Inc., March 20, 2025), Drainage Report (All Terrain Engineering, March 2025), and Soil and Geology Study and Wastewater Study (Rocky Mountain Group (RMG), March 20, 2025).
Hay Creek traverses the site and is mapped as a FEMA floodplain with potentially unstable slopes associated with its banks. This area is mapped on the final plat as a “no-build area/floodplain.” The building improvements should be located outside this no-build zone. An access road will cross the FEMA floodplain, with a proposed culvert planned at the intersection of Hay Creek.
Geologic Hazards and Steep Slopes: RMG states (page 20), “Geologic hazards found to be present at this site include faults and seismicity. Geologic conditions found to be present at this site include potentially compressive and expansive soils, FEMA floodplain, and potentially seasonally fluctuating water.” Debris fans/flows should also be included in this statement.
RMG has mapped steep slopes (ss) to the south of the site. The proposed lots contain slopes up to approximately 24 percent and RMG states (page 16), “no portions of the lots require a “no-build” designation due to steep slopes.” CGS agrees with RMG, “If the future proposed structures were to encroach upon the toe (bottom) of the slope, additional investigations may be required to verify the slope is stable prior to construction,” and “any new long-term cuts or fills should be no steeper than 3:1 without specific slope analysis.”
In the wastewater study, RMG shows proposed locations for the OWTS and buildings on FIG-5 (Septic Suitability Map). It would be prudent for the county to recommend that these locations be included in the final plat. Additionally, note 8 of the final plat should be updated to reference RMG’s report (finalized version) and include the geologic hazards/conditions associated with the site, along with mitigation measures. CGS recommends that this note be updated prior to approval of the final plat.
Debris Fans/Debris Flow Susceptibility: Based on debris flow susceptibility mapping (CGS, OF-18-11), small drainages emanating from the steep slopes to the north and south of the site are areas of debris flow hazards. The site soils are also mapped as colluvium and sheetwash alluvium deposits (Keller, J.W., 2006, CGS, OF-06-06). These areas may be affected by erosion, flooding, sediment-laden flows, and erosion following heavy precipitation. The lots affected by these hazards include Lots 2-4 (based on the final plat). RMG’s final report includes FIG-8 (Engineering and Geology Map), which shows mapped areas designated with debris flows (df), specifically Lot 4. Erosional setbacks from these mapped debris fans/flows should be established. Building and OWTS locations should not be located within areas designated with a mapped geologic hazard/constraint. CGS recommends including debris flow hazards in the final plat (note 8) along with the affected lots and mitigation measures (as appropriate).
Submitted 4/17/2025 by Amy Crandall, Engineering Geologist, Colorado Geological Survey (303-384-2632 or acrandall@mines.edu)
USAFA Base Plannerreview 3Apr 8, 2025
Thank you for sending USAFA the “Hidden Creek Estates Subdivision” project review request (File #: SF253). After reviewing the documents, we have determined that USAFA does not have any additional comments.
EPC Stormwater Reviewreview 2Apr 3, 2025
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) that will be uploaded by the PM and/or DS Engr:
- CDs
- Drainage Report
- FAE
- PBMP Applicability Form
EPC DPW Stormwater comments have been resolved on the following document(s):
- GEC Checklist
Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
719.675.2654
GlennReese@elpasoco.com
Tri-Lakes-Monument Fire Protection Districtreview 2Apr 1, 2025
No additional comment on this project.
Pikes Peak Regional Building Departmentreview 2Apr 1, 2025
1. Golden Valley View street name has not been approved by El Paso-teller County E-91-1 Authority. Enumerations requires an email from this department to move forward with the use of the street name.
2. Contact Enumerations when you are ready to have addresses assigned. Once received the addresses will need to be on the plat.
3. Standard Final Plat comments:
a. Enumerations will review the pre-plat (mylar) prior to plat for address placement, street names, and title block.
b. A $10.00 per lot and tract platting fee will be due at the time of the review of the pre-plat, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department. As of December 5th 2023, the fee for all credit/debit cards has changed from the flat 2.95% fee to the following: Over the phone Credit/Debit Card payments will be 2.3% and In-Person Debit Card payments will be 1.5% (in-person only).
c. Pre-plat reviews can be reviewed via “pdf” or in-person. The pre-plat will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations stamping the pre-plat and receiving payment of plat fees. If any pre-plat changes occur, even if changes do not apply to Enumerations, we still need to re-stamp the pre-plat. The Enumerations stamped pre-plat copy should match the recorded document minus a few signatures. If you would like an in-person review, please make an appointment on our website, https://www.pprbd.org/Home/BookAppt
d. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Please email the Enumerations staff member that reviewed your project. Amy@pprbd.org; Brent@pprbd.org; or BeckyA@pprbd.org
Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
Tri-Lakes-Monument Fire Protection Districtreview 2Mar 31, 2025
No additional comment
RBD Floodplainreview 2Mar 28, 2025
comments addressed no further comment on this submittal.
please coordinate the floodplain permit for the Zone A crossing with :
Keith Curtis, PE, CFM
Floodplain Administrator
Pikes Peak Regional Building Department
2880 International Circle
Colorado Springs CO, 80910
O: 719-327-2898
USAFA Base Plannerreview 2Mar 17, 2025
Thank you for sending USAFA the “Hay Creek Subdivision” project review request (File #: SF253). The new documents provided clarity on our previous concern about stormwater and Preble’s mouse habitat. We have also reviewed the applicant’s Wildfire Hazard & Mitigation Plan, Fire Protection Report, and Evacuation Plan. We wish to reiterate that wildfire on or near USAFA is a primary risk to mission readiness at USAFA. Additional residences in the wildland-urban interface area increases the risk; therefore, we are especially attuned to potential effects of development density and availability of emergency ingress/egress.
PCD Engineering Divisionreview 1Feb 18, 2025
Final Drainage Report Comments
PCD Engineering Divisionreview 1Feb 18, 2025
Review 1 comments on the following documents shall be uploaded:
-Final Drainage Report
-CD
-Final Plat
-FAE
-Letter of Intent
-GEC Checklist
-PBMP Applicability Form
reviewed by:
Daniel Torres
danieltorres@elpasoco.com
Mountain View Electric Association, Inc.review 1Feb 17, 2025
See attached comments
PCD Project Managerreview 1Feb 13, 2025
Planning has comments on the following version 1 documents:
-Access, Ingress, Egress, and Evac Plan
-Application Form
-Plat Drawings
-HOA Bylaws
-Fire Protection Report
-Letter of Intent
-OWTS Report
-Shared Fire Agreement (incomplete)
-Soils and Geology Report
-Title Commitment (incomplete)
-Wildland Fire & Hazard Mitigation Plan
The engineering services team will upload joint planning and engineering documents, such as the plat drawings, LOI, and engineering-specific documents.
Joe Letke
Planner
joeletke@elpasoco.com
PCD Project Managerreview 1Feb 13, 2025
-Access, Ingress, Egress, and Evacuation Plan
PCD Project Managerreview 1Feb 13, 2025
-Title Commitment (Current within 30 days of submittal)
EPC Stormwater Reviewreview 1Feb 13, 2025
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) that will be uploaded by the PM and/or DS Engr:
- CDs
- Drainage Report
- FAE
- GEC Checklist
- PBMP Applicability Form
Note that I spoke with the applicant (Nina Ruiz) on 2/10 and she stated that since the proposed soil disturbance is 0.99ac, they would not like to get an ESQCP at this time "just in case" disturbances end up exceeding 1ac during construction. However, if requested changes with this review end up increasing the disturbances to >1ac, then all ESQCP-related and likely PCM-related docs will be required. I also discussed this caveat with the project engineer Ryan Burns on 2/13. With all that in mind, I did provide some preliminary comments on the docs listed above but will need to do a more in-depth review once it is decided if an ESQCP or PCM is definitely required. The SWMP however was not reviewed at this time.
Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
719.675.2654
GlennReese@elpasoco.com
Colorado Geological Surveyreview 1Feb 13, 2025
With this referral, we received the Final Plat (Polaris Surveying, Inc., December 4, 2024), Construction Documents (All Terrain Engineering, September 16, 2024), Letter of Intent (Vertex Consulting Services, LLC, September 29, 2024), and Soil and Geology Study and Wastewater Study (Rocky Mountain Group (RMG), Undated (watermarked Preliminary Use Only)). CGS recommends that the RMG’s report be finalized prior to approval of the final plat.
Hay Creek traverses the site and is mapped as a FEMA floodplain with potentially unstable slopes associated with its banks. This area is mapped on the final plat as a “no-build area/floodplain.” The building improvements should be located outside this no-build zone. An access road will cross the FEMA floodplain, with a proposed culvert planned at the intersection of Hay Creek.
Geologic Hazards and Steep Slopes: RMG states (page 19), “Geologic hazards found to be present at this site include faults and seismicity. Geologic conditions found to be present at this site include potentially compressive and expansive soils, FEMA floodplain, and potentially seasonally fluctuating water.” RMG has mapped steep slopes (ss) to the south of the site. The proposed lots contain slopes up to approximately 24 percent and RMG states (page 16), “no portions of the lots require a “no-build” designation due to steep slopes.” CGS agrees with RMG, “If the future proposed structures were to encroach upon the toe (bottom) of the slope, additional investigations may be required to verify the slope is stable prior to construction,” and “any new long-term cuts or fills should be no steeper than 3:1 without specific slope analysis.” It would be prudent for the county to recommend that proposed building envelopes be included in the final plat. Additionally, note 8 of the plat should be updated to reference RMG’s report (finalized version) and include the geologic hazards/conditions associated with the site along with mitigation measures. CGS recommends that this note be updated prior to approval of the final plat.
Debris Fans/Debris Flow Susceptibility: Based on debris flow susceptibility mapping (CGS, OF-18-11), small drainages emanating from the steep slopes to the north and south of the site are areas of debris flow hazards. The site soils are also mapped as colluvium and sheetwash alluvium deposits (Keller, J.W., 2006, CGS, OF-06-06). These areas may be affected by erosion, flooding, sediment-laden flows, and erosion following heavy precipitation. Erosional setbacks from these mapped debris flows should be established. The lots affected by these hazards include Lots 2-4 (based on the final plat). CGS recommends the hazards associated with the mapped debris fans should be evaluated and mitigation measures (if deemed necessary) be provided in an updated report and included in the final plat.
Submitted 2/13/2025 by Amy Crandall, Engineering Geologist, Colorado Geological Survey (303-384-2632 or acrandall@mines.edu)
USAFA Base Plannerreview 1Feb 13, 2025
Thank you for sending USAFA the “Hay Creek Subdivision” project review request (File #: SF253). After reviewing the provided documents, it was determined that the project is not located on USAFA's boundary line, which minimizes the risk of direct impacts to USAFA's mission. However, there are a few potential cumulative impacts that should be highlighted. Please refer to the official letter posted for your review.
County Attorney - Development Reviewreview 1Feb 13, 2025
Please provide the Shared Fire Agreement in Word so that suggested edits may be provided.
Lori Seago
Sr. County Attorney
loriseago@elpasoco.com
Parks Advisory Boardreview 1Feb 12, 2025
El Paso County Parks and Community Services Department, Final Comments - Please See Attached Documentation (Endorsed by the Park Advisory Board on February 12, 2025)
Tri-Lakes-Monument Fire Protection Districtreview 1Feb 12, 2025
The fire department would prefer that the access road to lot six pass through the existing lot 1 access and not through the proposed private road that services the remaining lots. The fire department accepts the plan to share a cistern with the proposed neighboring development (O'Leary), but will require a written agreement allowing access between the two developers.
County Attorney - Waterreview 1Feb 11, 2025
Please resubmit a WSIS that matches the information provided in the Water Resource Report/Decree. The Count Attorney’s Office will then review after a letter of sufficiency is received from the Colorado Division of Water Resources.
EPC Parks Departmentreview 1Jan 30, 2025
El Paso County Parks and Community Services Department, Preliminary Comments - Please See Attached Documentation (To be presented to the Park Advisory Board for endorsement on February 12, 2025)
PCD Administrative Noticereview 1Jan 28, 2025
On 01/28/2025, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (11 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $7.59. JM
Pikes Peak Regional Building Departmentreview 1Jan 27, 2025
1. With the box in the center of lots 2-6 it is confusing to know where the lots start and stop. What is the purpose of this dashed box spanning from lots 2-6? Is the access easement area with in this boxed area? Can a driveway be in a no build area? It is not clear where each lot will access.
2. The access drive is much to far from the main road and should have a unique name assigned to it. Contact El Paso-teller County E-9-1-1 Authority to get a street name assigned.
3. Miss spelling in note 15.
4. Once the access is made clear , addresses will need to be assigned. Contact Enumerations when you are ready for addresses to each lot.
Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930 E: Amy@pprbd.org
911 Authority - El Paso/Teller Countyreview 1Jan 27, 2025
Comments for E911 as follows:
The access intended for lots 2-6 should be assigned a streetname.
Streetnaming information (criteria, existing/reserved names) can be found at:
https://elpasoteller911.org/191/Street-Name-Database
The development drawings also do not clearly depict how this road is intended to reach lots 5 and 6.
Please make adjustments to clearly indicate the access to all lots.
Thank you
Justin
RBD Floodplainreview 1Jan 24, 2025
The parcel is located within the current effective Zone A floodplain with no BFEs(no supporting model available). Draft model backed BFEs for this area have been developed as part of Phase 1 for the ongoing El Paso County, CO, Risk MAP Project”. The data has been reviewed and approved through FEMA’s QA/QC process (May 11, 2022) and is currently in the MIP (Case No. 19-08-0037s). The Phase 1/Base Level Engineering outputs and Zone A ready deliverables are, under the following folder:
K:/FY2019/19-08-0037S/Discovery - BLE - El Paso and Teller Counties, CO - FY18 - 04/Discovery Data Capture - Discovery Data Capture - El Paso and Teller Counties, CO - 01/El Paso_Discovery_1
1)BFEs from the aforementioned study should be shown on the final plat to comply with RBC 313.18.5
2) Provide less than 6" rise certification for A zone Crossing
contact Keith Curtis 719-327-2898 with questions, keith@pprbd.org
Land ownership timeline
- Aug 20, 2025Parcel 7133007025 acquired by 3405 HAY CREEK LLC (state record) for $10 (assessor record)
Timeline
- Sep 23, 2026Submission request sent to Applicant
- Sep 10, 2026Request for Review Comments returned by EPC Stormwater Review
- Sep 9, 2026Request for Review Comments returned by County Attorney - Development Review
- Aug 27, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Zachary Jannusch on behalf of EPC Stormwater Review
- Aug 27, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Mikayla Hartford on behalf of EPC Stormwater Review
- Aug 27, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Glenn Reese on behalf of EPC Stormwater Review
- Aug 27, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erica Rylander on behalf of EPC Stormwater Review
- Aug 27, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Christina Prete on behalf of EPC Stormwater Review
- Aug 27, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Development Review
- Aug 27, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Development Review
- Aug 27, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Development Review
- Aug 27, 2026Submission Triaged
- Aug 27, 2026Submission received from Applicant
- Aug 24, 2026Submission request sent to Applicant
- Aug 18, 2026Request for Review Comments returned by EPC Stormwater Review
- Aug 18, 2026Request for Review Comments returned by PCD Project Manager
- Aug 17, 2026Request for Review Comments returned by PCD Engineering Division
- Aug 14, 2026Request for Review Comments returned by County Attorney - Water
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Zachary Jannusch on behalf of EPC Stormwater Review
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Mikayla Hartford on behalf of EPC Stormwater Review
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Glenn Reese on behalf of EPC Stormwater Review
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Christina Prete on behalf of EPC Stormwater Review
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erica Rylander on behalf of EPC Stormwater Review
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Water
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Water
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Water
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Justin Kilgore on behalf of PCD Project Manager
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Gilbert LaForce on behalf of PCD Engineering Division
- Aug 4, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Engineering Manager on behalf of PCD Engineering Division
- Aug 4, 2026Submission Triaged
- Jul 30, 2026Submission received from Applicant
- Jul 24, 2026Request for Review Comments returned by County Attorney - Water
- Jul 21, 2026Submission request sent to Applicant
- Jul 21, 2026Submission Triaged
- Jul 21, 2026Submission request sent to Applicant
- Jul 21, 2026Submission received from Applicant
- Jul 21, 2026Submission request sent to Applicant
- Jul 21, 2026Submission request sent to Applicant
- Jul 21, 2026Submission Triaged
- Jul 21, 2026Submission received from Applicant
- Jul 21, 2026Submission request sent to Applicant
- Jul 20, 2026Request for Review Comments returned by Mountain View Electric Association, Inc.
- Jul 19, 2026Request for Review Comments returned by PCD Engineering Division
- Jul 14, 2026Request for Review Comments returned by PCD Project Manager
- Jul 14, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by General Email on behalf of Mountain View Electric Association, Inc.
- Jul 2, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Water
- Jul 2, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Water
- Jul 2, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Water
- Jul 2, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Water
- Jul 2, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Water
- Jul 2, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Water
- Jul 2, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Justin Kilgore on behalf of PCD Project Manager
- Jul 2, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Gilbert LaForce on behalf of PCD Engineering Division
- Jul 2, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Engineering Manager on behalf of PCD Engineering Division
- Jul 2, 2026Submission Triaged
- Jul 2, 2026Submission received from Applicant
- Apr 2, 2026Submission request sent to Applicant
- Mar 2, 2026Submission request sent to Applicant
- Mar 2, 2026Submission request canceled
- Feb 17, 2026Submission request sent to Applicant
- Feb 12, 2026Request for Review Comments returned by County Attorney - Water
- Jan 29, 2026Request for Review Comments returned by County Attorney - Development Review
- Jan 28, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Water
- Jan 28, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Water
- Jan 28, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Water
- Jan 28, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Development Review
- Jan 28, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Development Review
- Jan 28, 2026Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Development Review
- Jan 28, 2026Submission Triaged
- Jan 28, 2026Submission received from Applicant
- Jan 27, 2026Submission request sent to Applicant
- Jan 20, 2026Submission request sent to Applicant
- Dec 16, 2025Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Dec 15, 2025Request for Review Comments returned by County Attorney - Water
- Dec 11, 2025Request for Review Comments returned by Colorado Division of Water Resources
- Dec 4, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Water
- Dec 4, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Water
- Dec 4, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Water
- Dec 2, 2025Submission Triaged
- Dec 1, 2025Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
- Dec 1, 2025Submission received from Applicant
- Nov 25, 2025Request for Review Comments returned by PCD Engineering Division
- Nov 25, 2025Request for Review Comments returned by PCD Project Manager
- Nov 24, 2025Request for Review Comments returned by EPC Fire and Wildfire Program Manager
- Nov 24, 2025Submission request sent to Applicant
- Nov 23, 2025Request for Review Comments returned by EPC Health Department
- Nov 18, 2025Request for Review Comments returned by County Attorney - Development Review
- Nov 18, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
- Nov 18, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- Nov 18, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Nov 18, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Justin Kilgore on behalf of PCD Project Manager
- Nov 18, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Gilbert LaForce on behalf of PCD Engineering Division
- Nov 18, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Engineering Manager on behalf of PCD Engineering Division
- Nov 18, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Nov 18, 2025Submission Triaged
- Nov 18, 2025Submission received from Applicant
- Nov 13, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Development Review
- Nov 13, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Development Review
- Nov 13, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Development Review
- Nov 13, 2025Request for Review Comments returned by Colorado Division of Water Resources
- Nov 12, 2025Submission request sent to Applicant
- Nov 6, 2025Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
- Nov 5, 2025Submission request sent to Applicant
- Nov 4, 2025Request for Review Comments returned by EPC Stormwater Review
- Nov 3, 2025Request for Review Comments returned by PCD Engineering Division
- Nov 3, 2025Request for Review Comments returned by PCD Project Manager
- Nov 3, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Zachary Jannusch on behalf of EPC Stormwater Review
- Nov 3, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Mikayla Hartford on behalf of EPC Stormwater Review
- Nov 3, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Glenn Reese on behalf of EPC Stormwater Review
- Nov 3, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Christina Prete on behalf of EPC Stormwater Review
- Nov 3, 2025Request for Review Comments returned by EPC Fire and Wildfire Program Manager
- Nov 3, 2025Request for Review Comments returned by County Attorney - Water
- Oct 30, 2025Request for Review Comments returned by County Attorney - Development Review
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Vicki Wood on behalf of Lewis Palmer 38
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Melissa Andrews on behalf of Lewis Palmer 38
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Brett Ridgway on behalf of Lewis Palmer 38
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Kimberly Wilkes on behalf of US Forest Service, Pikes Peak Ranger District
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jennifer DeWoody on behalf of US Forest Service, Pikes Peak Ranger District
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Mike Till on behalf of Colorado State Forest Service
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jeff Kramer on behalf of EPC Sheriff's Department
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Andrew Prehm on behalf of EPC Sheriff's Department
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Mike McCarthy on behalf of EPC Health Department
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Catherine McGarvy on behalf of EPC Health Department
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by HEAEH LandUse on behalf of EPC Health Department
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Development Review
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Development Review
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Development Review
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Water
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Water
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Water
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Justin Kilgore on behalf of PCD Project Manager
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Gilbert LaForce on behalf of PCD Engineering Division
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Engineering Manager on behalf of PCD Engineering Division
- Oct 27, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Oct 27, 2025Submission Triaged
- Oct 24, 2025Submission received from Applicant
- Aug 12, 2025Submission request sent to Applicant
- Aug 8, 2025Request for Review Comments returned by Colorado Division of Water Resources
- Jul 30, 2025Submission request sent to Applicant
- Jul 30, 2025Request for Review Comments returned by PCD Project Manager
- Jul 30, 2025Request for Review Comments returned by PCD Engineering Division
- Jul 29, 2025Request for Review Comments returned by EPC Fire and Wildfire Program Manager
- Jul 29, 2025Request for Review Comments returned by County Attorney - Development Review
- Jul 29, 2025Request for Review Comments returned by Colorado Geological Survey
- Jul 28, 2025Request for Review Comments returned by EPC Stormwater Review
- Jul 28, 2025Request for Review Comments returned by County Attorney - Water
- Jul 21, 2025Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
- Jul 16, 2025Request for Review Comments returned by Pikes Peak Regional Building Department
- Jul 15, 2025Request for Review Comments returned by Monument
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by on behalf of Monument
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Vicki Wood on behalf of Lewis Palmer 38
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Melissa Andrews on behalf of Lewis Palmer 38
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Brett Ridgway on behalf of Lewis Palmer 38
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by on behalf of Pikes Peak Regional Building Department
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Kimberly Wilkes on behalf of US Forest Service, Pikes Peak Ranger District
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jennifer DeWoody on behalf of US Forest Service, Pikes Peak Ranger District
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Mike Till on behalf of Colorado State Forest Service
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Colorado Geological Survey on behalf of Colorado Geological Survey
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Javier Vargas-Johnson on behalf of Colorado Division of Water Resources
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Zachary Jannusch on behalf of EPC Stormwater Review
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Mikayla Hartford on behalf of EPC Stormwater Review
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Glenn Reese on behalf of EPC Stormwater Review
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Christina Prete on behalf of EPC Stormwater Review
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Mike McCarthy on behalf of EPC Health Department
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Catherine McGarvy on behalf of EPC Health Department
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by HEAEH LandUse on behalf of EPC Health Department
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Water
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Water
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Water
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Erika Keech on behalf of County Attorney - Development Review
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Lori Seago on behalf of County Attorney - Development Review
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by April Willie on behalf of County Attorney - Development Review
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Justin Kilgore on behalf of PCD Project Manager
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Gilbert LaForce on behalf of PCD Engineering Division
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Engineering Manager on behalf of PCD Engineering Division
- Jul 15, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Jul 15, 2025Submission Triaged
- Jul 11, 2025Submission received from Applicant
- Jul 8, 2025Submission request sent to Applicant
- May 1, 2025Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
- May 1, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
- May 1, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- May 1, 2025Request for Review Comments returned by 911 Authority - El Paso/Teller County
- Apr 28, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
- Apr 28, 2025Request for Review Comments email sent for Project Hidden Creek Estates Subdivision for review by Glenn West on behalf of 911 Authority - El Paso/Teller County