Iron Ridge Preliminary Plan
Preliminary plan to include ~28 lots and 1 tract
- Location
- WALKER RD, 80908
- Jurisdiction
- El Paso County
- Applicant
- Vertex Consulting Services Nina Ruiz
- Land owner (assessor)
- ATTICUS LAND LLC (state record)
- County project manager
- Joe Letke
- Filed
- May 1, 2025
- Parcels
- 6100000439, 6100000457
- Map
-
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
- Area map
- See all Tri-Lakes projects on the map
- Source record
- El Paso County EDARP file
Documents (65)
BOCC Hearing AgendaadditionalJul 20, 2026
Hearing Agenda for the Board of County Commissioners hearing on 07/23/2026. JM
BOCC Staff Report - final with attachmentsadditionalJul 10, 2026
Staff Report for the Board of County Commissioners hearing on 07/23/2026. JM
Adopted PC MinutesadditionalJul 7, 2026
Adopted Minutes from the Planning Commission hearing on 06/18/2026. JM
Signed PC ResolutionadditionalJun 22, 2026
Recommendation from the Planning Commission hearing on 06/18/2026. JM
PC Staff Report - final with attachmentsadditionalJun 16, 2026
Updated Staff Report for the Planning Commission hearing on 06/18/2026. JM
PC & BOCC PosteradditionalJun 4, 2026
Poster for the Planning Commission hearing on 06/18/2026 and the Board of County Commissioners hearing on 07/23/2026. JM
Mailing Labels - Hearing NoticeadditionalJun 4, 2026
Mailing Labels for the 17 surrounding property owners that received notices. PCD mailed the letters on 06/03/2026. Cost = $12.58. JM
Hearing Notice & Vicinity MapadditionalJun 4, 2026
Hearing Notice for the Planning Commission hearing on 06/18/2026 and the Board of County Commissioners hearing on 07/23/2026. JM
PC Hearing AgendaadditionalJun 4, 2026
Hearing Agenda for the Planning Commission hearing on 06/18/2026. JM
Email communication between the developer and neighboring HOA presidentadditionalNov 17, 2025
This attached email is discourse between Nina Ruiz of Vertex Consulting and neighboring property owner Kirk Dickenson regarding proposal changes based upon feedback.
Mailing LabelsadditionalSep 30, 2025
Mailing Labels for the 17 surrounding property owners that received notices. Cost = $12.58. JM
Neighbor Notice & Vicinity MapadditionalSep 30, 2025
Notice of Application letters were mailed to surrounding property owners on 09/30/2025. JM
Agency review comments (49)
County Attorney - Waterreview 5May 14, 2026
See attached Water Supply Review and Recommendations.
County Attorney - Development Reviewreview 4Apr 30, 2026
No comments from County Attorney - Development Review at this time.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com
County Attorney - Waterreview 4Apr 13, 2026
In both the Water Supply Information Summary (WSIS) and Water Resources Report (WRR) house-hold use is listed at .26 af/y which totals 7.28 af/y with a use of “other” listed at .543 af/y which totals 15.204 af/y. 7.28 af/y +15.204=22.484 af/y although the requested demand in both WSIS & WRR is listed at 24.09 af/y. Please account for the extra 1.606 af/y or update and upload new WSIS/WRR.
Page 3 of the WRR mentions that the “other” demand of .543 af/y per lot water will be utilized for irrigation, stock water, recreation (including pool and/or hot tob), landscape ponds, commercial, fire protection. Please break down the specific uses using the guidelines in LDC (B)(7)(d)&(e).
After the above has been addressed, and a new letter from the Colorado Division of Water Resources has been received showing sufficient water, we will begin review.
EPC DPW Development Services - Engineeringreview 4Apr 8, 2026
DPW Engineering review 4
Comments have been resolved on the following documents
- Deviation Request (Cul-de-sac length)
Engineering documents will be routed to the engineering manager for County approval.
Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
PCD Project Managerreview 4Apr 8, 2026
Planning has no further comments.
Joe Letke
Planner
JoeLetke@elpasoco.com
PCD Project Managerreview 3Jan 26, 2026
Planning has comments on the following version 3 document:
-LOI
Joe Letke
Planner
JoeLetke@elpasoco.com
EPC DPW Development Services - Engineeringreview 3Jan 26, 2026
DPW Engineering has comments on the following documents
- Deviation Request (Cul-de-sac length) - minor comments and needs owners signature
Comments have been resolved on the following documents
- Deviation Request (Brown Court)
Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
EPC DPW Development Services - Engineeringreview 3Jan 26, 2026
Deviation Request (Cul-de-sac length)
EPC DPW Stormwaterreview 3Jan 20, 2026
Review 3: EPC DPW Stormwater comments have been resolved on the following document(s):
- PCM Applicability Form
EPC DPW Stormwater has no further comments. EPC Project Manager: no re-review necessary.
Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
County Attorney - Waterreview 3Jan 14, 2026
The County Attorney’s Office will begin review when approved decree and replacement plan/augmentation plan has been uploaded as well as a letter from the Colorado Division of Water Resources with a water sufficiency finding.
PCD Project Managerreview 2Dec 29, 2025
Planning has comments on the following version two documents:
-LOI
-Preliminary Plan Drawings
Joe Letke
Planner
JoeLetke@elpasoco.com
Tri-Lakes-Monument Fire Protection Districtreview 2Dec 29, 2025
1. Proposed roads meet adopted fire code standards for fire department access.
2. Proposed 30,000 gallon firefighting cistern is acceptable.
3. This development will be subject to the Colorado Wildfire Resiliency Code requirements if permitted after June 30, 2026
EPC DPW Development Services - Engineeringreview 2Dec 29, 2025
DPW Engineering has comments on the following documents
- Deviation Request (Cul-de-sac length deviation was not resubmitted), see comments from review 1
- Deviation Request #2
Comments have been resolved on the following documents
- Traffic Impact study
- Preliminary Plan Drawings
- Drainage Report - Preliminary
The initial deviation request does not seem to have been resubmitted for exceeding the cul-du-sac length. Please include a revised version addressing comments made with review 1.
Please include a signed version of the drainage report with the next submittal.
Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
EPC DPW Stormwaterreview 2Dec 29, 2025
Review 2: All EPC DPW Stormwater comments have been addressed. Please sign/date/stamp and resubmit the following document(s):
- PCM Applicability Form
EPC DPW Stormwater comments have been resolved on the following document(s):
- Preliminary Plan Drawings
- Preliminary Drainage Report
Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
County Attorney - Development Reviewreview 2Dec 23, 2025
Review #2: No comment from County Attorney – Development Review at this time.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
Pikes Peak Regional Building Departmentreview 2Dec 18, 2025
1. Existing Brown Rd coming in from the north should be a logical continuation into this subdivision. Please update plans to show Brown Road.
2. When submitting the development plan to Enumerations for addressing, please be sure to send us a copy that does not have topography or elevation lines. We need a clean, clear copy to add addresses.
See standard development plan comments below:
1. For assignment of addressing for lots and tracts, place addressing marker (xxx) where they are intended to be utilized. Addressing marker for lots should be front door, and should be placed as close to the edge of the lot as possible, running parallel to the street it is being addressed from.
2. Provide a 100 scale copy or larger of the entire APPROVED development plan (d.p.) to this department so that addressing can be assigned. Once received, the development plan will be placed on a list to be addressed. Development plans that are not yet approved may be addressed, however additional plan review fees will accrue if changes are made to the D.P. after initial addressing.
Thank you,
Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
County Attorney - Waterreview 2Dec 17, 2025
Please see comments from 10/7/25. No additional comments until those have been resolved. Thanks!
EPC Parks Departmentreview 2Dec 15, 2025
El Paso County Parks Comments:
See attached documentation for the second review.
Thank you!
Ashlyn Mathy
Parks Planner
Park Planning Division
El Paso County Parks Department
Office 719.520.6999
911 Authority - El Paso/Teller Countyreview 2Dec 11, 2025
Comments for E911 as follows:
Iron Ridge Ct should instead be a logical continuation of existing Brown Rd.
Colt Ct – Acceptable logical continuation of existing road.
Thank you
Justin
El Paso County Conservation Distreview 1Oct 30, 2025
No comments at this time.
EPC Parks Departmentreview 1Oct 27, 2025
El Paso County Parks Staff Preliminary Comments:
Please See Attached Documentation. This project will be presented before the Parks Advisory Board on November 12, 2025.
Thank you!
Ashlyn Mathy
Parks Planner
Park Planning Division
El Paso County Parks Department
Office 719.520.6999
PCD Project Managerreview 1Oct 20, 2025
-V1 Drainage Report - Preliminary
EPC DPW Development Services - Engineeringreview 1Oct 20, 2025
DPW Engineering has comments on the following documents
- Traffic Impact Study
- Preliminary Plan Drawings
- Deviation Request
- Drainage Report - Preliminary
Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
County Attorney - Development Reviewreview 1Oct 20, 2025
No Comments from County Attorney – Development Review at this time.
Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
EPC DPW Stormwaterreview 1Oct 20, 2025
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s):
- PCM Applicability Form
- Preliminary Drainage Report
- Preliminary Plan Drawings
Reviewed by:
Zachary Jannusch
Associate Engineer - Stormwater
719.500.3170
ZacharyJannusch@elpasoco.com
Pikes Peak Regional Building Departmentreview 1Oct 17, 2025
1. We agree with Emergency Services 9-1-1 that existing Brown Rd coming in from the north should be a logical continuation into this subdivision. Please update plans to show Brown Road.
2. When submitting the development plan to Enumerations for addressing, please be sure to send us a copy that does not have topography or elevation lines. We need a clean, clear copy to add addresses.
See standard development plan comments below:
1. For assignment of addressing for lots and tracts, place addressing marker (xxx) where they are intended to be utilized. Addressing marker for lots should be front door, and should be placed as close to the edge of the lot as possible, running parallel to the street it is being addressed from.
2. Provide a 100 scale copy or larger of the entire APPROVED development plan (d.p.) to this department so that addressing can be assigned. Once received, the development plan will be placed on a list to be addressed. Development plans that are not yet approved may be addressed, however additional plan review fees will accrue if changes are made to the D.P. after initial addressing.
Thank you,
Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
PCD Project Managerreview 1Oct 16, 2025
Planning has comments on the following version one documents:
-Letter of Intent
-Preliminary Plan Drawings
-Fire Protection Report
Joe Letke
Planner
JoeLetke@elpasoco.com
EPC Fire and Wildfire Program Managerreview 1Oct 16, 2025
This submittal is acceptable for this stage of development. The site is only partially vegetated.
Please provide additional detail on the access to lots 4, 5, 7 and the turn around for the cistern in the Final Plat.
Roland Peterson
Fire Safety and Wildfire Mitigation Program Manager
Planning & Community Development
719.520.6075
Mountain View Electric Association, Inc.review 1Oct 8, 2025
See attached comment letter
Tri-Lakes-Monument Fire Protection Districtreview 1Oct 7, 2025
Please provide more detail for access to lots 4, 5, 7 in phase 1 (page 2 of preliminary plan).
County Attorney - Waterreview 1Oct 7, 2025
The County Attorney’s Office will begin review when approved decree and replacement plan/augmentation plan has been uploaded as well as a letter from the Colorado Division of Water Resources with a water sufficiency finding.
Please note that the Water Supply Information Summary does not identify an estimated demand for irrigation or stock watering (or landscape ponds/commercial as listed as possible water uses in the Water Resource Report). If no demand is proposed, those uses of water will be prohibited.
911 Authority - El Paso/Teller Countyreview 1Oct 7, 2025
Comments for E911 as follows:
Iron Ridge Ct should instead be a logical continuation of existing Brown Rd.
Colt Ct – Acceptable logical continuation of existing road.
Thank you
Justin
PCD Administrative Noticereview 1Sep 30, 2025
On 09/30/2025, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (17 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $12.58. JM
RBD Floodplainreview 1Sep 29, 2025
site not in the floodplain, no comment
Land ownership timeline
- Mar 26, 2025Parcels 6100000439, 6100000457 acquired by ATTICUS LAND LLC (state record) for $1,260,000 (assessor record)
Timeline
- Aug 19, 2026Left the EDARP active list (approved, withdrawn, or closed)
- Jun 19, 2026Fees paid: 6/19/2026 (Receipt: 1012196)
- Jun 9, 2026Payment Request sent: 6/9/2026
- May 14, 2026Submission Triaged
- May 14, 2026Submission received from Applicant
- May 14, 2026Submission request sent to Applicant
- May 14, 2026Request for Review Comments returned by County Attorney - Water
- Apr 30, 2026Request for Review Comments returned by County Attorney - Development Review
- Apr 29, 2026Submission Triaged
- Apr 29, 2026Submission received from Applicant
- Apr 29, 2026Submission request sent to Applicant
- Apr 28, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Lori Seago on behalf of County Attorney - Water
- Apr 28, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erika Keech on behalf of County Attorney - Water
- Apr 28, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by April Willie on behalf of County Attorney - Water
- Apr 27, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Lori Seago on behalf of County Attorney - Water
- Apr 27, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erika Keech on behalf of County Attorney - Water
- Apr 27, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by April Willie on behalf of County Attorney - Water
- Apr 27, 2026Submission Triaged
- Apr 27, 2026Submission received from Applicant
- Apr 27, 2026Submission request sent to Applicant
- Apr 23, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Lori Seago on behalf of County Attorney - Development Review
- Apr 23, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erika Keech on behalf of County Attorney - Development Review
- Apr 23, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by April Willie on behalf of County Attorney - Development Review
- Apr 23, 2026Submission Triaged
- Apr 23, 2026Submission received from Applicant
- Apr 22, 2026Submission request sent to Applicant
- Apr 20, 2026Request for Review Comments returned by Colorado Division of Water Resources
- Apr 13, 2026Request for Review Comments returned by County Attorney - Water
- Apr 8, 2026Request for Review Comments returned by EPC DPW Development Services - Engineering
- Apr 8, 2026Request for Review Comments returned by PCD Project Manager
- Mar 30, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Mike Matz on behalf of Colorado Division of Water Resources
- Mar 30, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Mar 30, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Mar 30, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Mar 30, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Lori Seago on behalf of County Attorney - Water
- Mar 30, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erika Keech on behalf of County Attorney - Water
- Mar 30, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by April Willie on behalf of County Attorney - Water
- Mar 30, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Justin Kilgore on behalf of PCD Project Manager
- Mar 30, 2026Submission Triaged
- Mar 30, 2026Submission received from Applicant
- Jan 26, 2026Submission request sent to Applicant
- Jan 26, 2026Request for Review Comments returned by PCD Project Manager
- Jan 26, 2026Request for Review Comments returned by EPC DPW Development Services - Engineering
- Jan 20, 2026Request for Review Comments returned by EPC DPW Stormwater
- Jan 14, 2026Request for Review Comments returned by County Attorney - Water
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Glenn Reese on behalf of EPC DPW Stormwater
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Christina Prete on behalf of EPC DPW Stormwater
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Lori Seago on behalf of County Attorney - Water
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erika Keech on behalf of County Attorney - Water
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by April Willie on behalf of County Attorney - Water
- Jan 12, 2026Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Justin Kilgore on behalf of PCD Project Manager
- Jan 12, 2026Submission Triaged
- Jan 9, 2026Submission received from Applicant
- Dec 29, 2025Submission request sent to Applicant
- Dec 29, 2025Request for Review Comments returned by PCD Project Manager
- Dec 29, 2025Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
- Dec 29, 2025Request for Review Comments returned by EPC DPW Development Services - Engineering
- Dec 29, 2025Request for Review Comments returned by EPC DPW Stormwater
- Dec 23, 2025Request for Review Comments returned by Colorado Division of Water Resources
- Dec 23, 2025Request for Review Comments returned by County Attorney - Development Review
- Dec 18, 2025Request for Review Comments returned by Pikes Peak Regional Building Department
- Dec 17, 2025Request for Review Comments returned by County Attorney - Water
- Dec 15, 2025Request for Review Comments returned by EPC Parks Department
- Dec 11, 2025Request for Review Comments returned by 911 Authority - El Paso/Teller County
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by on behalf of Pikes Peak Regional Building Department
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by on behalf of EPC Parks Department
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Glenn Reese on behalf of EPC DPW Stormwater
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Christina Prete on behalf of EPC DPW Stormwater
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Lori Seago on behalf of County Attorney - Water
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erika Keech on behalf of County Attorney - Water
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by April Willie on behalf of County Attorney - Water
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Lori Seago on behalf of County Attorney - Development Review
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erika Keech on behalf of County Attorney - Development Review
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by April Willie on behalf of County Attorney - Development Review
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Justin Kilgore on behalf of PCD Project Manager
- Dec 11, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Dec 11, 2025Submission Triaged
- Dec 11, 2025Submission received from Applicant
- Nov 13, 2025Request for Review Comments returned by US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Oct 30, 2025Request for Review Comments returned by El Paso County Conservation Dist
- Oct 28, 2025Request for Review Comments returned by EPC Health Department
- Oct 27, 2025Request for Review Comments returned by EPC Parks Department
- Oct 20, 2025Submission request sent to Applicant
- Oct 20, 2025Request for Review Comments returned by PCD Project Manager
- Oct 20, 2025Request for Review Comments returned by EPC DPW Development Services - Engineering
- Oct 20, 2025Request for Review Comments returned by County Attorney - Development Review
- Oct 20, 2025Request for Review Comments returned by EPC DPW Stormwater
- Oct 17, 2025Request for Review Comments returned by Pikes Peak Regional Building Department
- Oct 16, 2025Request for Review Comments returned by EPC Fire and Wildfire Program Manager
- Oct 16, 2025Request for Review Comments email resent for Project Iron Ridge Preliminary Plan for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Oct 16, 2025Request for Review Comments returned by EPC Fire and Wildfire Program Manager
- Oct 15, 2025Request for Review Comments returned by Colorado Geological Survey
- Oct 8, 2025Request for Review Comments returned by Mountain View Electric Association, Inc.
- Oct 7, 2025Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
- Oct 7, 2025Request for Review Comments returned by County Attorney - Water
- Oct 7, 2025Request for Review Comments returned by 911 Authority - El Paso/Teller County
- Sep 30, 2025Request for Review Comments returned by EPC Environmental Services
- Sep 30, 2025Request for Review Comments returned by PCD Administrative Notice
- Sep 29, 2025Request for Review Comments returned by RBD Floodplain
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Trish Riber on behalf of Black Hills Energy-Aquila
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Bob Swatek on behalf of Black Hills Energy-Aquila
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Adam Magoon on behalf of Black Hills Energy-Aquila
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Vicki Wood on behalf of Lewis Palmer 38
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Melissa Andrews on behalf of Lewis Palmer 38
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Brett Ridgway on behalf of Lewis Palmer 38
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Harry Thomas on behalf of El Paso County Conservation Dist
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Oliver Watkins on behalf of El Paso County Conservation Dist
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Katie Miller on behalf of El Paso County Conservation Dist
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erica Carter on behalf of El Paso County Conservation Dist
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by on behalf of El Paso County Conservation Dist
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Mariah Hudson on behalf of El Paso County Conservation Dist
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Cassie Olgren on behalf of El Paso County Conservation Dist
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Billy Richard on behalf of El Paso County Conservation Dist
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Keith Curtis on behalf of RBD Floodplain
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by on behalf of Pikes Peak Regional Building Department
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Colorado Geological Survey on behalf of Colorado Geological Survey
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Ailis Thyne on behalf of Colorado Division of Water Resources
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by on behalf of EPC Parks Department
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Mike McCarthy on behalf of EPC Health Department
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Catherine McGarvy on behalf of EPC Health Department
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by HEAEH LandUse on behalf of EPC Health Department
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Kathy Andrew on behalf of EPC Environmental Services
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Glenn Reese on behalf of EPC DPW Stormwater
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Christina Prete on behalf of EPC DPW Stormwater
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Lori Seago on behalf of County Attorney - Water
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erika Keech on behalf of County Attorney - Water
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by April Willie on behalf of County Attorney - Water
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Lori Seago on behalf of County Attorney - Development Review
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Erika Keech on behalf of County Attorney - Development Review
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by April Willie on behalf of County Attorney - Development Review
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Justin Kilgore on behalf of PCD Project Manager
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by on behalf of PCD Administrative Notice
- Sep 29, 2025Request for Review Comments email sent for Project Iron Ridge Preliminary Plan for review by Roland Peterson on behalf of EPC Fire and Wildfire Program Manager
- Sep 29, 2025Project Manager Assigned: Joe Letke
- Sep 25, 2025Fees paid: 9/25/2025 (Receipt: 1011116)
- Sep 25, 2025Payment Request sent: 9/25/2025
- Sep 25, 2025Payment Request sent: 9/25/2025
- Sep 25, 2025File # Assigned: SP253
- Sep 25, 2025Submission Triaged
- Sep 24, 2025Submission received from Applicant
- Jul 23, 2025Submission request sent to Applicant
- May 16, 2025Submission request sent to Applicant
- May 1, 2025Submission request sent to Applicant
- May 1, 2025Project Created
- May 1, 2025EA Assigned: EA2546
- May 1, 2025Project Manager Assigned: Lisa Elgin