Monument Ridge East Filing No 1

Final plat SF2514 Active
Location
MISTY ACRES BLVD; COUNTY LINE RD; 20255 MONUMENT HILL RD, 80132
Jurisdiction
El Paso County
Applicant
Vertex Consulting Services Nina Ruiz
Land owner (assessor)
MONUMENT RIDGE EAST LLC (state record)
County project manager
Kylie Bagley
Filed
Aug 3, 2021
Parcels
7102200006, 7102200008, 7102200010, 7102200013, 7102201001, 7102201014
Map
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
Area map
See all Tri-Lakes projects on the map
Source record
El Paso County EDARP file

Documents (84)

Deviation Pond AccessreviewJul 21, 2026
Closures Sheet (Survey)reviewJul 20, 2026
Final Plat DrawingsreviewJul 20, 2026
EPC TIS Response 7.20.26reviewJul 20, 2026
Traffic Impact StudyreviewJul 20, 2026
Soils & Geology ReportreviewJul 17, 2026
Water and Sewer PlansreviewJul 16, 2026
UT CDsreviewJul 16, 2026
Drainage Report - FinalreviewJul 16, 2026
Construction DrawingsreviewJul 16, 2026
PCM Applicability FormreviewJul 16, 2026
Financial Assurance FormsreviewJul 16, 2026
SWMP AppendixreviewJul 9, 2026
TIS MemoreviewMay 12, 2026
TIS Cover LetterreviewMay 12, 2026
Trip Generation AddendumreviewMay 12, 2026
CD WWSD Comment ResponsereviewMay 12, 2026
CD Comment ResponsereviewMay 12, 2026
FDR Comment ResponsereviewMay 12, 2026
Site Development PlanreviewMay 7, 2026
Letter of IntentreviewMay 7, 2026
Plat Comment ResponsereviewMay 7, 2026
O M ResponsereviewJan 5, 2026
SWMP ResponsereviewJan 2, 2026
Pond OpinionreviewJan 2, 2026
CD ResponsereviewJan 2, 2026
FDR ResponsereviewJan 2, 2026
FAE ResponsereviewJan 2, 2026
Landscape PlanreviewDec 22, 2025
Site Development PlanreviewDec 22, 2025
Piezometer TablereviewJul 29, 2025
CGS Response LetterreviewJul 29, 2025
SWMP checklistreviewJul 29, 2025
CD Comment ResponsereviewJul 21, 2025
Landscape ResponsereviewJun 18, 2025
Landscape Plan drawingsreviewJun 18, 2025
Letter of Intent ResponsereviewJun 12, 2025
Application/Petition FormreviewJun 12, 2025
Fire Commitment LetterreviewApr 15, 2025
Wetlands Analysis ReportreviewApr 15, 2025
Natural Features ReportreviewApr 15, 2025
Fire Protection ReportreviewApr 15, 2025
Well Abandonment ReportreviewApr 9, 2025
Returned Notice - 5/28/2025additionalMay 29, 2025
Returned Notice - 5/28/2025additionalMay 29, 2025
Returned Notice - 5/28/2025additionalMay 29, 2025
Returned Notice - 5/28/2025additionalMay 29, 2025
Returned Notice - 5/28/2025additionalMay 29, 2025
Returned Notice - 5/28/2025additionalMay 29, 2025
Returned Notice - 5/28/2025additionalMay 29, 2025
Selected RangeadditionalMay 19, 2025
Selected Range was 500 feet. JM
Neighbor Notice & Vicinity MapadditionalMay 19, 2025
Notice of Application letters were mailed to surrounding property owners on 05/19/2025. JM
Mailing LabelsadditionalMay 19, 2025
Mailing Labels for the 99 surrounding property owners that received notices. Cost = $68.31. JM

Agency review comments (117)

Comments returned by referral agencies during review, from the county's public EDARP file. Some agencies attach a letter instead of (or alongside) written comments.

County Attorney - Development Reviewreview 5Aug 24, 2026
See edits to SIA. Erika Keech Sr. County Attorney
View attached comment letter
County Attorney - Development Reviewreview 5Aug 24, 2026
See edits to DMA. Erika Keech Sr. County Attorney
View attached comment letter
PCD Engineering Divisionreview 5Aug 12, 2026
Review 5: EPC Development Services Engineer comments have been provided on the following documents. - Construction Drawings - FAE - Final Drainage Report - Final Plat - Utility Construction Drawings - Soils & Geology Report - Deviation request (for sidewalk along Misty Acres) Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com
PCD Engineering Divisionreview 5Aug 12, 2026
Utility Drawing Redlines
View attached comment letter
PCD Engineering Divisionreview 5Aug 12, 2026
Soils & Geology Report Redlines
View attached comment letter
PCD Engineering Divisionreview 5Aug 12, 2026
FAE Redlines
View attached comment letter
PCD Engineering Divisionreview 5Aug 12, 2026
Final Plat Redlines
View attached comment letter
PCD Engineering Divisionreview 5Aug 12, 2026
Drainage Report Redlines
View attached comment letter
PCD Engineering Divisionreview 5Aug 12, 2026
Deviation Request - Sidewalk
View attached comment letter
PCD Engineering Divisionreview 5Aug 12, 2026
Construction Drawing Redlines
View attached comment letter
EPC Stormwater Reviewreview 5Aug 12, 2026
PCM Applicability Form
View attached comment letter
EPC Stormwater Reviewreview 5Aug 12, 2026
Deviation Request - Pond Access
View attached comment letter
EPC Stormwater Reviewreview 5Aug 12, 2026
Review 5: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s): - CDs...................................(to be uploaded by Development Services) - Deviation Request - Pond Access - Drainage Report...............(to be uploaded by Development Services) - FAE...................................(to be uploaded by Development Services) - PCM Applicability Form - Utility CDs........................(to be uploaded by Development Services) EPC DPW Stormwater comments have been resolved on the following document(s): - ESQCP - GEC Checklist - SWMP Unresolved previous comment: For the PCM Maintenance Agreement, please upload the exhibits. They can be uploaded as a PDF, separate from the Agreement's Word doc if you want. Otherwise, add the text/images of the exhibits to the Word doc and upload as one. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
PCD Project Managerreview 5Aug 11, 2026
Minor comments on Final Plat
Colorado Department of Transportation - Pueblo Officereview 5Aug 4, 2026
Please refer to the attached letter for CDOT's comments regarding this development.
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
SWMP
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
Soils Report
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
PCM Applicability Form
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
FAE
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
ESQCP
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
FDR
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
CDs
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
Utility CDs
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
TIS Memo
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
Closures Sheet (Survey)
View attached comment letter
EPC Stormwater Reviewreview 4Jun 1, 2026
Review 4: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s): - CDs - Drainage Report - ESQCP - FAE - GEC Checklist - PCM Applicability Form - Soils Report (please address the blue comments) - SWMP Unresolved previous comment: For the PCM Maintenance Agreement, please upload the exhibits. They can be uploaded as a PDF, separate from the Agreement's Word doc if you want. Otherwise, add the text/images of the exhibits to the Word doc and upload as one. If any of our comments are confusing or you disagree with them, please schedule a meeting to discuss with us. Many of our previous comments went completely unresolved or were only partially resolved. This is causing this project to go through more review cycles than necessary and using up a lot of time for many people. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
PCD Engineering Divisionreview 4May 28, 2026
Final Plat comments
View attached comment letter
PCD Engineering Divisionreview 4May 28, 2026
Review 4: EPC Development Services Engineer comments have been provided on the following documents. All redlines to be uploaded by stormwater engineering with the exception of the Final Plat comments. - Closure Sheets - Construction Drawings - FAE - Final Drainage Report - Final Plat - Utility Construction Drawings - TIS Memo - Soils Report Additional required documents: - Deviation request (for sidewalk along Misty Acres) - Deviation request (for matching pipe soffits when diameter changes) Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com
PCD Project Managerreview 4May 27, 2026
Planning Department has comments on Final Plat. Redlines will be uploaded by Engineering.
Colorado Geological Surveyreview 4May 27, 2026
See attached comments.
View attached comment letter
County Attorney - Development Reviewreview 4May 26, 2026
No additional comments from County Attorney - Development Review at this time. Reviewed by: Erika Keech, Sr. County Attorney
Woodmoor Water and Sanitation Districtreview 4May 21, 2026
Updated Water and Sewer Construction Plans were not submitted for this review. Please submit updated Water and Sewer Construction Plans per the last round of WWSD Review comments on 01.15.2026.
Woodmoor Water and Sanitation Districtreview 4May 21, 2026
Please see the attached document for all remaining WWSD comments on the Final Plat.
View attached comment letter
Colorado Department of Transportation - Pueblo Officereview 4May 19, 2026
Please see the attached letter for CDOT's comments regarding this development.
View attached comment letter
PCD Project Managerreview 3Jan 29, 2026
SWMP Redlines
View attached comment letter
PCD Project Managerreview 3Jan 29, 2026
GEC Checklist Redlines
View attached comment letter
PCD Project Managerreview 3Jan 29, 2026
PCM Applicability Form Redlines
View attached comment letter
PCD Project Managerreview 3Jan 29, 2026
ESCQP Redlines
View attached comment letter
PCD Engineering Divisionreview 3Jan 28, 2026
Review 3: EPC Development Services Engineer comments have been provided on the following documents: - Closure Sheets - Construction Drawings - FAE - Final Drainage Report - Letter of Intent - Final Plat - Utility Construction Drawings - Traffic Impact Study - Soils Report (See comment below) Additional Comments: 1. Soils Report Comment: Address shallow groundwater mitigation for ponds. The report addresses foundations but not Pond 1 which has groundwater levels in the depth of the proposed pond. 2. Please address CGS, Misty Acres Metro and CDOT comments. 3. Due to the nature and volume of comments provided and information not included, additional comments may be expected with the third review. Planner, please note that next review will need to be seen as a first review. 4. Note comment in FDR that additional modeling will need to be provided for detention ponds in series, due to close proximity of ponds, including existing pond, to each other. Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314
PCD Engineering Divisionreview 3Jan 28, 2026
Utility CD Redlines
View attached comment letter
PCD Engineering Divisionreview 3Jan 28, 2026
TIS Redlines
View attached comment letter
PCD Engineering Divisionreview 3Jan 28, 2026
LOI Redlines
View attached comment letter
PCD Engineering Divisionreview 3Jan 28, 2026
FAE Redlines
View attached comment letter
PCD Engineering Divisionreview 3Jan 28, 2026
Plat Redlines
View attached comment letter
PCD Engineering Divisionreview 3Jan 28, 2026
FDR Redlines
View attached comment letter
PCD Engineering Divisionreview 3Jan 28, 2026
Construction Drawing Redlines
View attached comment letter
PCD Engineering Divisionreview 3Jan 28, 2026
Closure Redlines
View attached comment letter
EPC Stormwater Reviewreview 3Jan 26, 2026
Review 3: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) to be uploaded by the PM: - CDs - Drainage Report - ESQCP - FAE - GEC Checklist - PCM Applicability Form - SWMP Unresolved previous comment (a revised agreement was not uploaded this round for my review): For the PCM Maintenance Agreement, please upload the exhibits. They can be uploaded as a PDF, separate from the Agreement's Word doc if you want. Otherwise, add the text/images of the exhibits to the Word doc and upload as one. EPC DPW Stormwater comments have been resolved on the following document(s): - PCM - MHFD Detention Calcs or SDI Form - PCM O&M Manual - PCM - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal) Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
PCD Project Managerreview 3Jan 26, 2026
Comments on the Final Plat. Comments will be uploaded by the Engineering department as part of their review.
Colorado Geological Surveyreview 3Jan 26, 2026
View attached comment letter
Colorado Geological Surveyreview 3Jan 26, 2026
View attached comment letter
County Attorney - Development Reviewreview 3Jan 22, 2026
Review # 3: County Attorney comments from 10/30/25, with respect to the PCM Maintenance Agreement, remain unaddressed. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
Woodmoor Water and Sanitation Districtreview 3Jan 22, 2026
Please see the attached markups for all WWSD comments on the Utility Construction Plans
View attached comment letter
Woodmoor Water and Sanitation Districtreview 3Jan 22, 2026
Please see the attached markups for all WWSD comments on the Final Plat.
View attached comment letter
Misty Acres Metroreview 3Jan 16, 2026
Where is the response to the Misty Acres Metro District's previous concerns? To summarize, the traffic study is faulty because it does not factor in high school traffic/illegal parking. It was also done outside of school being in session. We also think their drainage and water management plans are faulty because we are working on improving flow of water from Monument Ridge north to their land. There will be more water than the designs anticipate since we are changing the status quo in the spring of 2026. We also propose a side walk on the east side (or both sides) of Misty Acres Blvd for the increase foot traffic from the new development to Palmer Ridge HS and the Misty Acres MD public parks.
PCD Project Managerreview 3Jan 16, 2026
Per CDOTs review letter, County approvals for this development be held until the requested documents have been received and approved by CDOT, in accordance with the State Highway Access Code. Applicant must provide proof of approved CDOT documents
Colorado Department of Transportation - Pueblo Officereview 3Jan 15, 2026
Please refer to the attached letter for CDOT's comments.
View attached comment letter
Mountain View Electric Association, Inc.review 2Nov 18, 2025
MVEA has no further comments.
PCD Engineering Divisionreview 2Nov 13, 2025
Review 2: EPC Development Services Engineer comments have been provided on the following documents: - Closure Sheets - Construction Drawings - FAE - Final Drainage Report - Letter of Intent - Final Plat - Soils Report (See comment below) Additional Comments: 1. Soils Report Comment: Address shallow groundwater mitigation for ponds. The report addresses foundations but not Pond 1 which has groundwater levels in the depth of the proposed pond. 2. Please provide copy of utility construction drawings for review and EPC approval. 3. Deviation requests need to be provided for intersections without pedestrian ramps at all 4 corners and for sidewalk not be installed in locations of Misty Acres & Monument Hill. (See CD's for additional information regarding this comment.) 4. Please address CGS and CDOT comments. 5. Due to the nature and volume of comments provided and information not included, additional comments may be expected with the second review. Planner, please note that next review will need to be seen as a first review. Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com Joe Sandstrom, EI, Associate Engineer josephsandstrom@elpasoco.com (719) 520-6314
PCD Engineering Divisionreview 2Nov 13, 2025
SWMP Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
O&M Manual Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
PCM Applicability Form
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
Non Jurisdictional Impoundment Structure Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
MHFD Calcs Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
GEC Checklist Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
ESQCP Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
Plat Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
LOI Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
FDR Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
FAE Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
Construction Drawing Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
Closure Sheet Redlines
View attached comment letter
PCD Engineering Divisionreview 2Nov 13, 2025
Monumentation Detail - to be included with CD set
View attached comment letter
Colorado Department of Transportation - Pueblo Officereview 2Nov 12, 2025
Please refer to the attached letter for CDOT's comments regarding this development.
View attached comment letter
PCD Project Managerreview 2Nov 7, 2025
Comments on final plat. Engineer to upload final plat with their comments.
EPC Stormwater Reviewreview 2Nov 6, 2025
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) to be uploaded by the PM: - CDs - Drainage Report - ESQCP - FAE - GEC Checklist - PCM Applicability Form - PCM - MHFD Detention Calcs or SDI Form - PCM O&M Manual - PCM - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal) - SWMP For the PCM Maintenance Agreement, please upload the exhibits. They can be uploaded as a PDF, separate from the Agreement's Word doc if you want. Otherwise, add the text/images of the exhibits to the Word doc and upload as one. EPC DPW Stormwater comments have been resolved on the following document(s): - Final Plat - SWMP Checklist Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
Colorado Geological Surveyreview 2Nov 6, 2025
See attached comments.
View attached comment letter
Misty Acres Metroreview 2Nov 6, 2025
The water and drainage plan omits changes in the works on the south side of the development by Misty Acres Metro District (MAMD) and El Paso County (EPC). There are no storm sewers on the EPC roads on the north end of the Misty Acres Metro District. The existing infrastructure on the roadside and on the MAMD trail network has washed away or is not working. MAMD is considering options to better handle rainwater and we would like the support of EPC and the new development to collaborate in designing an effective drainage solution. The new development seems to be working in a vacuum and is incorrectly assuming the status quo is working and will persist. We have a lot of water that needs to go somewhere and the new development is downhill of MAMD. Where should it all go?
Misty Acres Metroreview 2Nov 6, 2025
I disagree with their traffic studies. They omit Palmer Ridge High School traffic and the illegal parking on Misty Acres Blvd. There's going to be a lot of collisions around there with increased traffic and inexperienced drivers. There's also a pedestrian risk with children darting out between cars and short sight lines. Sidewalks on both sides of Misty Acres Blvd from Monument Hill Rd to Lindenmere are needed to help pedestrian traffic and drainage. A sidewalk along Misty Acres Blvd from Lindenmere to the new development is needed. Misty Acres Blvd has deep washout on both sides and is not wide enough to safely handle increase car and pedestrian traffic. I think a traffic circle would help at Misty Acres Blvd and Monument Hill Road. There is a bad backup at carline times caused by people turning left onto Monument Hill Rd. The additional traffic will make this problem much worse.
Woodmoor Water and Sanitation Districtreview 2Nov 6, 2025
1. Please see the attached WWSD comments for the most recent Final Plat submittal. 2. Please note that only the Plat was reviewed because there were no water or sanitary sewer construction plans attached to the current submittal to review.
View attached comment letter
County Attorney - Development Reviewreview 2Oct 30, 2025
No comments regarding updated SIA. Regarding the PCM Maintenance Agreement, please edit the name of the Subdivision in Recital C, so it is consistent with the language on the final plat: “Monument Ridge Filing #1” (numeric digit rather than abbreviated number). Please also identify the tracts in which the pond will be built in Recital J and paragraph 8.a. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
Pikes Peak Regional Building Departmentreview 2Oct 24, 2025
1. Add the addressing to the plat. Each address should be running parallel to the street they are being addressed from. Addressing should be as close to the edge of the lot as possible. This indicates and is made clear to anyone looking at the plat, which street the lot is addressed from. 2. Standard Final Plat comments: a. Enumerations will review the pre-plat (mylar) prior to plat for address placement, street names, and title block. b. A $10.00 per lot and tract platting fee will be due at the time of the review of the pre-plat, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. As of December 5th 2023, the fee for all credit/debit cards has changed from the flat 2.95% fee to the following: Over the phone Credit/Debit Card payments will be 2.3% and In-Person Debit Card payments will be 1.5% (in-person only). Paid directly to the Enumerations Department. c. Pre-plat reviews can be reviewed via “pdf” or in-person. The pre-plat will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations stamping the pre-plat and receiving payment of plat fees. If any pre-plat changes occur, even if changes do not apply to Enumerations, we still need to re-stamp the pre-plat. The Enumerations stamped pre-plat copy should match the recorded document minus a few signatures. If you would like an in-person review, please make an appointment on our website, https://www.pprbd.org/Home/BookAppt d. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Please email the Enumerations staff member that reviewed your project. Amy@pprbd.org; Brent@pprbd.org; or BeckyA@pprbd.org Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org
Misty Acres Metroreview 1May 29, 2025
The Misty Acres BoD agreed to discuss the petition to leave our Metro District at our next meeting, August 21. We will also have public comment at that meeting. We will post documents on our website before the meeting explaining the process to our residents.
Colorado Department of Transportation - Pueblo Officereview 1May 29, 2025
Please see the attached letter.
View attached comment letter
Mountain View Electric Association, Inc.review 1May 28, 2025
See attached comment
View attached comment letter
EPC Stormwater Reviewreview 1May 27, 2025
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - CDs - Drainage Report - FAE - Final Plat - GEC Plan - GEC Checklist - your version - GEC Checklist - EPC version - SWMP - SWMP Checklist Please provide the following document(s) upon resubmittal (the planner will need to send an upload request): - ESQCP - PCM Applicability Form - PCM Maintenance Agreement - PCM - MHFD Detention Calcs or SDI Form - PCM O&M Manual - PCM - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal) Due to the volume or complexity of the comments provided, these comments are preliminary in nature and EPC DPW Stormwater reserves the right to make additional comments. Additional detailed comments will be provided upon receipt of complete information/plans and resolution of the major issues. Please feel free to call if you have any questions regarding this review. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
EPC Stormwater Reviewreview 1May 27, 2025
SWMP Checklist
View attached comment letter
EPC Stormwater Reviewreview 1May 27, 2025
SWMP
View attached comment letter
EPC Stormwater Reviewreview 1May 27, 2025
GEC Checklist - EPC version
View attached comment letter
EPC Stormwater Reviewreview 1May 27, 2025
GEC Checklist - your version
View attached comment letter
EPC Stormwater Reviewreview 1May 27, 2025
GEC Plan
View attached comment letter
EPC Stormwater Reviewreview 1May 27, 2025
Final Plat
View attached comment letter
EPC Stormwater Reviewreview 1May 27, 2025
FAE
View attached comment letter
EPC Stormwater Reviewreview 1May 27, 2025
Drainage Report
View attached comment letter
EPC Stormwater Reviewreview 1May 27, 2025
CDs
View attached comment letter
PCD Engineering Divisionreview 1May 24, 2025
Review 1: EPC Development Services Engineer comments have been provided on the following documents: - Application - Closure Sheets - Construction Drawings - FAE - Final Drainage Report - Letter of Intent - Plat - Soils Report (See comment below) - Traffic Report Additional Comments: 1. Soils Report Comment: Address shallow groundwater mitigation for ponds. The report addresses foundations but not Pond 1 which has groundwater levels in the depth of the proposed pond. 2. Please provide copy of utility construction drawings for review and EPC approval. 3. Deviation requests need to be provided for intersections without pedestrian ramps at all 4 corners and for sidewalk not be installed in locations of Misty Acres & Monument Hill. (See CD's for additional information regarding this comment.) 4. Due to the nature and volume of comments provided and information not included, additional comments may be expected with the second review. Planner, please note that next review will need to be seen as a first review. Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com
PCD Engineering Divisionreview 1May 24, 2025
TIS Redlines
View attached comment letter
PCD Engineering Divisionreview 1May 24, 2025
Plat Redlines
View attached comment letter
PCD Engineering Divisionreview 1May 24, 2025
FAE Redlines
View attached comment letter
PCD Engineering Divisionreview 1May 24, 2025
Letter of Intent Redlines
View attached comment letter
PCD Engineering Divisionreview 1May 24, 2025
Drainage Report Redlines
View attached comment letter
PCD Engineering Divisionreview 1May 24, 2025
Construction Drawing Redlines
View attached comment letter
PCD Engineering Divisionreview 1May 24, 2025
Closure Sheet Redlines
View attached comment letter
PCD Engineering Divisionreview 1May 24, 2025
Application Redlines
View attached comment letter
Colorado Parks and Wildlifereview 1May 23, 2025
No additional comments exist for the Monument Ridge East Filing No 1. Colorado Parks and Wildlife (CPW) commented on the Monument Ridge East project back on June 8, 2024 and August 5, 2024. CPW encourages the Town of Monument to refer back to these documents for our previous comments. Thank You.
PCD Project Managerreview 1May 22, 2025
Landscape Plan Redlines
View attached comment letter
PCD Project Managerreview 1May 22, 2025
The planning department has comments on the following documents: - Final Plat Drawings (to be uploaded by engineer) - Landscape Plan - Financial Assurance Form (to be uploaded by engineer)
County Attorney - Development Reviewreview 1May 22, 2025
See edits to attached SIA. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
View attached comment letter
Woodmoor Water and Sanitation Districtreview 1May 20, 2025
Please see the attached document for all Woodmoor Water & Sanitation District Comments on the Final Plat.
View attached comment letter
PCD Administrative Noticereview 1May 19, 2025
On 05/19/2025, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (99 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $68.31. JM
Parks Advisory Boardreview 1May 15, 2025
El Paso County Parks Department, Final Comments - Please See Attached Documentation (Endorsed by the Park Advisory Board on May 14, 2025)
View attached comment letter
EPC Parks Departmentreview 1May 15, 2025
El Paso County Parks Department, Final Comments - Please See Attached Documentation (Endorsed by the Park Advisory Board on May 14, 2025)
View attached comment letter
County Attorney - Waterreview 1May 13, 2025
A water finding was made at Preliminary Plan, File No. SP-24-1 on November 14, 2024. We note that Requirement B. has been met in this filing.
911 Authority - El Paso/Teller Countyreview 1May 13, 2025
Comments for E911 as follows: Streetnames have been previously approved for this development, but not all streets are labeled on the Final Plat Drawings included with this submittal. Please ensure that all streets are properly labeled on final documents. Thank you Justin
Tri-Lakes-Monument Fire Protection Districtreview 1May 12, 2025
The fire department has reviewed the final plat drawing and it is acceptable for the following: 1. Fire department access: road standards including road width and turnarounds are acceptable. The cul du sac at the north end is 80' diameter or greater with a dead-end less than 500' in length. 2. Proposed fire hydrant location is acceptable. The fire hydrant spacing on the site must be an average of 500'. The spacing for this site is average of 480'.
Pikes Peak Regional Building Departmentreview 1May 8, 2025
1. The street approved names need to be added to the plat. Once the addresses are received they to will need to be on the plat. 2. Contact this department when you are ready to have the addresses assign to the project. If tract addressing is needed, mark the locations with an addressing marker (xxx). 3. 20255 Monument Hill Road is an existing home on 71022-01-001. A wrecking permit will be required to remove this home with RBD, prior to any plan being approved in the Enumerations department. 4. Standard Final Plat comment: a. Enumerations will review the pre-plat (mylar) prior to plat for address placement, street names, and title block. b. A $10.00 per lot and tract platting fee will be due at the time of the review of the pre-plat, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department. As of December 5th 2023, the fee for all credit/debit cards has changed from the flat 2.95% fee to the following: Over the phone Credit/Debit Card payments will be 2.3% and In-Person Debit Card payments will be 1.5% (in-person only). c. Pre-plat reviews can be reviewed via “pdf” or in-person. The pre-plat will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations stamping the pre-plat and receiving payment of plat fees. If any pre-plat changes occur, even if changes do not apply to Enumerations, we still need to re-stamp the pre-plat. The Enumerations stamped pre-plat copy should match the recorded document minus a few signatures. If you would like an in-person review, please make an appointment on our website, https://www.pprbd.org/Home/BookAppt d. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Please email the Enumerations staff member that reviewed your project. Amy@pprbd.org; Brent@pprbd.org; or BeckyA@pprbd.org Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org
RBD Floodplainreview 1May 1, 2025
project not in the floodplain , no comment

Land ownership timeline

The documented chain of ownership per parcel, from El Paso County Assessor records and TriLakes Growth's monthly re-checks. Where the record hasn't been collected yet, the gap is shown rather than papered over.

Timeline