Needles Highway 83 Rezoning RR-5 to RR-2.5
Rezone from RR-5 to RR-2.5 to support a proposed subdivision.
- Location
- 17675 HIGHWAY 83, 80908
- Jurisdiction
- El Paso County
- Applicant
- Vertex Consulting Services, LLC Nina Ruiz
- Land owner (assessor)
- NORTH RANCH LLC
- County project manager
- Joe Letke
- Filed
- Feb 9, 2026
- Parcel
- 6100000369
- Map
-
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
- Area map
- See all Tri-Lakes projects on the map
- Source record
- El Paso County EDARP file
Documents (15)
Neighbor Notice & Vicinity MapadditionalJun 16, 2026
Notice of Application letters were mailed to surrounding property owners on 06/16/2026. JM
Mailing LabelsadditionalJun 16, 2026
Mailing Labels for the 36 surrounding property owners that received notices. Cost = $26.64. JM
Timeline
- Aug 11, 2026Request for Review Comments returned by EPC DPW Development Services - Engineering
- Aug 5, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Victoria Poulton on behalf of Colorado Parks and Wildlife
- Aug 5, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Travis Sauder on behalf of Colorado Parks and Wildlife
- Aug 5, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Tim Kroening on behalf of Colorado Parks and Wildlife
- Aug 5, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Karen Voltura on behalf of Colorado Parks and Wildlife
- Aug 5, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Peter Chapman on behalf of Colorado Parks and Wildlife
- Aug 5, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
- Aug 5, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Aug 5, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Aug 5, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Justin Kilgore on behalf of PCD Project Manager
- Aug 5, 2026Submission Triaged
- Aug 5, 2026Submission received from Applicant
- Aug 4, 2026Submission request sent to Applicant
- Aug 4, 2026Request for Review Comments returned by PCD Project Manager
- Aug 4, 2026Request for Review Comments returned by EPC DPW Development Services - Engineering
- Jul 22, 2026Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
- Jul 14, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
- Jul 14, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
- Jul 14, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
- Jul 14, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
- Jul 14, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Jul 14, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Jul 14, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Justin Kilgore on behalf of PCD Project Manager
- Jul 14, 2026Submission Triaged
- Jul 14, 2026Submission received from Applicant
- Jul 2, 2026Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
- Jun 30, 2026Submission request sent to Applicant
- Jun 30, 2026Request for Review Comments returned by PCD Project Manager
- Jun 30, 2026Request for Review Comments returned by EPC DPW Development Services - Engineering
- Jun 26, 2026Request for Review Comments returned by EPC Environmental Services
- Jun 22, 2026Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
- Jun 18, 2026Request for Review Comments returned by EPC DPW Stormwater
- Jun 16, 2026Request for Review Comments returned by PCD Administrative Notice
- Jun 16, 2026Request for Review Comments returned by Pikes Peak Regional Building Department
- Jun 10, 2026Request for Review Comments returned by EPC Parks Department
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Zachary Jannusch on behalf of EPC DPW Stormwater
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Mikayla Hartford on behalf of EPC DPW Stormwater
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Glenn Reese on behalf of EPC DPW Stormwater
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Erica Rylander on behalf of EPC DPW Stormwater
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Christina Prete on behalf of EPC DPW Stormwater
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by on behalf of PCD Administrative Notice
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by on behalf of Pikes Peak Regional Building Department
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Scott Benson on behalf of Tri-Lakes-Monument Fire Protection District
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Aaron Wood on behalf of Tri-Lakes-Monument Fire Protection District
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by on behalf of EPC Parks Department
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Catherine McGarvy on behalf of EPC Health Department
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by HEAEH LandUse on behalf of EPC Health Department
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Kathy Andrew on behalf of EPC Environmental Services
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by Justin Kilgore on behalf of PCD Project Manager
- Jun 9, 2026Request for Review Comments email sent for Project Needles Highway 83 Rezoning RR-5 to RR-2.5 for review by on behalf of PCD Administrative Notice
- Jun 8, 2026Project Manager Assigned: Joe Letke
- Jun 8, 2026Fees paid: 6/8/2026 (Receipt: 1012138)
- Jun 4, 2026File # Assigned: P268
- Jun 4, 2026Payment Request sent: 6/4/2026
- Jun 4, 2026Submission Triaged
- Jun 3, 2026Submission received from Applicant
- Feb 11, 2026Submission request sent to Applicant
- Feb 9, 2026Project Created
- Feb 9, 2026EA Assigned: EA2616