Retreat at TimberRidge Fil No. 3
33 single-family detached lots total; 30 to be served by Central water & sewer, 6 lots to be served by Well and OWTS; 6 tracts and public ROW. 6 rural lots and 27 urban lots. 3 of the rural lots are on central water and the other three are on well.
- Jurisdiction
- El Paso County
- Applicant
- Classic Homes Construction Austin Lenz
- County project manager
- Charlene Durham
- Filed
- Aug 19, 2024
- Parcels
- 5221400001, 5227200006, 5227200007, 5227200008, 5228000039
- Map
-
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
- Source record
- El Paso County EDARP file
Documents (5)
Agency review comments (11)
PCD Engineering Divisionreview 5Apr 4, 2025
DPW Engineering review comments have been addressed on the following document and will be sent to the Engineering Manager for signature:
- Pavement Report #3
Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
PCD Engineering Divisionreview 4Mar 21, 2025
DPW Engineering review has comments on the following document
- Pavement Report #3
Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
PCD Engineering Divisionreview 3Feb 7, 2025
DPW Engineering review of Arroyo Lane pavement report and deviation request have no comments.
Documents will be routed for signature of Engineering Manager.
Review by
Bret Dilts, PE
bretdilts@elpasoco.com
719-520-6864
PCD Engineering Divisionreview 2Sep 30, 2024
Engineering review 2: Comments have been resolved on the following documents:
- Pavement Report
- Deviation Request
Review comments provided by:
Bret Dilts, PE
BretDilts@elpasoco.com
719-520-6864
PCD Engineering Divisionreview 1Sep 10, 2024
Use of CTS for Paving Season 2024 - updated
PCD Engineering Divisionreview 1Sep 10, 2024
Engineering review 1 has comments on the following documents:
- Pavement Report
- Deviation Request
Additional documents provided by the County:
- 2024 Clarification on CTS
- Memo 2 - ElPasoCTS
- Use of CTS for Paving Season 2024 - updated
Review comments provided by:
Bret Dilts, PE
BretDilts@elpasoco.com
719-520-6864
Elizabeth Nijkamp, PE
ElizabethNijkamp@elpasoco.com
719-520-7852
PCD Engineering Inspectionsreview 1Sep 3, 2024
No Commits from Inspections
Timeline
- Apr 18, 2025Project Ready for Approval requests. Review Comment period is complete.
- Apr 7, 2025Request for Review Comments returned by PCD Engineering Inspections
- Apr 4, 2025Request for Review Comments returned by PCD Engineering Division
- Mar 31, 2025Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Brad Walters on behalf of PCD Engineering Inspections
- Mar 31, 2025Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
- Mar 31, 2025Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
- Mar 31, 2025Submission Triaged
- Mar 28, 2025Submission received from Applicant
- Mar 24, 2025Submission request sent to Applicant
- Mar 21, 2025Request for Review Comments returned by PCD Engineering Division
- Mar 17, 2025Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
- Mar 17, 2025Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
- Mar 17, 2025Submission Triaged
- Mar 13, 2025Submission received from Applicant
- Mar 12, 2025Submission request sent to Applicant
- Mar 12, 2025Project reopened for Review Comments
- Mar 6, 2025Submission request sent to Applicant
- Feb 25, 2025Project Approved: 2/25/2025
- Feb 25, 2025Project Closed
- Feb 24, 2025Project Ready for Approval requests. Review Comment period is complete.
- Feb 7, 2025Request for Review Comments returned by PCD Engineering Division
- Feb 6, 2025Project reopened for Review Comments
- Feb 4, 2025Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
- Feb 4, 2025Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
- Feb 4, 2025Submission Triaged
- Feb 3, 2025Submission received from Applicant
- Feb 3, 2025Submission request sent to Applicant
- Dec 5, 2024Project Closed
- Dec 5, 2024Project Approved: 12/5/2024
- Dec 4, 2024Project Manager Assigned: Charlene Durham
- Sep 30, 2024Request for Review Comments returned by PCD Engineering Division
- Sep 19, 2024Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
- Sep 19, 2024Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
- Sep 19, 2024Submission Triaged
- Sep 18, 2024Submission received from Applicant
- Sep 10, 2024Submission request sent to Applicant
- Sep 10, 2024Request for Review Comments returned by PCD Engineering Division
- Sep 3, 2024Request for Review Comments returned by PCD Engineering Inspections
- Sep 3, 2024Submission Triaged
- Aug 30, 2024Submission received from Applicant
- Aug 27, 2024Submission request sent to Applicant
- Aug 21, 2024Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Brad Walters on behalf of PCD Engineering Inspections
- Aug 21, 2024Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Gilbert LaForce on behalf of PCD Engineering Division
- Aug 21, 2024Request for Review Comments email sent for Project Retreat at TimberRidge Fil No. 3 for review by Engineering Manager on behalf of PCD Engineering Division
- Aug 21, 2024Submission Triaged
- Aug 19, 2024Submission received from Applicant
- Aug 19, 2024Submission request sent to Applicant
- Aug 19, 2024Set Applicant to Classic Homes Construction
- Aug 19, 2024File # Assigned: PAV2412
- Aug 19, 2024No Fees
- Aug 19, 2024Project Created. Parent Project: Retreat at TimberRidge Fil No. 3 (SF2241)
- Aug 19, 2024Project Manager Assigned: Brad Walters