Sterling Ranch East Fil 8 Subdivision

Final plat SF2526 Active

304 single-family detached lots, ROW, detention ponds, lift station. ; PUD Amendment concurrently requested or may be approved by the time of submittal

Jurisdiction
El Paso County
Applicant
N.E.S. Inc. Andrea Barlow
Land owner (assessor)
CLASSIC SRJ LAND LLC (state record)
County project manager
Kari Parsons
Filed
Sep 2, 2025
Parcel
5233000021
Map
Parcel boundaries: Colorado public parcel data · Basemap © OpenStreetMap contributors
Area map
See all Tri-Lakes projects on the map
Source record
El Paso County EDARP file

Documents (49)

Plat ResponsesreviewJan 27, 2026
Final Plat DrawingsreviewJan 27, 2026
License AgreementreviewJan 26, 2026
OFF site Pond CDsreviewJan 26, 2026
FDR ResponsesreviewJan 26, 2026
CD ResponsesreviewJan 26, 2026
Drainage Report - FinalreviewJan 26, 2026
Letter of IntentreviewJan 23, 2026
Plat ResponsesreviewDec 4, 2025
FDR ResponsesreviewDec 4, 2025
CD ResponsesreviewDec 4, 2025
Utility PlansreviewDec 3, 2025
Application/Petition FormreviewNov 6, 2025
Traffic Impact StudyreviewNov 6, 2025
Closures Sheet (Survey)reviewNov 4, 2025
PCM Applicability FormreviewSep 9, 2025
Fire Protection ReportreviewSep 9, 2025
Soils & Geology ReportreviewSep 9, 2025
water reportreviewSep 5, 2025
wastewater reportreviewSep 5, 2025
Landscape Plan drawingsreviewSep 2, 2025
Noise StudyreviewSep 2, 2025
Natural Features ReportreviewSep 2, 2025
returned noticeadditionalMar 24, 2026
3/23/26

Agency review comments (58)

Comments returned by referral agencies during review, from the county's public EDARP file. Some agencies attach a letter instead of (or alongside) written comments.

Black Hills Energy-Aquilareview 3Feb 19, 2026
This is a BHE certificated area. Please contact me at marcus.henderson@blackhillsenrergy.com
PCD Project Managerreview 3Feb 10, 2026
Please address comments and sign.
PCD Project Managerreview 3Feb 10, 2026
FAE version 3 comments
View attached comment letter
PCD Project Managerreview 3Feb 10, 2026
Drainage comments 3
View attached comment letter
PCD Project Managerreview 3Feb 10, 2026
CD comments 3
View attached comment letter
EPC DPW Stormwaterreview 3Feb 10, 2026
Review 3: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) to be uploaded by the DS Engr: - CDs - Drainage Report Document that still needs to be revised and resubmitted that was not resubmitted with this review cycle: - PCM Applicability Form - revise per my V1 comments and add notes to page 3 that explain that Pond FSD-16 docs will be submitted with SRE F6. A revised PCM Applicability Form was not uploaded with V2 or V3. Please revise and resubmit. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
EPC DPW Development Services - Engineeringreview 3Feb 5, 2026
DPW Engineering review 3 has minor comments on the following documents - CDs - FAE Reviewed by: Charlene Durham, PE charlenedurham@elpasoco.com
County Attorney - Waterreview 3Feb 4, 2026
Water supply was reviewed in connection with the PUDSP application (PUDSP 256).
County Attorney - Development Reviewreview 3Jan 29, 2026
My signature to Maintenance Agreement attached. Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com
View attached comment letter
County Attorney - Development Reviewreview 3Jan 29, 2026
My signature to SIA attached. Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com
View attached comment letter
County Attorney - Development Reviewreview 3Jan 29, 2026
My signature to ROW License Agreement attached. Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com
View attached comment letter
PCD Project Managerreview 2Jan 5, 2026
CD Comments V2
View attached comment letter
PCD Project Managerreview 2Jan 5, 2026
Drainage Report comments V2
View attached comment letter
EPC DPW Development Services - Engineeringreview 2Dec 22, 2025
SF2526: Foursquare at Sterling Ranch SF Amendment (Sterling Ranch East Filing 8) DPW Review 2 Engineering Comments have been provided on the following documents (to be uploaded by Project Manager): V2- Drainage Report V2- CDs Applicant Notes: I am requesting a response letter with your next submittal explaining how each comment was addressed (please copy and paste all comments to your response letter and respond below each comment). Please do not use the words done, fixed, etc. instead explain how you addressed each comment and indicate the sheet number where each comment was addressed. Please email me at the email address indicated below, a request for a TEAM’S RCR “Review Comment Resolution” meeting prior to resubmittal to make sure all comments are addressed, so we can move this project forward to approval. Please address the attached Bluebeam comments. Please acknowledge the following two notes from the meeting held on 12/18/25 and provide just a documentation that these items/tasks are/will be completed: 1. Include the Wall Plans and the detail plans in the G&E Plans and the Building Plans (NOT the SF/Plat Plans). 2. Filing 8: The “Pond Plans” (CD Plans for the pond) must be OFFSITE Plans to Filing 8 (and the Pond will be Plated with Filing 6). Please address the following comment on the V2FAE; the following item “Guide/Street Name Sign” doesn’t have a unit cost, please add the unit cost. The applicant must upload the revised items indicated below with his/her resubmittal: - Drainage Report - CDs -FAE PDF -Missing (GE Plans for the site) Reviewed by: Jalal Jalal Saleh, PE jalalsaleh@elpasoco.com Bret Dilts, PE bretdilts@elpasoco.com Charlene Durham, PE charlenedurham@elpasoco.com
County Attorney - Development Reviewreview 2Dec 22, 2025
Review #2: County Attorney comments from 10/7/25 with respect to the DMA, License Agreement and SIA have not yet been addressed. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com
PCD Project Managerreview 2Dec 18, 2025
Letter of Intent- Planning Only Comments
View attached comment letter
PCD Project Managerreview 2Dec 18, 2025
Final Plat Planning Only Comments
View attached comment letter
PCD Project Managerreview 2Dec 18, 2025
Planning Staff is uploading planning-only comments on the LOI and Plat due to the upcoming scheduled time off. Please look to receive full set of redlines on documents; the due date is December 29th. Please note: CAO requires applicants to sign, and finalize contracts with attachments in PDF format prior o CAO signature. Applicant should address all comments finalized and upload to EDARP for signature on all contracts (SIA, DMA, License agreement etc)
EPC DPW Stormwaterreview 2Dec 15, 2025
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following document(s) to be uploaded by the Planner or DS Engr: - CDs - Drainage Report Docs that still need to be revised and resubmitted that were not resubmitted for this review cycle: - FAE Form - update to review Permanent Pond costs - PCM Applicability Form - revise per my V1 comments and add notes to page 3 that explain that Pond FSD-16 docs will be submitted with SRE F6. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
Parks Advisory Boardreview 2Dec 12, 2025
El Paso County Parks Department, Final Comments, 5th Submittal - Please See Attached Documentation for Revised Comments and Recommendations (Originally endorsed by the El Paso County Park Advisory Board on January 11, 2023)
View attached comment letter
EPC Parks Departmentreview 2Dec 12, 2025
El Paso County Parks Department, Final Comments, 5th Submittal - Please See Attached Documentation for Revised Comments and Recommendations (Originally endorsed by the El Paso County Park Advisory Board on January 11, 2023)
View attached comment letter
Pikes Peak Regional Building Departmentreview 2Dec 11, 2025
1. Readdressing fee still applies. 2. Contact me directly when you are ready to have the remaining area addressed. 3. Standard Final Plat comments still apply. Plat fees are for 154 lots & 10 tracts, (two addresses per lot and tract) total due at time of the review of the mylar $ 1,660.00 Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org
911 Authority - El Paso/Teller Countyreview 2Dec 10, 2025
Streetnames previously approved. No action for E911 on this submittal. Thank you. Justin
Colorado Division of Water Resourcesreview 1Oct 24, 2025
View attached comment letter
EPC Health Departmentreview 1Oct 17, 2025
View attached comment letter
Colorado Parks and Wildlifereview 1Oct 10, 2025
Colorado Parks and Wildlife (CPW) has reviewed the plans for the Sterling Ranch East Fil 8 Subdivision in El Paso County. Colorado Parks and Wildlife (CPW) is familiar with the site and has commented on the overall Sterling Ranch project area. Therefore, CPW would defer to those previous comments. CPW anticipates that this project's impacts on the wildlife resource would be negligible if our previous comments are taken into consideration. We appreciate being allowed to comment. Please feel free to contact District Wildlife Manager, Aaron Berscheid, should you have any questions or require additional information at 719-439-9601 or via email at aaron.berscheid@state.co.us
EPC DPW Stormwaterreview 1Oct 9, 2025
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - CDs - Drainage Report - ESQCP - GEC Checklist - PCM Applicability Form Other docs uploaded with Development Services' comments: - FAE Please provide the following document(s) upon resubmittal (the planner will need to send an upload request): - PCM - MHFD Detention Calcs or SDI Form - PCM - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal) Revise and resubmit PCM Maintenance Agreement per COA comments. None of the template's blanks were filled in, so there was nothing for me to review. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com
EPC DPW Stormwaterreview 1Oct 9, 2025
FAE
View attached comment letter
EPC DPW Stormwaterreview 1Oct 9, 2025
PCM Applicability Form
View attached comment letter
EPC DPW Stormwaterreview 1Oct 9, 2025
GEC Checklist
View attached comment letter
EPC DPW Stormwaterreview 1Oct 9, 2025
ESQCP
View attached comment letter
EPC DPW Stormwaterreview 1Oct 9, 2025
Drainage Report
View attached comment letter
EPC DPW Stormwaterreview 1Oct 9, 2025
CDs
View attached comment letter
EPC DPW Development Services - Engineeringreview 1Oct 9, 2025
DPW Engineering review 1 has comments on the following documents - Drainage Report - CDs - Soils and Geology Report (see comments on the uploaded document in PUDSP256) - FAE - Traffic Impact Study (see comments on the uploaded document in PUDSP256) - Plat Additional comments and review may be required as PUDSP256 is modified. Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 Jalal Saleh, PE jalalsaleh@elpasoco.com Charlene Durham, PE charlenedurham@elpasoco.com
EPC DPW Development Services - Engineeringreview 1Oct 9, 2025
Plat Engineering comments
View attached comment letter
PCD Project Managerreview 1Oct 9, 2025
Planning only FAE comments
View attached comment letter
PCD Project Managerreview 1Oct 9, 2025
Final Plat preliminary comments. Plat will change post meeting.
View attached comment letter
PCD Project Managerreview 1Oct 9, 2025
Preliminary comments on LOI- meeting requested.
View attached comment letter
PCD Project Managerreview 1Oct 9, 2025
Comment meeting requested. Please address comments on PUDSP which will change this plat. Lets discuss both PUDSP and SF Tuesday at our meeting
Upper Black Squirrel Creek GWMDreview 1Oct 8, 2025
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on future submittals.
Black Forest Fire Protection Districtreview 1Oct 7, 2025
BFFRPD (Black Forest Fire Rescue Protection District) has reviewed the proposed project. With this project being served by central municipal water system our recommendation is that it must meet and comply with EL Paso County standards, IBC 2021 and IFC 2021 standards. The fire flow required must meet El Paso County’s adopted Land Development Code (LDC), Engineering Criteria Manual (ECM), adopted International Fire Code (IFC), and all other adopted codes, provisions, or statutes that impact fire safety to include access/egress, water supply, hardening of structures, addressing, fire protection systems, etc. The County is the authority having jurisdiction, BFFRPD does not support any variances from the codes. Be advised that BFFRPD does not maintain or test fire hydrants. The metro district or water district are responsible for the maintenance.
County Attorney - Waterreview 1Oct 7, 2025
Water supply will be reviewed with the PUDSP application (PUDSP 256). Lori Seago Sr. County Attorney loriseago@elpasoco.com
EPC Fire and Wildfire Program Managerreview 1Oct 7, 2025
Per Land Development Code 6.3.3 C c (i) the fire flow at 20 psi shall be provided. What is the required fire flow for the structures to be built and what is the fire flow provided from the system at 20 psi? Release of financial assurances for water system improvements to be approved after demonstrate by testing that the capacity of the water supply system will meet fire protection design requirements by a qualified professional. Roland Peterson Fire Safety and Wildfire Mitigation Program Manager Planning & Community Development 719.520.6075 rolandpeterson@elpasoco.com
County Attorney - Development Reviewreview 1Oct 7, 2025
With respect to Detention Maintenance Agreement – please fill out highlighted portions of the document. No comments from County Attorney- Development Review with respect to HOA Bylaws and Declaration of Covenants at this time. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
County Attorney - Development Reviewreview 1Oct 7, 2025
Regarding License Agreement – please see attached edits, accept track changes and resubmit for signature. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
View attached comment letter
County Attorney - Development Reviewreview 1Oct 7, 2025
Regarding SIA, please see attached edits. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com.
View attached comment letter
Colorado Geological Surveyreview 1Oct 7, 2025
Entech Engineering’s soils and geology report (Entech Engineering, Job No. 220572, August 27, 2025) makes appropriate preliminary recommendations for mitigating the site’s hazards. We offer the following comments and recommendations. 1. In the test borings drilled for Entech’s study, groundwater was encountered at 7 and 14.5 feet below grade during drilling, and Entech observed standing water to the south of the site at the northwest corner of future Briargate Parkway and Sterling Ranch Road. Entech states (page 4), “The proposed housing will have crawlspaces.” Additionally, the PUD development plan (Classic Consulting, July 17, 2025) states, “No basements are proposed within this subdivision.” CGS recommends adding a note to the final plat stating that no basements are permitted in the Sterling Ranch East Fil 8 development, similar to other Sterling Ranch developments. Reviewed on 10/7/2025 by Amy Crandall, Engineering Geologist (acrandall@mines.edu, 303-384-2632)
Mountain View Electric Association, Inc.review 1Oct 7, 2025
See attached comment letter.
View attached comment letter
Road Impact Fee Administratorreview 1Sep 30, 2025
victoriachavez@elpasoco.com At this time, I do not see any credit agreements that require processing. If this changes, please contact me.
EPC Environmental Servicesreview 1Sep 29, 2025
View attached comment letter
Colorado Springs Planning & Community Developmentreview 1Sep 29, 2025
City Planning has no comment.
Colorado Springs Utilities, Dev, Svc.(includes water resources)review 1Sep 24, 2025
Please include CSU's Terms and Conditions per Rec. No. 224026331.
911 Authority - El Paso/Teller Countyreview 1Sep 22, 2025
Streetnames previously approved. No action for E911 on this submittal. Thank you. Justin
Academy SD 20 Building Fundreview 1Sep 22, 2025
Academy District 20 is in receipt of File #SF2526 for approval of the Foursquare at Sterling Ranch AKA (Sterling Ranch East Fil 8). Academy District 20 is requesting land dedication in lieu of fees for all residential units within the Sterling Ranch development per the approved agreement between the District, El Paso County, SR Land, LLC and Classic SRJ Land, LLC. The District is experiencing ongoing residential development. The District gained approximately 12,000 new residential units between 2018 and 2024 which included 5,278 Single Family, 1,156 Single Family Attached, and 5,576 Apartments as reported to the District by local developers. During that same timeframe, the District only experienced a total membership increase of 138 students. This information is updated annually in October A drop in the birth rate plus the significant increase in the cost of housing has slowed student growth in the District. The District is able to serve each student who is a resident of District 20. If you need additional information, please contact me. Don Smith Planning Consultant
Parks Advisory Boardreview 1Sep 19, 2025
El Paso County Parks Department, Final Comments, 4th Submittal - Please See Attached Documents for Additional Comments and Revised Development Application Review Form and Recommended Motion (Originally endorsed by the El Paso County Park Advisory Board on 01/11/2023)
View attached comment letter
EPC Parks Departmentreview 1Sep 19, 2025
El Paso County Parks Department, Final Comments, 4th Submittal - Please See Attached Documents for Additional Comments and Revised Development Application Review Form and Recommended Motion (Originally endorsed by the El Paso County Park Advisory Board on 01/11/2023)
View attached comment letter
Pikes Peak Regional Building Departmentreview 1Sep 18, 2025
1. Where the addressing markers are shown should be the front door. If it is not, please move them so that addressing can be assigned correctly. 2. Is tract D around lots 67-77? I am not finding tract D. 3. Can you show me filing no.4 to the north, not finding this on the overall map. 4. Standard plat comments: New plat fee’s will be provided once I know where tract D is. a. Enumerations will review the pre-plat (mylar) prior to plat for address placement, street names, and title block. b. A $10.00 per lot and tract platting fee will be due at the time of the review of the pre-plat, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. As of December 5th 2023, the fee for all credit/debit cards has changed from the flat 2.95% fee to the following: Over the phone Credit/Debit Card payments will be 2.3% and In-Person Debit Card payments will be 1.5% (in-person only). Paid directly to the Enumerations Department. C. Pre-plat reviews can be reviewed via “pdf” or in-person. The pre-plat will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations stamping the pre-plat and receiving payment of plat fees. If any pre-plat changes occur, even if changes do not apply to Enumerations, we still need to re-stamp the pre-plat. The Enumerations stamped pre-plat copy should match the recorded document minus a few signatures. If you would like an in-person review, please make an appointment on our website, https://www.pprbd.org/Home/BookAppt d. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Please email the Enumerations staff member that reviewed your project. Amy@pprbd.org; Brent@pprbd.org; or BeckyA@pprbd.org Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org
Colorado Department of Transportation - Pueblo Officereview 1Sep 18, 2025
CDOT has no comments or concerns

Timeline